Mumbai/Project record

MahaRERA · the public record

Palava Verde A - E

Palava · PALAVA DWELLERS PVT LTD

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 May 2025declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 May 2025

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51700020267

Delivery and registration

When is the project declared for completion?

Palava Verde A - E is registered with MahaRERA as P51700020267 and the promoter has declared completion for 30 May 2025.

30 May 2025

declared completion

16months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51700020267
Registered on30 Mar 2019
Promoter-declared completion30 May 2025
Current statusCertificate Signed
Against todayabout 16 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Palava Verde A - E record 26 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Deregistered — MahaRERA has deregistered this project — it is off the register.
  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (FY 2025-2026).

Promoter record

What else is this promoter on record for?

Palava Dwellers is the promoter of record on 86 projects registered with MahaRERA, 13 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

86projects

registered with MahaRERA

13flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Palava Verde A - E in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date.

BuildingWingsFloorsDeclared completion
Palava Verde A1-31 May 2024
Palava Verde B1-31 May 2024
Palava Verde C1-31 May 2024
Palava Verde D1-31 May 2024
Palava Verde E1-31 May 2024

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Legal & Litigation

The promoter has declared 2 court cases on this project to MahaRERA. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your home. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
Civil Judge Jd Kalyan5862016Files Say Ws
Civil Judge Jd Kalyan2842015Files Say Ws

Location, Land & Connectivity

Located at Palava, Kalyan Shifphata Road Palava, Mumbai City, Mumbai City, 421204. Per the filed land record, the plot is bounded to the north by 63 by 2 and 64 by 2, to the south by 61 and 62, to the east by 53 by 1 and 148 by 13 and to the west by 63 by 2. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Palava Dwellers PVT LTD is the promoter on 10 MahaRERA-registered projects, of which 5 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

See every Palava Dwellers PVT LTD project & its RERA track record →

Other flagged projects by Palava Dwellers PVT LTD

Palava Dwellers PVT LTD
Deregistered by MahaRERAThane
Palava Dwellers PVT LTD
Deregistered by MahaRERAThane
Palava Dwellers PVT LTD
Deregistered by MahaRERAThane
Palava Dwellers PVT LTD
Deregistered by MahaRERAThane

Other RERA-registered projects in Dombivali

Runwal Gardens Phase 4 Bldg No. 33-34
possession by Sep 2026 · Runwal Residency Private Limited
Sai Siddhi Residency
possession by Sep 2026 · Devendra Damodar Patil
Alimkar Heights
possession by Oct 2026 · Alimkar & Sons
Neelkamal Residency AND Business Park
possession by Dec 2026 · Neelkamal Buildco
Paramount
possession by Dec 2026 · Metro Dream Homes
Auroville Wing C AND D
possession by Dec 2026 · Arya Construction

Major developers building in Dombivali

Other RERA-registered projects in Thane

Palm Beach Galleria
declared completion Jan 2021 · VEE Square Hitech Infra PVT LTD
Palm Galaxy
possession by Dec 2026 · SAI Lifestyle
Palm Gardens
declared completion Dec 2022 · ECO Realties PVT LTD
Palm Riveria
possession by Dec 2033 · YES Realty
Palm View AND Swanand CHS
possession by Dec 2026 · V J Consultants
Panchratna Sapphire
possession by Mar 2027 · Pancharatna Developers

What to verify (inactive registration)

  1. Download the MahaRERA order stating the reason for deregistration or suspension — this is public on the portal.
  2. Check whether the developer has filed a challenge in the Appellate Tribunal and whether the order is stayed.
  3. Do not make any further payments until the registration status is restored or you obtain legal advice.
  4. Contact MahaRERA's helpdesk for guidance on alternative arrangements or pending dues.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026