Mumbai/Project record

MahaRERA · the public record

BALAJI ACCOLADE

Mulund West · BALAJI DEVELOPERS

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Jan 2021declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Jan 2021

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51800003420

Delivery and registration

When is the project declared for completion?

BALAJI ACCOLADE is registered with MahaRERA as P51800003420 and the promoter has declared completion for 30 Jan 2021.

30 Jan 2021

declared completion

68months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51800003420
Registered on05 Aug 2017
Promoter-declared completion30 Jan 2021
Current statusCertificate Signed
Against todayabout 68 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for BALAJI ACCOLADE record 15 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 15 quarterly progress reports on record since registration, with no current default.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for BALAJI ACCOLADE in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+8.

BuildingWingsFloorsDeclared completion
BALAJI ACCOLADE1G+830 Jan 2021

Legal and disputes

What disputes are disclosed?

3 complaints are on the MahaRERA record for BALAJI ACCOLADE, with orders passed in 3 of them.

3complaints

3with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000005760809/01/2019BABITA KAMAL KUMAR AGRAWAL vs BALAJI DEVELOPERSorder passed
CC00600000019298826/07/2020Anjali Mhatre vs Balaji Developerorder passed
CC00600000033393112/01/2023M/S. KOTWALA REALTY PRIVATE LIMITED vs M/S. BALAJI DEVELOPERSorder passed

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered30 Jul 2020The said Project was delayed on account of delay in receipt of the approvals for the amended plans and also for change of user from 'Commercial' to 'Nursing Home'. Kindly grant us

Location, Land & Connectivity

Located at Mulund West, Kurla, Mumbai Suburban, 400080. Per the filed land record, the plot is bounded to the north by CTS NO 1071, to the south by DEVDAYAL ROAD DP ROAD, to the east by CTS NO 1072 AND 1073 and to the west by EXISTING ROAD. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~8 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Powai / Hiranandani business park8 km
Andheri MIDC / SEEPZ9 km
Chhatrapati Shivaji Int'l Airport13 km
Bandra Kurla Complex (BKC)14 km
Lower Parel / Worli business district23 km
Nariman Point / Fort30 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Balaji Developers is the promoter on 22 MahaRERA-registered projects, of which 5 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

See every Balaji Developers project & its RERA track record →

Other flagged projects by Balaji Developers

Balaji Developers
Past its declared completion dateThane

Other RERA-registered projects in Mulund West

AAI Satidevi Paradise
possession by Sep 2026 · Shreenath Developers
Laizer Elegance
Not filing quarterly progress reports · possession by Sep 2026 · Laizer Builders & Developers
THE NEW Anand Deep CHS LTD
possession by Sep 2026 · Shreejee Buildcon
Tirupati Apartments Chsl
possession by Oct 2026 · Tirupati Aparmtnets CO Operative Housing
Horizon Garden View
possession by Nov 2026 · Horizon Promoters India LTD
Montana Phase - 3
possession by Dec 2026 · Lohitka Properties LLP

Major developers building in Mulund West

Other RERA-registered projects in Mumbai Suburban

Balaji Apartment
possession by Dec 2026 · Tridev Realty AND Construction PVT LTD
Balaji Darshan
declared completion May 2026 · Starspace Ventures Private Limited
Balaji Empire
declared completion Dec 2022 · M/S Trimurti & K. Mukesh Builders AN
Balaji Heights Redevelopment OF Rajendra Nagar OM Sairam CHS LTD
possession by May 2027 · Balaji Builders AND Developers
Baldevsingh Thakur SRA Coop HSG SOC LTD
declared completion Jul 2026 · Krishna Narsingrao Pimple
Bali Primera
possession by Sep 2027 · Bali Landmarks LLP

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026