RAJA RITZ AVENUE - PHASE II

Bengaluru East · RAJA HOUSING

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Dec 2021declared completionK-RERA registration · read 20 Sep 2026
210registered unitsK-RERA registration · read 20 Sep 2026

The record · free to read

Registration read 20 Sep 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2021

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

K-RERA registration · read 20 Sep 2026

Inventory & scale

What this registration contains.

1 BHK, 2 BHK, 3HK
210

Filed categories, unchanged · K-RERA registration · read 20 Sep 2026

The whole registration

3.1registered acres

66.8registered units per acre

The average covers the registered land and all registered unit types. It does not describe the space, outlook or surroundings of an individual home.

From another project · Prestige Park Grove

A larger advertised area. Almost the same carpet area.

In Tower 14, E4 has 141 sq ft more saleable area than E2. Its carpet area is only 0.46 sq m larger. The report puts the two layouts side by side.

This illustrates the report format. These findings concern the named sample, not this project.

Read the sample report ↗
Prestige Park Grove · Tower 14 comparison · approved sample report
Prestige Park Grove · Tower 14 comparison · approved sample report

The source record

The details behind the headline.

K-RERA · PRM/KA/RERA/1251/446/PR/180524/001816

This project, on the record

The comparable facts of this project, from its own RERA registration record. Each context percentile names its exact comparison set, drawn from Quietlist’s full register store. The paid report adds drawing-read rows to this same table — what the filed plans show about the site, its edges and the unit layouts.

On the register

Declared completion31 December 2021
Land area12,716 sq m (3.1 acres)
Homes registered210
Tower/wing entries4
Unit mix210 × 1 BHK, 2 BHK, 3HK

In context

Density66.8 homes per acre
Density in context36th percentile of 1119 Bengaluru East projects (median 75.5)

Values as crawled from the official K-RERA record; context percentiles name their comparison population.

Official Registry Facts

Official project scale

RERA filing

Registration-form facts from the K-RERA detail page: use these to sanity-check the builder brochure, parking allotment, and sanctioned-plan references before relying on plan-extracted approximations.

DisclosureOfficial valueWhy it matters
Registered units210Total inventory registered with K-RERA.
Official carpet area16,260 sqmRegulator-disclosed project-level carpet area, not vision-derived room sums.
Registered land area12,716 sqmThe land area attached to this K-RERA registration.
Sanctioned FAR/FSI2Higher FAR generally means a denser vertical build, subject to site layout and open-space design.
Registered tower/wing entries4Official tower/wing count in the K-RERA detail page.
Parking total (reconciled)924Separate filed counts; these categories may overlap and are not added together.
Open-parking field0Separate filed counts; these categories may overlap and are not added together.
Garage field0Separate filed counts; these categories may overlap and are not added together.
Project start date18-05-2018

Official inventory & towers

RERA filing

K-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.

Registered inventory mix

TypeUnitsShareOfficial carpet area
1 BHK, 2 BHK, 3HK210100%16,260 sqm

Registered tower / wing summary

Tower/wingFloorsUnitsParkingHeight
Block 1430231-
Block 2470231-
Block 3460231-
Block 4450231-

Official unit register

RERA filing

K-RERA detail-page flat rows: exact unit numbers, official carpet area, UDS, and parking lots. 210 official flat/unit rows, matching the 210 registered units disclosed above. Use this as a checklist against the specific flat number in your cost sheet and draft agreement.

By unit type

Unit typeRowsCarpet areaUDSParking lots
2BHK111743.6-1,005.0 sqft290,850.0 sqft111
3BHK65745.0-1,142.3 sqft290,850.0 sqft65
1BHK34466.0-841.6 sqft290,850.0 sqft34

By tower / wing

Tower/wingRowsCarpet areaUDSParking lots
Block 270466.0-1,024.1 sqft290,850.0 sqft70
Block 360490.1-1,005.1 sqft290,850.0 sqft60
Block 450474.5-1,004.7 sqft290,850.0 sqft50
Block 130524.8-1,142.3 sqft290,850.0 sqft30
Show sample official unit rows
UnitTowerFloorTypeCarpetUDSParking
1Block 103BHK1,112.3 sqft290,850.0 sqft1
2Block 103BHK1,142.3 sqft290,850.0 sqft1
3Block 101BHK524.8 sqft290,850.0 sqft1
4Block 102BHK849.5 sqft290,850.0 sqft1
5Block 102BHK867.8 sqft290,850.0 sqft1
6Block 102BHK849.5 sqft290,850.0 sqft1

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

No litigation declared on this project's K-RERA filing.

