Ashiana Amarah Phase I & Ia

VILL. WAZIRPUR , SEC 93 , GUR UGRAM · Ashiana Housing

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

224units in latest filingQ2 2026 filing
0units sold that quarterQ2 2026 filing
15 Jan 2027registration expiryHRERA registration · read 20 Sep 2026

The record · free to read

Registration read 20 Sep 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

registration expiry

15 Jan 2027

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

HRERA registration · read 20 Sep 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

HRERA ·

Escrow account

What has moved through the RERA escrow account?

Across 15 filed quarterly reports, Ashiana Amarah Phase I & Ia records ₹165.36 Cr paid into and ₹161.81 Cr withdrawn from its RERA escrow account, with a latest recorded balance of ₹0 L.

₹165.36 Cr

into the escrow account

₹161.81 Cr

withdrawn

₹0 L

latest balance

Amounts as filed in the developer's own quarterly progress reports to HRERA, summed across the quarters on record.

Source · HRERA quarterly progress reports

Official Unit Inventory

360 apartments filed across 6 carpet-area configurations, 7 towers, carpet areas from 122 to 1,408 sq ft. These are the carpet areas the developer filed with HRERA — match the unit a broker quotes you against this table; a "1,650 sq ft" pitch should map to a filed configuration here (carpet area is the RERA-defined saleable floor).

Carpet area(metric)Units of this size
1,408 sq ft130.8 sq m56
1,205 sq ft112.0 sq m56
1,000 sq ft92.9 sq m112
190 sq ft17.7 sq m120
144 sq ft13.3 sq m6
122 sq ft11.3 sq m10

Sales Traction, Quarter by Quarter

Units the developer reported booking in each quarterly HRERA filing — the closest public read on real demand.

QuarterUnits bookedTotal units
2022 Q4448448
2023 Q12224
2023 Q20224
2023 Q3224224
2023 Q4224224
2024 Q10360
2024 Q20360
2024 Q30360
2024 Q40224
2025 Q10224
2025 Q20224
2025 Q30224
2025 Q40224
2026 Q10224
2026 Q20224

Escrow Account Activity

Money moving through the RERA-mandated escrow account each quarter. Withdrawals from it are statutorily meant to fund construction milestones.

QuarterDepositedWithdrawnBalance
2022 Q4₹36.07 Cr₹10.21 Cr₹31.07 Cr
2023 Q1₹8.51 Cr₹29.04 Cr₹10.53 Cr
2023 Q2₹3.66 Cr₹4.79 Cr₹16 L
2023 Q3₹17.05 Cr₹16.77 Cr₹44 L
2023 Q4₹4.42 Cr₹4.67 Cr₹19 L
2024 Q1₹6.58 Cr₹6.51 Cr₹74 L
2024 Q2₹16.21 Cr₹16.45 Cr₹51 L
2024 Q3₹14.08 Cr₹14.18 Cr₹41 L
2024 Q4₹13.89 Cr₹14.12 Cr₹18 L
2025 Q1₹2.46 Cr₹2.54 Cr₹10 L
2025 Q2₹1.79 Cr₹1.84 Cr₹4 L
2025 Q3₹1.81 Cr₹1.85 Cr₹0 L
2025 Q4₹35.10 Cr₹35.07 Cr₹4 L
2026 Q1₹2.75 Cr₹2.63 Cr₹15 L
2026 Q2₹98 L₹1.14 Cr₹0 L

Builder Record

Ashiana Housing has 11 other Gurgaon projects on the HRERA register; 0 are past the declared completion date with no OC yet, 3 delivered. Read it as a spot-check list for a pattern, not a delay rate.

  • Ashiana Aaroham Phase 1 — declared 2033-10-31
  • Ashiana Aaroham Phase II — declared 2033-10-31
  • Ashiana Amarah Phase 3 & 3a — declared 2028-10-16
  • Ashiana Amarah Phase 4 — declared 2029-04-30

Location & Connectivity

The nearest major job hub is ~6 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
IMT Manesar6 km
Golf Course Road belt18 km
Cyber City / DLF Cyber Hub18 km
Udyog Vihar18 km
IGI Airport, Delhi23 km
Connaught Place, Delhi37 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Ashiana Housing. View Ashiana Housing's full track record →
Ashiana Housing has 11 projects registered in Gurgaon, 3 completed.

Buyer reviews · MouthShut

★★☆☆☆ 1.69/5

56 reviews for Ashiana Housing in Gurgaon
Read 56 reviews on MouthShut →

Other projects by this builder in Gurgaon

Ashiana Amarah Phase 3 & 3A
On track
Ashiana Amarah Phase 4
On track · 4% sold
Ashiana Amarah Phase II
On track · 0% sold

Other RERA-registered projects in Sector 93

Major developers building in Sector 93

Figures are the developer's own quarterly disclosures on the Haryana RERA register. "Sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Gurgaon project-health tool.