Bangalore/Project record

K-RERA · the public record

Spectra Parijatha

Bengaluru East · Spectra Constructions

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

65%construction reportedQ1 2026 filing
61units not bookedof 140 · Q1 2026 filing
31 Aug 2028declared completionK-RERA registration · read 20 Sep 2026

The record · free to read

Registration read 20 Sep 2026

Progress & dates

The timeline on file.

Promoter-reported construction

K-RERA quarterly filings · Q3 2025 to Q1 2026

declared completion

31 Aug 2028

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

K-RERA registration · read 20 Sep 2026

Inventory & scale

What this registration contains.

3 BHK
128
2 BHK
12

Filed categories, unchanged · K-RERA registration · read 20 Sep 2026

The whole registration

2.1registered acres

66.3registered units per acre

The average covers the registered land and all registered unit types. It does not describe the space, outlook or surroundings of an individual home.

From another project · Prestige Park Grove

A larger advertised area. Almost the same carpet area.

In Tower 14, E4 has 141 sq ft more saleable area than E2. Its carpet area is only 0.46 sq m larger. The report puts the two layouts side by side.

This illustrates the report format. These findings concern the named sample, not this project.

Read the sample report ↗
Prestige Park Grove · Tower 14 comparison · approved sample report
Prestige Park Grove · Tower 14 comparison · approved sample report

The source record

The details behind the headline.

K-RERA · PRM/KA/RERA/1251/446/PR/251023/006346

This project, on the record

The comparable facts of this project, from its own RERA registration record. Each context percentile names its exact comparison set, drawn from Quietlist’s full register store. The paid report adds drawing-read rows to this same table — what the filed plans show about the site, its edges and the unit layouts.

On the register

Declared completion31 August 2028
Land area8,545 sq m (2.1 acres)
Homes registered140
Tower/wing entries3
Unit mix128 × 3 BHK, 12 × 2 BHK

In context

Density66.3 homes per acre
Density in context35th percentile of 1119 Bengaluru East projects (median 75.5)

Values as crawled from the official K-RERA record; context percentiles name their comparison population.

Official Registry Facts

Official project scale

RERA filing

Registration-form facts from the K-RERA detail page: use these to sanity-check the builder brochure, parking allotment, and sanctioned-plan references before relying on plan-extracted approximations.

DisclosureOfficial valueWhy it matters
Registered units140Total inventory registered with K-RERA.
Official carpet area14,860 sqmRegulator-disclosed project-level carpet area, not vision-derived room sums.
Official built-up area26,266 sqmUseful scale context when comparing density and project cost.
Registered land area8,545 sqmThe land area attached to this K-RERA registration.
Sanctioned FAR/FSI2.25Higher FAR generally means a denser vertical build, subject to site layout and open-space design.
Registered tower/wing entries3Official tower/wing count in the K-RERA detail page.
Parking total (reconciled)140Separate filed counts; these categories may overlap and are not added together.
Covered-parking field179Separate filed counts; these categories may overlap and are not added together.
Open-parking field45Separate filed counts; these categories may overlap and are not added together.
Garage field0Separate filed counts; these categories may overlap and are not added together.
Approved plan numberBBMP /Use this to match the sanctioned drawing set shown by the builder.
Plan approval date31-08-2023
Project start date18-09-2023

Official inventory & towers

RERA filing

K-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.

Registered inventory mix

TypeUnitsShareOfficial carpet area
3 BHK12891%13,810 sqm
2 BHK129%1,050 sqm

Registered tower / wing summary

Tower/wingFloorsUnitsParkingHeight
Tower A14363642.3 m
Tower B14525242.3 m
Tower C14525242.3 m

Official unit register

RERA filing

K-RERA detail-page flat rows: exact unit numbers, official carpet area, UDS, and parking lots. 140 official flat/unit rows, matching the 140 registered units disclosed above. Use this as a checklist against the specific flat number in your cost sheet and draft agreement.

By unit type

Unit typeRowsCarpet areaUDSParking lots
3 BHK128107.2-108.6 sqm51.4-52.0 sqm128
2 BHK1287.5 sqm45.5 sqm12

By tower / wing

Tower/wingRowsCarpet areaUDSParking lots
Tower B52107.2-108.6 sqm51.4-52.0 sqm52
Tower C52107.2-108.6 sqm51.4-52.0 sqm52
Tower A3687.5-108.6 sqm45.5-52.0 sqm36
Show sample official unit rows
UnitTowerFloorTypeCarpetUDSParking
A-202Tower A23 BHK107.2 sqm51.4 sqm1
A-203Tower A23 BHK108.6 sqm52.0 sqm1
A-204Tower A22 BHK87.5 sqm45.5 sqm1
A-302Tower A33 BHK107.2 sqm51.4 sqm1
A-303Tower A33 BHK108.6 sqm52.0 sqm1
A-304Tower A32 BHK87.5 sqm45.5 sqm1

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

No litigation declared on this project's K-RERA filing.

16 of 47 compliance document slots are filed as Not Applicable; the remaining 31 slots have usable uploaded filings.

