MahaRERA Property Intelligence · Mumbai Suburban

OLYMPIA A B

P51800011870 · promoter Nirmal Developer

Certificate SignedDue 30 Dec 2025

Delivery & Registration

MahaRERA registrationP51800011870
Registered on31 Aug 2017
Promoter-declared completion30 Dec 2025
Current statusCertificate Signed
Against todayabout 7 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Nirmal Developer is the promoter of record on 66 projects, of which 40 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+54.

BuildingWingsFloorsDeclared completion
Olympia A B1G+54-

Complaints & Orders

46 complaints are on the MahaRERA record for this project, with orders passed in 44. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.

Complaint no.FiledPartiesStatus
CC00600000004439109/09/2019Nandkishor Shivaji Mane vs Dharmesh Jain MD and CEOorder passed
CC00600000000196517/11/2017AVINASH THAKARE vs NIRMAL DEVELOPERSorder passed
CC00600000005571211/08/2018avinash Thakare vs Nirmal Developersorder passed
CC00600000001248127/12/2017Nilaja Jagdish Achrekar vs Dharmesh Jainorder passed
CC00600000002350626/02/2018Nirmal Developer Olympia Aggrieved Buyers Association vs Nirmal Developersorder passed
CC00600000005457720/05/2018Kalpana Ambavane vs M/S Nirmal developersorder passed
CC00600000005457820/05/2018Archana Ambavane vs M/S Nirmal Developersorder passed
CC00600000014102930/09/2019ARCHANA AMBAVANE vs M/S NIRMAL DEVELOPERS THROUGH MR. DHARMESH JAINorder passed
CC00600000014103030/09/2019KALPANA AMBAVANE vs M/S NIRMAL DEVELOPERS THROUGH DHARMESH JAINorder passed
CC00600000004423624/06/2018Shivaprasad Nair vs Nirmal Developersorder passed
CC00600000005460623/05/2018Nirmal Developer Olympia Aggrieved Buyer Association vs Nirmal Developerorder passed
CC00600000005470231/05/2018B H PANDIT vs NIRMAL DEVELOPERSorder passed
CC00600000005490313/06/2018PRASAD PIMPALE vs NIRMAL DEVELOPERSorder passed
CC00600000005790130/01/2019Manish Pathak vs Nirmal Developersorder passed
CC00600000005556905/08/2018Seema Bhagchand Chatani vs Nirmal developer (dharmesh jain)order passed
CC00600000005579021/08/2018Gayatri Gupte vs NIRMAL DEVELOPERS - OLYMPIAorder passed
CC00600000005584220/08/2018Om Praskash Pandey vs Nirmal Developersorder passed
CC00600000019286104/03/2020Om Prakash Pandey vs Nirmal Developersorder passed
CC00600000009006110/07/2019Amit Arabatti vs Dharmesh Jainorder passed
CC00600000005656213/10/2018ROHAN BHOSALE vs NIRMAL DEVELOPERorder passed
CC00600000007833404/03/2019SMITA GODFREY DSILVA vs Nirmal Developer (Mr. Rajiv Jain)order passed
CC00600000005769616/01/2019SHASHANK SANJAY SHARMA vs NIRMAL GROUP OF COMPANIESorder passed
CC00600000007873202/05/2019HARISHCHANDRA T FULPADIA vs DHARMESH JAINorder passed
CC00600000007882910/04/2019Dnyandeo Premchand Chaudhari vs Nirmal Developersorder passed
CC00600000007913301/07/2019Rekha Mishra vs Nirmal Developerorder passed
CC00600000008997106/07/2019Prasanna Iyengar vs Nirmal Developersorder passed
CC00600000010054219/08/2019Debashish Prakash Karkera vs Nirmal Developersorder passed
CC00600000016123211/10/2019Anil Narottamdas Somaiya vs Nirmal Developersorder passed
CC00600000017176609/12/2019Kunal Anand Date vs Nirmal Developersorder passed
CC00600000017178307/12/2019Vasant Bhadra vs Nirmal Developersorder passed
CC00600000017179507/12/2019Himmat Bhanushali vs Nirmal Developersorder passed
CC00600000019212211/01/2020Aniket Dinkar Metkar vs Dharmesh Jainorder passed
CC00600000019220916/01/2020Ravi Jethwani vs Nirmal Lifestyle Pvt. Ltd.; Lucrative Properties Pvt. Ltd.order passed
CC00600000019240203/02/2020RAJESH RAMAKANT BHUSE vs RAJIV JAINorder passed
CC00600000019271122/02/2020Jayprakash Ramawadh Singh vs Nirmal Developersorder passed
CC00600000019300518/03/2020Nilaja Achrekar vs Nirmal Developersorder passed
CC00600000019300718/03/2020Ankit Kishore Chande vs Nirmal Developersorder passed
CC00600000019469011/11/2020Rajkumar Bimalchandra Dubey vs Nirmal Developersorder passed
CC00600000019663405/04/2021Arvind Bhandare vs Arvind Bhandareorder passed
CC00600000019895308/11/2021SUSMITA MAJUMDAR vs Nirmal Developersorder passed
CC00600000025169101/07/2022Ashok Lokhande vs Nirmal Developerorder passed
CC00600000039614109/06/2023RAMCHANDRA VASANT BHOGLE vs NIRMAL DEVELOPERorder passed
CC00600000039706914/08/2023SUDHIR RAMAKANT PARAB vs NIRMAL DEVELOPERorder passed
CC00600000039736607/09/2023Anjana Vikram Lavangare vs Nirmal Developerorder passed
CC1260015710/01/2026Mamta Kishore Jethwani vs Nirmal Developerpending / no order on file
CC1260385522/06/2026Prabhat Ranjan vs Nirmal Developerpending / no order on file

