100%construction reportedQ4 2025 filing
78units not bookedof 213 · Q4 2025 filing
27 Jun 2025declared completionK-RERA registration · read 20 Sep 2026

The record · free to read

Registration read 20 Sep 2026

Progress & dates

The timeline on file.

Promoter-reported construction

K-RERA quarterly filings · Q3 2025 to Q4 2025

declared completion

27 Jun 2025

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

K-RERA registration · read 20 Sep 2026

Inventory & scale

What this registration contains.

213
213

Filed categories, unchanged · K-RERA registration · read 20 Sep 2026

The whole registration

16.9registered acres

12.6registered units per acre

The average covers the registered land and all registered unit types. It does not describe the space, outlook or surroundings of an individual home.

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

K-RERA · PRM/KA/RERA/1251/308/PR/200211/003281

This project, on the record

The comparable facts of this project, from its own RERA registration record. Each context percentile names its exact comparison set, drawn from Quietlist’s full register store. The paid report adds drawing-read rows to this same table — what the filed plans show about the site, its edges and the unit layouts.

On the register

Declared completion27 June 2025
Land area68,442 sq m (16.9 acres)
Homes registered213
Tower/wing entries1
Unit mix213 × 213

In context

Density12.6 homes per acre
Density in context4th percentile of 471 Anekal projects (median 75.8)

Values as crawled from the official K-RERA record; context percentiles name their comparison population.

Official Registry Facts

Official project scale

RERA filing

Registration-form facts from the K-RERA detail page: use these to sanity-check the builder brochure, parking allotment, and sanctioned-plan references before relying on plan-extracted approximations.

DisclosureOfficial valueWhy it matters
Registered units213Total inventory registered with K-RERA.
Official carpet area41,989 sqmRegulator-disclosed project-level carpet area, not vision-derived room sums.
Registered land area68,442 sqmThe land area attached to this K-RERA registration.
Sanctioned FAR/FSI1.5Higher FAR generally means a denser vertical build, subject to site layout and open-space design.
Registered tower/wing entries1Official tower/wing count in the K-RERA detail page.
Parking total (reconciled)312Separate filed counts; these categories may overlap and are not added together.
Open-parking field0Separate filed counts; these categories may overlap and are not added together.
Garage field0Separate filed counts; these categories may overlap and are not added together.
Project start date03-01-2020

Official inventory & towers

RERA filing

K-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.

Registered inventory mix

TypeUnitsShareOfficial carpet area
213213100%41,989 sqm

Registered tower / wing summary

Tower/wingFloorsUnitsParkingHeight
JRC PALLADIO2213312-

Official unit register

RERA filing

K-RERA detail-page flat rows: exact unit numbers, official carpet area, UDS, and parking lots. 213 official flat/unit rows, matching the 213 registered units disclosed above. Use this as a checklist against the specific flat number in your cost sheet and draft agreement.

By unit type

Unit typeRowsCarpet areaUDSParking lots
4BHK121205.8-269.0 sqm162.0-216.0 sqm242
3BHK70139.7-141.2 sqm135.0 sqm70
ODD22--0

By tower / wing

Tower/wingRowsCarpet areaUDSParking lots
JRC PALLADIO213139.7-269.0 sqm135.0-216.0 sqm312
Show sample official unit rows
UnitTowerFloorTypeCarpetUDSParking
1JRC PALLADIO0ODD---
2JRC PALLADIO03BHK141.2 sqm135.0 sqm1
3JRC PALLADIO03BHK141.2 sqm135.0 sqm1
4JRC PALLADIO03BHK141.2 sqm135.0 sqm1
5JRC PALLADIO03BHK141.2 sqm135.0 sqm1
6JRC PALLADIO03BHK141.2 sqm135.0 sqm1

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

No litigation declared on this project's K-RERA filing.

All 21 standard compliance document slots have usable uploaded filings.

No completion certificate (OC) on file yet — project has not been declared complete.