1 of 37 compliance document slots are filed as Not Applicable; the remaining 36 slots have usable uploaded filings.

No completion certificate (OC) on file yet — project has not been declared complete.

⚠ Registration validity has lapsed: originally due 31 Dec 2021, extended (Section 6 Extension) to 30 Sep 2023 — both dates have passed with no OC on file. The extension on file was granted on 29 Mar 2023 (K-RERA extension no. EX/PRM/KA/RERA/1251/446/PR/230329/001816) — it has been used, its deadline has also passed, and no further extension is recorded.

Named utility/regulatory approvals

Electricity (BESCOM/ESCOM)✓ On file (BESCOM)
Water & sewage (BWSSB/KWSSB)✓ On file (BWSSB)
Fire NOC✓ On file (Fire Force Department)
Pollution control (KSPCB)✓ On file (KSPCB)
Environmental clearance✓ On file (SEIAA)
Airport Authority height clearance✓ On file (Airport Authority of India)

"Not found in catalog" can mean the approval genuinely isn't on file yet, or that it doesn't apply to this project (K-RERA doesn't tell us which). Ask the builder directly for any marked not found before relying on it.

K-RERA enforcement record (the regulator's own defaulter list & penalty orders)

⚠ Listed on K-RERA's official DEFAULTER list.

K-RERA complaint orders (12 complaints against a project of this name on K-RERA's orders register)

PartiesRelief soughtDisposalOrder date
Manish Saraswat vs Raja Housing Limited and Raja Dutta,Interest & compensation for delay period from BuilderAUTHORITY30/06/2025
Santanu Kumar Meher vs M/S RAJA HOUSING LIMITED, RAJA DATTA, RAJA SUCHINDRAPass an order and instruct Builder to honour the Sale Agreement and complete the project soon with all promised amenities as per Sale Agreement and pay delay compensation on monthly basisAUTHORITY22/08/2023
Aniket Ashok Vaste vs M/S RAJA HOUSING LIMITED, RAJA DATTA, RAJA SUCHINDRACompensation from builder for delayed delivery.AUTHORITY22/08/2023
Naresh Kumar Gunjalli vs M/S RAJA HOUSING LIMITED, RAJA DATTA, RAJA SUCHINDRAImpose builder to start paying delay compensation as per agreement terms and share ETA for completion. RERA to not grant extension to the builder as he has already breached 9 months of COVID extensionAUTHORITY22/08/2023
Chaya Ramanna Karmore vs RAJA HOUSING LIMITEDDirect the Respondents to come forward for executing the Sale Deed in favour of the Complainants after receiving balance consideration as agreed & pay delay period interest on the monies paid till dayAUTHORITY21/10/2025
Firoj Kumar Meher vs M/S RAJA HOUSING LIMITED, RAJA DATTA, RAJA SUCHINDRARERA needs to pass an order to the builder for giving posession and compensate for the delayAUTHORITY21/08/2023
Puneet Shahapete vs M/S RAJA HOUSING LIMITED & TWO OTHERSImpose builder to start paying delay compensation as per agreement terms and share ETA for completion. RERA to not grant extension to the builder as he has already breached 9months of COVID extensionAUTHORITY12/12/2023
Sumeet Shahapeti vs M/S RAJA HOUSING LIMITED & TWO OTHERSImpose builder to start paying delay compensation as per agreement terms and share ETA for completion. RERA to not grant extension to the builder as he has already breached 9 months of COVID extensionAUTHORITY12/12/2023
Abhisek Kumar & Anupama Verma vs RAJA HOUSING LIMITEDI have taken home loan in order to pay for the flat. Home loan EMI and rent for my current house is a trouble. I expect RERA should not give any further extension to builder and compensate for delay.AUTHORITY07/12/2023
shubhramani mazumdar & IPSHITA DUTTA vs Raja Housing Limited & 2 othersWant the delivery of our unit from the builder on a new commited date. Builder should provide the details of compensation to be paid to the buyers as soon as possible.AUTHORITY06/02/2024
Amit Shirgurkar & Ashwini Shirgurkar vs Raja Housing Limited & 2 othersWe want complete compensation against this delay.AUTHORITY06/02/2024
Ajay Pandurang Adsul & Bhagyashri Ajay Adsul vs Raja Housing Limited & 2 othersI request RERA to help us to get monthly compensation from builder as per the agreementAUTHORITY06/02/2024

⚠ Matched by PROJECT NAME (the orders register carries no registration number) — confirm the respondent above is this project's builder before relying on it.

