Building No. A, Richmond of Rutu City Complex

Thane · HARASIDDH DEVELOPERS

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Jun 2022declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Jun 2022

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51700001284

Delivery and registration

When is the project declared for completion?

Building No. A, Richmond of Rutu City Complex is registered with MahaRERA as P51700001284 and the promoter has declared completion for 30 Jun 2022.

30 Jun 2022

declared completion

51months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51700001284
Registered on27 Jul 2017
Promoter-declared completion30 Jun 2022
Current statusCertificate Signed
Against todayabout 51 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Building No. A, Richmond of Rutu City Complex record 20 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 20 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Harasiddh Developers is the promoter of record on 7 projects registered with MahaRERA, none of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

7projects

registered with MahaRERA

0flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Building No. A, Richmond of Rutu City Complex in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+32.

BuildingWingsFloorsDeclared completion
Building No A Richmond of Rutu City Complex1G+3230 Jun 2021

Legal and disputes

What disputes are disclosed?

1 complaint is on the MahaRERA record for Building No. A, Richmond of Rutu City Complex, with orders passed in 1 of them.

1complaint

1with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000019755108/07/2021Harasiddh Developers vs Meera Madhukar Kedarorder passed

Legal & Litigation

The promoter has declared 1 court case on this project to MahaRERA. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your home. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
Court Of Joint Civil Judge Senior Division ThaneRegular Civil Suit No 1242013The Matter Is Listed For Hearing On An Amendment Application Taken Out By Ms Harasiddh Developers

Location, Land & Connectivity

Located at Thane, Thane, Thane, Thane, 400607. Per the filed land record, the plot is bounded to the north by Nalla , to the south by DP Road , to the east by Land Bearing S No 169-2 and to the west by Village Boriwade . These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~16 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
Powai / Hiranandani business park16 km
Andheri MIDC / SEEPZ17 km
Chhatrapati Shivaji Int'l Airport21 km
Bandra Kurla Complex (BKC)23 km
Lower Parel / Worli business district32 km
Nariman Point / Fort39 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Harasiddh Developers is the promoter on 3 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

Other flagged projects by Harasiddh Developers

Harasiddh Developers
FlaggedThane
Harasiddh Developers
FlaggedThane

Other RERA-registered projects in Kolshet

Godrej Exquisite
possession by Sep 2026 · Godrej Macbricks Private Limited
Lodha Crown Kolshet-Tower 1
possession by Sep 2026 · Lodha Developers Limited
Odysseus
possession by Sep 2026 · Sagar Enterprise
Unique Vistas Mhada Building NO. 1,2,3
possession by Sep 2026 · Madhu Harshad Doshi
Unique Vistas Mhada Buildingno. 4 5 6 7
possession by Sep 2026 · Madhu Harshad Doshi
Daffodil
possession by Dec 2026 · Shree Tirupati Greenfield Developers

Major developers building in Kolshet

Other RERA-registered projects in Thane

BUL BUL CO-Operative Housing Society Limited
possession by Dec 2026 · Ashwiniinfradevelopments Private Limited
Bunch Berry
declared completion Dec 2021 · Seema Land Developers
Business Square
possession by Dec 2031 · Allerindia Infra LLP
Butterfly Wings
declared completion May 2024 · Om Shree Maruti Sthapatya
Callista
declared completion Dec 2025 · Otto Constructions
Capital Edge
possession by Sep 2032 · Jindal Today Infra LLP

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026