⚠ Registration validity has lapsed: originally due 27 Jun 2025, extended (Covid Extension) to 27 Mar 2026 — both dates have passed with no OC on file.

Named utility/regulatory approvals

Electricity (BESCOM/ESCOM)✓ On file (BESCOM)
Water & sewage (BWSSB/KWSSB)✓ On file (BWSSB)
Fire NOCNot found in catalog
Pollution control (KSPCB)✓ On file (KSPCB)
Environmental clearanceNot found in catalog
Airport Authority height clearance✓ On file (Airport Authority of India)

"Not found in catalog" can mean the approval genuinely isn't on file yet, or that it doesn't apply to this project (K-RERA doesn't tell us which). Ask the builder directly for any marked not found before relying on it.

Statutory approval status

RERA filing

10 further authority slots are marked not applicable by the regulator.

Authority / NOCStatusDateFile

Project team & certifications

RERA filing

K-RERA names 2 project professional/vendor rows across Architect, Contractor. Use this to cross-check whose certificates, drawings, and contractor commitments support the filing; final reliance still belongs with your lawyer/technical reviewer.

RoleNameRegistration / licenceSinceLocality
ArchitectDSK ARCHITECTS-20079th Main, Jayanagar 2nd block
ContractorCIVITECH DESIGNS-20084th Block, koramangala

Builder track record

RERA filing

Jrc Projects has 7 other K-RERA-registered projects in our records (average reported construction progress 82%). 3 are past their declared completion deadline with no completion certificate recorded — but because K-RERA publishes OCs inconsistently, a project that has actually been finished and handed over still shows up this way, so this overstates real delays, especially for a high-volume established builder. That is a lower delayed rate than the K-RERA average across Bengaluru on the same measure.

Read this as a list to spot-check for a pattern of genuinely stalled projects, not as a delay rate — pull up a few of the builder’s other K-RERA registrations and check whether they’ve actually been delivered.

Financials & Construction Progress

Financial disclosures

RERA filing

Latest quarterly filing (2025-Q4): ₹218.59 Cr collected from buyers, ₹204.23 Cr withdrawn from the project's escrow account.

Construction progress100% → 100% (+0 pts)
Units sold/booked as registered135/213 (63%)
Buyer collections in available QPRs₹437.19 Cr
Escrow withdrawals in available QPRs₹408.46 Cr (0.93x collections)

QPR figures are developer-filed quarterly disclosures. Collections and withdrawals are not a project valuation; they are a sanity check for whether sales, construction progress, and escrow draws appear directionally aligned.

Declared construction cost ÷ registered units averages to ₹68.1 lakhs per unit — the developer's own declared construction/development cost, not a sale price. K-RERA filings don't disclose what the builder is charging, so this can't tell you whether you're getting a fair deal — only you comparing your quoted price against comparable listings nearby can answer that.

RERA 70% project account is on file: Axis Bank SARJAPUR ROAD (IFSC UTIB0001888, a/c …0578). RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Location & Connectivity

The nearest major job hub is ~12 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
Electronic City12 km
Bellandur–Marathahalli belt15 km
Whitefield IT hub16 km
MG Road / city centre24 km
Outer Ring Road / Manyata29 km
Kempegowda Int'l Airport41 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Jrc Projects. View Jrc Projects's full track record →
Jrc Projects has 8 projects registered in Bangalore, 2 completed.

Other projects by this builder in Bangalore

JRC Sanzio
Filing overdue · 100% built · 92% sold
JRC Wild Woods Phase III
Filing overdue · 65% built · 6% sold
JRC Wild Woods Building 2
No filings

Other RERA-registered projects in Sarjapura

Major developers building in Sarjapura

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.

Own a unit in JRC Palladio?

Sell directly to Quietlist's pre-screened buyer list — flat fee, no broker commission.

List your unit →

Last checked against the RERA register: 20 Sep 2026