No completion certificate (OC) on file yet — project has not been declared complete.

Named utility/regulatory approvals

Electricity (BESCOM/ESCOM)✓ On file (ESCOM/Electricity)
Water & sewage (BWSSB/KWSSB)✓ On file (KWSSB/Water)
Fire NOC✓ On file (Fire Force Department)
Pollution control (KSPCB)✓ On file (KSPCB)
Environmental clearance✓ On file (SEIAA)
Airport Authority height clearance✓ On file (Airport Authority of India)

"Not found in catalog" can mean the approval genuinely isn't on file yet, or that it doesn't apply to this project (K-RERA doesn't tell us which). Ask the builder directly for any marked not found before relying on it.

Statutory approval status

RERA filing

Clean approvals profile: every applicable statutory NOC is on file — including Fire NOC, the clearances buyers most often find still pending. Nothing is outstanding among the statutory NOCs — which compliance documents are filed versus still under process is a separate matter, covered in Litigation & compliance above. Note environmental clearance and pollution-control clearance (KSPCB) are not among the approvals K-RERA marks applicable to this project — if the named-approvals check shows them as "not found in catalog", that is why; ask the builder directly whether they apply here. Since these are developer-filed portal statuses, have your lawyer confirm them against the linked NOC copies.

5 further authority slots are marked not applicable by the regulator.

Authority / NOCStatusDateFile
Water supply and sewage boardApproved08-03-2022NOC - BWSSB.pdf
KPTCL- BESCOMApproved27-10-2021NOC - BESCOM.pdf
Fire and SafetyApproved11-03-2022NOC - FIRE.pdf
Airport Authority of IndiaApproved14-09-2021NOC - Airport Authority of India.pdf
BSNL/Telecommunication DepartmentApproved01-09-2021NOC - BSNL.pdf

Project team & certifications

RERA filing

K-RERA names 4 project professional/vendor rows across Chartered accountant, Engineer, Architect, Contractor. Use this to cross-check whose certificates, drawings, and contractor commitments support the filing; final reliance still belongs with your lawyer/technical reviewer.

RoleNameRegistration / licenceSinceLocality
Chartered accountantSaurabh Srivastava0893711980Bengaluru Urban, Karnataka - 560102
EngineerDhruvaraj IyengarBCC / BL - 3.6 / SE - 246 - 2017 - 182016Bengaluru Urban, Karnataka - 560004
ArchitectAnup NaikCA/96/207942011Bengaluru Urban, Karnataka - 560052
ContractorSpectra Constructions Private Limited-1999Bengaluru Urban, Karnataka - 560038

Builder track record

RERA filing

Spectra Constructions has 4 other K-RERA-registered projects in our records (average reported construction progress 51%). 3 are past their declared completion deadline with no completion certificate recorded — but because K-RERA publishes OCs inconsistently, a project that has actually been finished and handed over still shows up this way, so this overstates real delays, especially for a high-volume established builder.

Read this as a list to spot-check for a pattern of genuinely stalled projects, not as a delay rate — pull up a few of the builder’s other K-RERA registrations and check whether they’ve actually been delivered.

Financials & Construction Progress

Financial disclosures

RERA filing

Latest quarterly filing (2026-Q1): ₹10.25 Cr collected from buyers, ₹7.17 Cr withdrawn from the project's escrow account.

Construction progress60% → 65% (+5 pts)
Units sold/booked as registered79/140 (56%)
Buyer collections in available QPRs₹43.55 Cr
Escrow withdrawals in available QPRs₹30.48 Cr (0.70x collections)
  • Construction progress moved from 60% to 65% across the filed QPR window.
  • The builder has drawn 0.70x of buyer collections from escrow (about 70% of the ₹44 Cr collected) — money is largely staying in the regulated escrow account rather than being pulled out ahead of spend, which is the safer direction. A ratio near or above 1.0 would be the one to scrutinise.

QPR figures are developer-filed quarterly disclosures. Collections and withdrawals are not a project valuation; they are a sanity check for whether sales, construction progress, and escrow draws appear directionally aligned.

Declared construction cost ÷ registered units averages to ₹52.2 lakhs per unit — the developer's own declared construction/development cost, not a sale price. K-RERA filings don't disclose what the builder is charging, so this can't tell you whether you're getting a fair deal — only you comparing your quoted price against comparable listings nearby can answer that.

RERA 70% project account is on file: HDFC CMH Road, Indiranagar IFSC Code : HDFC0000184 Pin Code : 560038. RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Location & Connectivity

The nearest major job hub is ~2 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Whitefield IT hub2 km
Bellandur–Marathahalli belt6 km
MG Road / city centre14 km
Electronic City15 km
Outer Ring Road / Manyata15 km
Kempegowda Int'l Airport27 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Spectra Constructions. View Spectra Constructions's full track record →
Spectra Constructions has 5 projects registered in Bangalore.

Other projects by this builder in Bangalore

Spectra Reserve
On track · 51% built · 22% sold

Other RERA-registered projects in Whitefield

Major developers building in Whitefield

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.