Bangalore/Project record

K-RERA · the public record

TVS EMERALD AURALIS

Yelahanka · EMERALD HAVEN RESIDENCES

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

41%construction reportedQ1 2026 filing
5units not bookedof 393 · Q1 2026 filing
30 Jun 2030declared completionK-RERA registration · read 20 Sep 2026

The record · free to read

Registration read 20 Sep 2026

Progress & dates

The timeline on file.

Promoter-reported construction

K-RERA quarterly filings · Q3 2025 to Q1 2026

declared completion

30 Jun 2030

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

K-RERA registration · read 20 Sep 2026

Inventory & scale

What this registration contains.

2 BHK 1T
2
2 BHK 2T
172
3 BHK 2T
121
3 BHK 3T
97
1 BHK
1

Filed categories, unchanged · K-RERA registration · read 20 Sep 2026

The whole registration

3.7registered acres

105.9registered units per acre

The average covers the registered land and all registered unit types. It does not describe the space, outlook or surroundings of an individual home.

From another project · Prestige Park Grove

A larger advertised area. Almost the same carpet area.

In Tower 14, E4 has 141 sq ft more saleable area than E2. Its carpet area is only 0.46 sq m larger. The report puts the two layouts side by side.

This illustrates the report format. These findings concern the named sample, not this project.

Read the sample report ↗
Prestige Park Grove · Tower 14 comparison · approved sample report
Prestige Park Grove · Tower 14 comparison · approved sample report

The source record

The details behind the headline.

K-RERA · PRM/KA/RERA/1251/472/PR/110925/008087

This project, on the record

The comparable facts of this project, from its own RERA registration record. Each context percentile names its exact comparison set, drawn from Quietlist’s full register store. The paid report adds drawing-read rows to this same table — what the filed plans show about the site, its edges and the unit layouts.

On the register

Declared completion30 June 2030
Land area15,023 sq m (3.7 acres)
Homes registered393
Tower/wing entries6
Unit mix2 × 2 BHK 1T, 172 × 2 BHK 2T, 121 × 3 BHK 2T, 97 × 3 BHK 3T, 1 × 1 BHK

In context

Density105.9 homes per acre
Density in context84th percentile of 125 Yelahanka projects (median 76)

Values as crawled from the official K-RERA record; context percentiles name their comparison population.

Official Registry Facts

Official project scale

RERA filing

Registration-form facts from the K-RERA detail page: use these to sanity-check the builder brochure, parking allotment, and sanctioned-plan references before relying on plan-extracted approximations.

DisclosureOfficial valueWhy it matters
Registered units393Total inventory registered with K-RERA.
Official carpet area32,071 sqmRegulator-disclosed project-level carpet area, not vision-derived room sums.
Official built-up area62,633 sqmUseful scale context when comparing density and project cost.
Registered land area15,023 sqmThe land area attached to this K-RERA registration.
Sanctioned FAR/FSI3Higher FAR generally means a denser vertical build, subject to site layout and open-space design.
Registered tower/wing entries6Official tower/wing count in the K-RERA detail page.
Parking total (reconciled)393Separate filed counts; these categories may overlap and are not added together.
Covered-parking field352Separate filed counts; these categories may overlap and are not added together.
Open-parking field93Separate filed counts; these categories may overlap and are not added together.
Garage field0Separate filed counts; these categories may overlap and are not added together.
Approved plan numberLP.No.Use this to match the sanctioned drawing set shown by the builder.
Plan approval date30-08-2025
Project start date01-09-2025

Official inventory & towers

RERA filing

K-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.

Registered inventory mix

TypeUnitsShareOfficial carpet area
2 BHK 1T21%133 sqm
2 BHK 2T17244%11,443 sqm
3 BHK 2T12131%10,451 sqm
3 BHK 3T9725%9,997 sqm
1 BHK10%47 sqm

Registered tower / wing summary

Tower/wingFloorsUnitsParkingHeight
A12757539.15 m
B12484839.15 m
C12505039.15 m
D12747439.15 m
E12747439.15 m
F12727239.15 m

Official unit register

RERA filing

K-RERA detail-page flat rows: exact unit numbers, official carpet area, UDS, and parking lots. 393 official flat/unit rows, matching the 393 registered units disclosed above. Use this as a checklist against the specific flat number in your cost sheet and draft agreement.

By unit type

Unit typeRowsCarpet areaUDSParking lots
2 BHK 2T17265.2-67.8 sqm29.6-30.5 sqm172
3 BHK 2T12185.3-88.1 sqm39.8-40.9 sqm121
3 BHK 3T97100.8-104.3 sqm47.2-48.1 sqm97
2 BHK 1T266.2-67.0 sqm30.1-30.7 sqm2
1 BHK147.0 sqm22.4 sqm1

By tower / wing

Tower/wingRowsCarpet areaUDSParking lots
A7566.2-87.5 sqm30.1-40.5 sqm75
D7466.0-86.0 sqm29.9-40.3 sqm74
E7486.1-104.2 sqm40.2-48.1 sqm74
F7286.9-104.3 sqm40.6-48.0 sqm72
C5047.0-67.6 sqm22.4-30.5 sqm50
B4865.2-85.9 sqm29.6-40.2 sqm48
Show sample official unit rows
UnitTowerFloorTypeCarpetUDSParking
A001A02 BHK 2T66.3 sqm30.1 sqm1
A005A02 BHK 1T66.2 sqm30.1 sqm1
A006A02 BHK 2T66.8 sqm30.3 sqm1
A101A12 BHK 2T66.3 sqm30.1 sqm1
A102A12 BHK 2T67.8 sqm30.3 sqm1
A103A12 BHK 2T67.0 sqm30.1 sqm1

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

No litigation declared on this project's K-RERA filing.

