Ashiana Amarah Phase II
REVENUE ESTATE OF VILLAGE- WA ZIRPUR, SECTOR 93, DISTT. GURUGRAM, HARYANA · Ashiana Housing
Know the project.
Then choose your home.
The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.
The record · free to read
Registration read 20 Sep 2026Progress & dates
The timeline on file.
Available record
No construction trend to plot.
The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.
registration expiry
15 Oct 2027
The registered date and a construction update answer different questions. Neither is a confirmation of possession.
HRERA registration · read 20 Sep 2026
From another project
See the report before you buy.
A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.
Read a sample report ↗The source record
The details behind the headline.
HRERA ·
Escrow account
What has moved through the RERA escrow account?
Across 12 filed quarterly reports, Ashiana Amarah Phase II records ₹142.43 Cr paid into and ₹186.97 Cr withdrawn from its RERA escrow account, with a latest recorded balance of ₹0 L.
₹142.43 Cr
into the escrow account
₹186.97 Cr
withdrawn
₹0 L
latest balance
Amounts as filed in the developer's own quarterly progress reports to HRERA, summed across the quarters on record.
Source · HRERA quarterly progress reports
Sales Traction, Quarter by Quarter
Units the developer reported booking in each quarterly HRERA filing — the closest public read on real demand.
| Quarter | Units booked | Total units |
|---|---|---|
| 2023 Q2 | 224 | 224 |
| 2023 Q3 | 224 | 224 |
| 2023 Q4 | 224 | 224 |
| 2024 Q1 | 0 | 224 |
| 2024 Q2 | 0 | 224 |
| 2024 Q3 | 0 | 224 |
| 2024 Q4 | 0 | 224 |
| 2025 Q1 | 0 | 224 |
| 2025 Q2 | 0 | 224 |
| 2025 Q3 | 0 | 224 |
| 2025 Q4 | 0 | 224 |
| 2026 Q1 | 0 | 224 |
Escrow Account Activity
Money moving through the RERA-mandated escrow account each quarter. Withdrawals from it are statutorily meant to fund construction milestones.
| Quarter | Deposited | Withdrawn | Balance |
|---|---|---|---|
| 2023 Q2 | ₹52.58 Cr | ₹52.29 Cr | ₹56 L |
| 2023 Q3 | ₹2.22 Cr | ₹22.56 Cr | ₹21 L |
| 2023 Q4 | ₹10.15 Cr | ₹9.40 Cr | ₹95 L |
| 2024 Q1 | ₹4.92 Cr | ₹8.67 Cr | ₹21.49 Cr |
| 2024 Q2 | ₹13.25 Cr | ₹7.75 Cr | ₹26.99 Cr |
| 2024 Q3 | ₹15.82 Cr | ₹8.31 Cr | ₹34.51 Cr |
| 2024 Q4 | ₹26.10 Cr | ₹9.68 Cr | ₹50.92 Cr |
| 2025 Q1 | ₹5.01 Cr | ₹11.62 Cr | ₹44.32 Cr |
| 2025 Q2 | ₹4.58 Cr | ₹7.60 Cr | ₹41.30 Cr |
| 2025 Q3 | ₹4.52 Cr | ₹17.70 Cr | ₹28.12 Cr |
| 2025 Q4 | ₹2.67 Cr | ₹25.89 Cr | ₹4.91 Cr |
| 2026 Q1 | ₹60 L | ₹5.51 Cr | ₹0 L |
Builder Record
Ashiana Housing has 11 other Gurgaon projects on the HRERA register; 0 are past the declared completion date with no OC yet, 3 delivered. Read it as a spot-check list for a pattern, not a delay rate.
- Ashiana Aaroham Phase 1 — declared 2033-10-31
- Ashiana Aaroham Phase II — declared 2033-10-31
- Ashiana Amarah Phase 3 & 3a — declared 2028-10-16
- Ashiana Amarah Phase 4 — declared 2029-04-30
Location & Connectivity
The nearest major job hub is ~6 km away — a manageable everyday commute to a major job hub.
| Landmark | Straight-line |
|---|---|
| IMT Manesar | 6 km |
| Golf Course Road belt | 18 km |
| Cyber City / DLF Cyber Hub | 18 km |
| Udyog Vihar | 18 km |
| IGI Airport, Delhi | 23 km |
| Connaught Place, Delhi | 37 km |
Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.