MahaRERA Property Intelligence · Thane

Alpinia

P51700000778 · promoter Acme Housing India

Certificate SignedDue 30 Dec 2021

Delivery & Registration

MahaRERA registrationP51700000778
Registered on23 Jul 2017
Promoter-declared completion30 Dec 2021
Current statusCertificate Signed
Against todayabout 55 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+27.

BuildingWingsFloorsDeclared completion
Alpinia1G+27-

Complaints & Orders

6 complaints are on the MahaRERA record for this project, with orders passed in 6. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.

Complaint no.FiledPartiesStatus
CC00600000007860006/04/2019RAJESH KUMAR PODDAR vs ACME HOUSING INDIA PRIVATE LTDorder passed
CC00600000007908503/05/2019Jaywant Anant Pandit & 2 Ors. vs Acme Housing India Private Limitedorder passed
CC00600000010039504/08/2019DHRUBA JYOTI BORA vs ACME HOUSING INDIA PVT. LTD.order passed
CC00600000019258212/02/2020PIJUSH BISWAS AND KANIKA BISWAS vs Ms Ascent construction pvt ltdorder passed
CC00600000019308420/06/2020Mr. Aniket Deelip Alashe and Mrs. Rajashree Deelip Alashe vs Acme Housing India Private Limitedorder passed
CC00600000039621723/06/2023SHAHEEN IFTIKHAR PUNJABI vs Ascent construction private limitedorder passed

Legal & Litigation

The promoter has declared 6 court cases on this project to MahaRERA. 6 are still pending. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your flat. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
High Court Bombay7949 of 20152015Pending
High Court BombayFirst Appeal No 1264 of 20152015Pending
Thane Civil CourtSCS 925 of 2008 New no RCS 1120 of 20122012Pending
High Court BombayCri WP No 4182 of 20152015Pending
High Court BombayCivil WP No 4096 of 20152015Pending
Consumer Court State CommissionCC/13/182013Pending

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 1 time. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
30 Dec 202130 Dec 2020• 17 Months Delay - Tree cutting permission delay • 06 Months Delay - Between tree authority permission and commencement certificate from TMC • 05 Months Delay - High Court Stay

Location, Land & Connectivity

Located at Andheri, Mumbai Suburban, 400607. Per the filed land record, the plot is bounded to the north by 19 13 56 91 N 72 58 21 04 E, to the south by 19 13 56 44 N 72 58 21 09 E, to the east by 19 13 56 22 N 72 58 21 61 E and to the west by 19 13 56 60 N 72 58 20 20 E. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~16 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
Powai / Hiranandani business park16 km
Andheri MIDC / SEEPZ17 km
Chhatrapati Shivaji Int'l Airport21 km
Bandra Kurla Complex (BKC)23 km
Lower Parel / Worli business district32 km
Nariman Point / Fort39 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Acme Housing India Private Limited is the promoter on 8 MahaRERA-registered projects, of which 1 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

See every Acme Housing India Private Limited project & its RERA track record →

Other flagged projects by Acme Housing India Private Limited

Acme Housing India Private Limited
FlaggedThane
Acme Housing India Private Limited
FlaggedThane
Acme Housing India Private Limited
FlaggedThane
Acme Housing India Private Limited
Deregistered by MahaRERAThane
Acme Housing India Private Limited
FlaggedThane
Acme Housing India Private Limited
FlaggedThane

Other RERA-registered projects in Thane

Godrej Exquisite
possession by Sep 2026 · Godrej Macbricks Private Limited
Lodha Crown Kolshet-Tower 1
possession by Sep 2026 · Lodha Developers Limited
Odysseus
possession by Sep 2026 · Sagar Enterprise
Unique Vistas Mhada Building NO. 1,2,3
possession by Sep 2026 · Madhu Harshad Doshi
Unique Vistas Mhada Buildingno. 4 5 6 7
possession by Sep 2026 · Madhu Harshad Doshi
Daffodil
possession by Dec 2026 · Shree Tirupati Greenfield Developers

Major developers building in Thane

Other RERA-registered projects in Thane

Altus 24
possession by Sep 2032 · Jindal Today Infra LLP
Amaira
declared completion Jul 2023 · Pacific Excellence
Amaira 2
possession by Apr 2027 · Pacific Excellence
Amakin Mohammadiya Complex Phase III
declared completion Dec 2024 · RAJ Corporation
Amakin Mohammadiyah Complex
possession by Dec 2030 · RAJ Corporation
Amakin Mohammediyah Phase 3
declared completion Dec 2024 · Amakin Mohammediyah Private Limited

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026