ANAND MANGAL

Mumbai Suburban · SAMARTH KRUPA DEVELOPER

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Oct 2020declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Oct 2020

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51800008706

Delivery and registration

When is the project declared for completion?

ANAND MANGAL is registered with MahaRERA as P51800008706 and the promoter has declared completion for 30 Oct 2020.

30 Oct 2020

declared completion

71months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51800008706
Registered on19 Aug 2017
Promoter-declared completion30 Oct 2020
Current statusCertificate Signed
Against todayabout 71 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for ANAND MANGAL record 14 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 14 quarterly progress reports on record since registration, with no current default.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for ANAND MANGAL in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+7.

BuildingWingsFloorsDeclared completion
ANAND MANGAL1G+7-

Legal and disputes

What disputes are disclosed?

13 complaints are on the MahaRERA record for ANAND MANGAL, with orders passed in 13 of them.

13complaints

13with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000002291815/01/2018YOBU JOSEPH vs SAMARTH KRUPA DEVELOPERorder passed
CC00600000002293116/01/2018RAGHUNATH SAWANT vs SAMARTH KRUPA DEVELOPERorder passed
CC00600000002296017/01/2018PRASAD DAGLE vs SAMARTH KRUPA DEVELOPERorder passed
CC00600000002298918/01/2018KASHINATH SHIRWADKAR vs SAMARTH KRUPA DEVELOPERorder passed
CC00600000005641802/10/2018KASHINATH SHIRWADKAR vs M/s Samarth Krupa Developerorder passed
CC00600000002300819/01/2018GOPAL KAWALI vs SAMARTH KRUPA DEVELOPERorder passed
CC00600000005762910/01/2019GOPAL KAWALI vs SAMARTH KURPA DEVELOPERorder passed
CC00600000007941622/05/2019ANAND MANGAL ASSOCIATION OF ALLOTTEES vs SAMARTH KRUPA DEVELOPERorder passed
CC00600000035451425/02/2023Gopal Narsappa Kawali vs SAMARTH KRUPA DEVELOPERorder passed
CC00600000002301620/01/2018DINESH BHALEKAR vs SAMARTH KRUPA DEVELOPERorder passed
CC00600000002303421/01/2018SHIVAJYOTHI YOBU vs SAMARTH KRUPA DEVELOPERorder passed
CC00600000002314230/01/2018PRASHANT MUNGEKAR vs SAMARTH KRUPA DEVELOPERorder passed
CC1250153408/05/2025Dinesh Sakharam Bhalekar and Diksha Dinesh Bhalekar vs SAMARTH KRUPA DEVELOPERorder passed

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 2 times, as recorded on the register.

FromExtended toStated reason
as registered30 Apr 2020Because of our site condition we could not get drainage connection now we have got the permission and completed the drainage work and applying for OC.
30 Apr 202030 Apr 2020Required extension to obtain the required Occupation Certificate for the project.

Location, Land & Connectivity

Located at Kurla, Mumbai Suburban, 400080. Per the filed land record, the plot is bounded to the north by DP ROAD, to the south by NES SCHOOL, to the east by CTS NO 464 AND CTS NO 468 and to the west by NES SCHOOL. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~8 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Powai / Hiranandani business park8 km
Andheri MIDC / SEEPZ9 km
Chhatrapati Shivaji Int'l Airport13 km
Bandra Kurla Complex (BKC)14 km
Lower Parel / Worli business district23 km
Nariman Point / Fort30 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Mulund West

AAI Satidevi Paradise
possession by Sep 2026 · Shreenath Developers
Laizer Elegance
Not filing quarterly progress reports · possession by Sep 2026 · Laizer Builders & Developers
THE NEW Anand Deep CHS LTD
possession by Sep 2026 · Shreejee Buildcon
Tirupati Apartments Chsl
possession by Oct 2026 · Tirupati Aparmtnets CO Operative Housing
Horizon Garden View
possession by Nov 2026 · Horizon Promoters India LTD
Montana Phase - 3
possession by Dec 2026 · Lohitka Properties LLP

Major developers building in Mulund West

Other RERA-registered projects in Mumbai Suburban

Anand Milan Co.op. Housing Society Limited
declared completion Mar 2024 · Anand Milan Co.op. Housing Society Limit
Anand ONE
possession by Dec 2030 · Mahalakshmi Padam Private Limited
Anand Tower
declared completion Oct 2020 · Arihant Associates
Anand Villa
possession by Dec 2027 · Ivaan Buildcon LLP
Ananda CHS Wing B
possession by Mar 2027 · Ananda Living Spaces LLP
Anandam
declared completion Aug 2026 · M/s Analiza Realty Pvt. Ltd.

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026