Ashiana Amarah Phase 3 & 3a
REVENUE ESTATE OF VILLAGE- WA ZIRPUR, SECTOR 93, DISTT. GURUGRAM, HARYANA · Ashiana Housing
Know the project.
Then choose your home.
The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.
The record · free to read
Registration read 20 Sep 2026Progress & dates
The timeline on file.
Available record
No construction trend to plot.
The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.
registration expiry
16 Oct 2028
The registered date and a construction update answer different questions. Neither is a confirmation of possession.
HRERA registration · read 20 Sep 2026
From another project
See the report before you buy.
A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.
Read a sample report ↗The source record
The details behind the headline.
HRERA ·
Escrow account
What has moved through the RERA escrow account?
Across 9 filed quarterly reports, Ashiana Amarah Phase 3 & 3a records ₹194.36 Cr paid into and ₹159.40 Cr withdrawn from its RERA escrow account, with a latest recorded balance of ₹60.78 Cr.
₹194.36 Cr
into the escrow account
₹159.40 Cr
withdrawn
₹60.78 Cr
latest balance
Amounts as filed in the developer's own quarterly progress reports to HRERA, summed across the quarters on record.
Source · HRERA quarterly progress reports
Official Unit Inventory
329 apartments filed across 1 carpet-area configurations, 6 towers, carpet areas from 1,738 to 246,958 sq ft. These are the carpet areas the developer filed with HRERA — match the unit a broker quotes you against this table; a "1,650 sq ft" pitch should map to a filed configuration here (carpet area is the RERA-defined saleable floor).
| Carpet area | (metric) | Units of this size |
|---|---|---|
| 1,738 sq ft | 161.5 sq m | 13 |
Sales Traction, Quarter by Quarter
Units the developer reported booking in each quarterly HRERA filing — the closest public read on real demand.
| Quarter | Units booked | Total units |
|---|---|---|
| 2024 Q2 | 0 | 329 |
| 2024 Q3 | 0 | 329 |
| 2024 Q4 | 0 | 224 |
| 2025 Q1 | 0 | 224 |
| 2025 Q2 | 0 | 224 |
| 2025 Q3 | 0 | — |
| 2025 Q4 | 0 | 224 |
| 2026 Q1 | 0 | 224 |
| 2026 Q2 | 0 | 224 |
Escrow Account Activity
Money moving through the RERA-mandated escrow account each quarter. Withdrawals from it are statutorily meant to fund construction milestones.
| Quarter | Deposited | Withdrawn | Balance |
|---|---|---|---|
| 2024 Q2 | ₹62.22 Cr | ₹48.01 Cr | ₹40.04 Cr |
| 2024 Q3 | ₹17.85 Cr | ₹6.38 Cr | ₹51.51 Cr |
| 2024 Q4 | ₹92 L | ₹13.24 Cr | ₹39.19 Cr |
| 2025 Q1 | ₹17.96 Cr | ₹9.18 Cr | ₹47.96 Cr |
| 2025 Q2 | ₹13.18 Cr | ₹11.39 Cr | ₹49.76 Cr |
| 2025 Q3 | ₹42.96 Cr | ₹12.35 Cr | ₹80.37 Cr |
| 2025 Q4 | ₹27.67 Cr | ₹13.96 Cr | ₹94.08 Cr |
| 2026 Q1 | ₹3.43 Cr | ₹31.19 Cr | ₹66.32 Cr |
| 2026 Q2 | ₹8.17 Cr | ₹13.70 Cr | ₹60.78 Cr |
Builder Record
Ashiana Housing has 11 other Gurgaon projects on the HRERA register; 0 are past the declared completion date with no OC yet, 3 delivered. Read it as a spot-check list for a pattern, not a delay rate.
- Ashiana Aaroham Phase 1 — declared 2033-10-31
- Ashiana Aaroham Phase II — declared 2033-10-31
- Ashiana Amarah Phase 4 — declared 2029-04-30
- Ashiana Amarah Phase 5 — declared 2030-01-31
Location & Connectivity
The nearest major job hub is ~6 km away — a manageable everyday commute to a major job hub.
| Landmark | Straight-line |
|---|---|
| IMT Manesar | 6 km |
| Golf Course Road belt | 18 km |
| Cyber City / DLF Cyber Hub | 18 km |
| Udyog Vihar | 18 km |
| IGI Airport, Delhi | 23 km |
| Connaught Place, Delhi | 37 km |
Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.