Complaints on this project's K-RERA page (34 complaints listed against this promoter)

ComplaintSubject (as filed)ProjectStatus
CMP/211111/0008542
11-11-2021
Project delayed and interest not paid by builderRAJA RITZ AVENUE - PHASE 1 (another project by this promoter)DISPOSED AUTHORITY BENCH4
CMP/211210/0008709
10-12-2021
Possession delayed and not paying compensationRAJA RITZ AVENUE - PHASE 1 (another project by this promoter)DISPOSED AUTHORITY BENCH6
CMP/220207/0008977
07-02-2022
Project delayed, builder is not responding and not paying compensation for the delay posessionRAJA RITZ AVENUE - PHASE 1 (another project by this promoter)DISPOSED AUTHORITY BENCH6
CMP/220209/0008994
09-02-2022
Delay in Delivery of Flat and deliberate delay in completion of projectRAJA RITZ AVENUE - PHASE 1 (another project by this promoter)DISPOSED AUTHORITY BENCH6
CMP/220215/0009005
15-02-2022
Possession delayed, not paying compensation and no proper communication from builderRAJA RITZ AVENUE - PHASE 1 (another project by this promoter)DISPOSED AUTHORITY BENCH6
CMP/220215/0009006
15-02-2022
My property is not handed over by RERA pocession dateRAJA RITZ AVENUE - PHASE 1 (another project by this promoter)DISPOSED AUTHORITY BENCH6
CMP/220215/0009014
15-02-2022
Possession delayed and not paying compensationRAJA RITZ AVENUE - PHASE 1 (another project by this promoter)DISPOSED AUTHORITY BENCH6
CMP/220218/0009024
18-02-2022
Rera date expired, possession delayed and compensation not paidRAJA RITZ AVENUE - PHASE 1 (another project by this promoter)DISPOSED AUTHORITY BENCH6

Listed on the project's own K-RERA detail page (registration-exact source). Rows on the promoter's other projects are track-record context — read the subject text, it is the complainant's own filed wording.

Project team & certifications

RERA filing

K-RERA names 3 project professional/vendor rows across Architect, Contractor, Structural engineer. Use this to cross-check whose certificates, drawings, and contractor commitments support the filing; final reliance still belongs with your lawyer/technical reviewer.

RoleNameRegistration / licenceSinceLocality
ArchitectJaglur FF - M/s.Spacemast Architect-1997Vyalikaval, GD Park Extension
ContractorM/s.Umiya Constructions-2009Nobel Residency, Yelanahalli
Structural engineerTharanath - M/s.Rachana Consultants---

Builder track record

RERA filing

Raja Housing has 7 other K-RERA-registered projects in our records (average reported construction progress 52%). 4 are past their declared completion deadline with no completion certificate recorded — but because K-RERA publishes OCs inconsistently, a project that has actually been finished and handed over still shows up this way, so this overstates real delays, especially for a high-volume established builder.

Read this as a list to spot-check for a pattern of genuinely stalled projects, not as a delay rate — pull up a few of the builder’s other K-RERA registrations and check whether they’ve actually been delivered.

Financials & Construction Progress

Financial disclosures

RERA filing

⚠ No quarterly financial disclosures (collections, escrow withdrawals) on record, despite no completion certificate yet — meaning we can't verify the project's cashflows against its construction progress. Worth asking the builder directly why no quarterly filings are available.

Declared construction cost ÷ registered units averages to ₹26.5 lakhs per unit — the developer's own declared construction/development cost, not a sale price. K-RERA filings don't disclose what the builder is charging, so this can't tell you whether you're getting a fair deal — only you comparing your quoted price against comparable listings nearby can answer that.

RERA 70% project account is on file: HDFC RICHMOND ROAD, BANGALORE – 560025 (IFSC HDFC0000523, a/c …3021). RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Construction photo filings

RERA filing

K-RERA has 1 project-photo upload.

These are developer-uploaded progress photos in the official document catalog. We do not treat them as proof of current site condition; use them as a prompt to ask for newer dated photos or a site visit. Individual filings are listed in the document catalog below.

Location & Connectivity

The nearest major job hub is ~4 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Whitefield IT hub4 km
Bellandur–Marathahalli belt7 km
MG Road / city centre12 km
Outer Ring Road / Manyata12 km
Electronic City17 km
Kempegowda Int'l Airport24 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Raja Housing. View Raja Housing's full track record →
Raja Housing has 8 projects registered in Bangalore.

Other projects by this builder in Bangalore

Raja Platino
On track · 50% built · 3% sold
Raja Ritz Avenue - Phase 1
No filings

Other RERA-registered projects in Mahadevapura

Major developers building in Mahadevapura

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.