2 of 28 compliance document slots are filed as Not Applicable; the remaining 26 slots have usable uploaded filings.

No completion certificate (OC) on file yet — project has not been declared complete.

Named utility/regulatory approvals

Electricity (BESCOM/ESCOM)✓ On file (ESCOM/Electricity)
Water & sewage (BWSSB/KWSSB)✓ On file (KWSSB/Water)
Fire NOC✓ On file (Fire Force Department)
Pollution control (KSPCB)✓ On file (KSPCB)
Environmental clearance✓ On file (SEIAA)
Airport Authority height clearance✓ On file (Airport Authority of India)

"Not found in catalog" can mean the approval genuinely isn't on file yet, or that it doesn't apply to this project (K-RERA doesn't tell us which). Ask the builder directly for any marked not found before relying on it.

Statutory approval status

RERA filing

10 further authority slots are marked not applicable by the regulator.

Authority / NOCStatusDateFile

Project team & certifications

RERA filing

K-RERA names 4 project professional/vendor rows across Chartered accountant, Engineer, Architect, Contractor. Use this to cross-check whose certificates, drawings, and contractor commitments support the filing; final reliance still belongs with your lawyer/technical reviewer.

RoleNameRegistration / licenceSinceLocality
Chartered accountantG Muralidharan00359051975Chennai, Tamil Nadu - 600008
EngineerVishnu KumarM-59398/71993Bengaluru Urban, Karnataka - 560050
ArchitectGNANAVEL TCA/2001/270792001Bengaluru Urban, Karnataka - 560032
ContractorEMERALD HAVEN RESIDENCES PVT LTD-2023Bengaluru Urban, Karnataka - 560064

Builder track record

RERA filing

Emerald Haven has 3 other K-RERA-registered projects in our records (average reported construction progress 20%). 0 are past their declared completion deadline with no completion certificate recorded — but because K-RERA publishes OCs inconsistently, a project that has actually been finished and handed over still shows up this way, so this overstates real delays, especially for a high-volume established builder. That is a lower delayed rate than the K-RERA average across Bengaluru on the same measure.

Read this as a list to spot-check for a pattern of genuinely stalled projects, not as a delay rate — pull up a few of the builder’s other K-RERA registrations and check whether they’ve actually been delivered.

Financials & Construction Progress

Financial disclosures

RERA filing

Latest quarterly filing (2026-Q1): ₹24.32 Cr collected from buyers, ₹30.00 Cr withdrawn from the project's escrow account. This quarter the escrow withdrawal (₹30.00 Cr) exceeded buyer collections (₹24.32 Cr) — worth asking the builder to reconcile against certified construction milestones, which is what RERA requires escrow draws to track.

Construction progress14% → 41% (+27 pts)
Units sold/booked as registered388/393 (99%)
Buyer collections in available QPRs₹295.42 Cr
Escrow withdrawals in available QPRs₹149.79 Cr (0.51x collections)
  • 99% of registered units are shown as sold/booked, but no completion certificate is on file yet.
  • Construction progress moved from 14% to 41% across the filed QPR window.
  • The builder has drawn 0.51x of buyer collections from escrow (about 51% of the ₹295 Cr collected) — money is largely staying in the regulated escrow account rather than being pulled out ahead of spend, which is the safer direction. A ratio near or above 1.0 would be the one to scrutinise.
  • In the latest QPR, escrow withdrawal exceeds buyer collections for that quarter. This can be normal if prior balance existed, but it needs a clean explanation.

QPR figures are developer-filed quarterly disclosures. Collections and withdrawals are not a project valuation; they are a sanity check for whether sales, construction progress, and escrow draws appear directionally aligned.

Declared construction cost ÷ registered units averages to ₹44.2 lakhs per unit — the developer's own declared construction/development cost, not a sale price. K-RERA filings don't disclose what the builder is charging, so this can't tell you whether you're getting a fair deal — only you comparing your quoted price against comparable listings nearby can answer that.

RERA 70% project account is on file: HDFC Richmond road IFSC Code : HDFC0000523 Pin Code : 560025. RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Location & Connectivity

The nearest major job hub is ~8 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Outer Ring Road / Manyata8 km
Kempegowda Int'l Airport12 km
MG Road / city centre16 km
Whitefield IT hub21 km
Bellandur–Marathahalli belt21 km
Electronic City30 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Emerald Haven.
Emerald Haven has 4 projects registered in Bangalore.

Other projects by this builder in Bangalore

Cascadia BY TVS Emerald
On track · 26% built · 56% sold
TVS Emerald Altura
On track · 15% built · 0% sold

Other RERA-registered projects in Gummanahalli

Emerald & Luminaire Block At Brigade El Dorado
Dioro & Beryl At Brigade El Dorado

Major developers building in Gummanahalli

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.

Own a unit in TVS Emerald Auralis?

Sell directly to Quietlist's pre-screened buyer list — flat fee, no broker commission.

List your unit →

Last checked against the RERA register: 20 Sep 2026