Legal & Litigation

The promoter has declared 4 court cases on this project to MahaRERA. 3 are still pending. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your flat. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
City Civil Court At Mumbai1090101994Pending
City Civil Court At Mumbai1092721994Pending
Small Cause Court At Dhobi Talao Mumbai111/1382012Pending
State Consumer Disputes Redressal Commission MumbaiCC/862 /20162016Next Hearing In The Month Of August

Location, Land & Connectivity

Located at Kurla, Mumbai Suburban, 400080. Per the filed land record, the plot is bounded to the north by NALLAH, to the south by 13 M W ROAD, to the east by BLDG C D and to the west by Proposed Building. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~8 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Powai / Hiranandani business park8 km
Andheri MIDC / SEEPZ9 km
Chhatrapati Shivaji Int'l Airport13 km
Bandra Kurla Complex (BKC)14 km
Lower Parel / Worli business district23 km
Nariman Point / Fort30 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Mulund West

Kailash Residency
possession by Aug 2026 · Tridev Shreeji Associates
Ananta
possession by Aug 2026 · K Ajmera Developers
AAI Satidevi Paradise
possession by Sep 2026 · Shreenath Developers
Laizer Elegance
Not filing quarterly progress reports · possession by Sep 2026 · Laizer Builders & Developers
THE NEW Anand Deep CHS LTD
possession by Sep 2026 · Shreejee Buildcon
Tirupati Apartments Chsl
possession by Oct 2026 · Tirupati Aparmtnets CO Operative Housing

Major developers building in Mulund West

Other RERA-registered projects in Mumbai Suburban

Olympia C D
declared completion Dec 2025 · Nirmal Developers
Olympus
declared completion Dec 2024 · Vaibhavlaxmi Builders And Developers
OM Aarti
declared completion Dec 2025 · C H Patil AND Sons LLP
OM Amar Shakti
possession by Dec 2027 · Shree Shakti Realty
Om Ambe Smruti
possession by Dec 2026 · Oscar Infrastructure Private Limited
OM Dhanlaxmi Heights
possession by Dec 2026 · V P Realty

What to verify (QPR non-filer)

  1. Cross-check the developer's last QPR filing date on the MahaRERA portal — non-filing can indicate stalled construction.
  2. Visit the site (or request a third-party inspection report) to verify actual construction progress.
  3. If no QPR has been filed for more than two quarters, file a complaint with MahaRERA for non-disclosure.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026