Palava Verde A - E

P51700020267 · Palava · promoter Palava Dwellers Pvt

Certificate SignedDue 30 May 2025

Delivery & Registration

MahaRERA registrationP51700020267
Registered on30 Mar 2019
Promoter-declared completion30 May 2025
Current statusCertificate Signed
Against todayabout 14 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Palava Dwellers Pvt is the promoter of record on 83 projects, of which 12 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date.

BuildingWingsFloorsDeclared completion
Palava Verde A1-31 May 2024
Palava Verde B1-31 May 2024
Palava Verde C1-31 May 2024
Palava Verde D1-31 May 2024
Palava Verde E1-31 May 2024

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Legal & Litigation

The promoter has declared 2 court cases on this project to MahaRERA. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your flat. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
Civil Judge Jd Kalyan5862016Files Say Ws
Civil Judge Jd Kalyan2842015Files Say Ws

Location, Land & Connectivity

Located at Palava, Kalyan Shifphata Road Palava, Mumbai City, Mumbai City, 421204. Per the filed land record, the plot is bounded to the north by 63 by 2 and 64 by 2, to the south by 61 and 62, to the east by 53 by 1 and 148 by 13 and to the west by 63 by 2. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Palava Dwellers PVT LTD is the promoter on 10 MahaRERA-registered projects, of which 5 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

See every Palava Dwellers PVT LTD project & its RERA track record →

Other flagged projects by Palava Dwellers PVT LTD

Palava Dwellers PVT LTD
Deregistered by MahaRERAThane
Palava Dwellers PVT LTD
FlaggedThane
Palava Dwellers PVT LTD
Deregistered by MahaRERAThane
Palava Dwellers PVT LTD
FlaggedThane
Palava Dwellers PVT LTD
Deregistered by MahaRERAThane
Palava Dwellers PVT LTD
FlaggedThane

Other RERA-registered projects in Dombivali

Balaji Estate
possession by Jul 2026 · M/s. Sai Balaji Buildcon
Jayram Heights
possession by Jul 2026 · Ashapura Enterprises
Pearl B
possession by Jul 2026 · Lodha Developers Limited
Runwal Gardens Phase 4 Bldg No. 33-34
possession by Sep 2026 · Runwal Residency Private Limited
Sai Siddhi Residency
possession by Sep 2026 · Devendra Damodar Patil
Alimkar Heights
possession by Oct 2026 · Alimkar & Sons

Major developers building in Dombivali

Other RERA-registered projects in Thane

Palava Viento A To D
declared completion Mar 2018 · Palava Dwellers Private Limited
Palava Vista A To D
declared completion Apr 2018 · Palava Dwellers Private Limited
Pallavi Palace
declared completion Mar 2026 · Jeevan Tukaram Joshi
Palm
declared completion May 2021 · Pranjee Properties Pvt. Ltd
Palm Galaxy
possession by Dec 2026 · SAI Lifestyle
Palm Gardens
declared completion Dec 2022 · ECO Realties PVT LTD

What to verify (inactive registration)

  1. Download the MahaRERA order stating the reason for deregistration or suspension — this is public on the portal.
  2. Check whether the developer has filed a challenge in the Appellate Tribunal and whether the order is stayed.
  3. Do not make any further payments until the registration status is restored or you obtain legal advice.
  4. Contact MahaRERA's helpdesk for guidance on alternative arrangements or pending dues.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.