MahaRERA Property Intelligence · Mumbai Suburban

ROOPNIKETAN CO.OPERATIVE HOUSING SOCIETY LTD.

P51800051469 · MULUND EAST · promoter Shree Shingar Constructions

Certificate SignedDue 30 Jun 2026

Delivery & Registration

MahaRERA registrationP51800051469
Registered on23 Jun 2023
Promoter-declared completion30 Jun 2026
Current statusCertificate Signed
Against todayabout 1 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Shree Shingar Constructions is the promoter of record on 2 projects, of which none currently carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Construction Progress

MahaRERA's cost filing puts construction at ~85.0% of the estimated project cost incurred as of the last certificate (₹19.92 Cr spent against a ₹23.44 Cr estimate). This financial % is the regulator's own proxy for how much is physically built — the closest public read on real progress, and one a brochure never shows. The declared completion date has already passed while the cost-incurred filing sits at ~85.0% — a wide gap between the promise and the money actually spent on site.

Cost-incurred % as last certified to MahaRERA; it can lag on-site reality between filings. Confirm the current stage and the latest Form 2 before you book.

Sales & Inventory

Of 42 homes filed with MahaRERA, 25 are sold/booked (24 with registered agreements + 1 booked) and 17 remain available (~60% sold) — selling steadily. Buyers have committed ₹21.28 Cr in agreement value so far. Of that, ₹16.40 Cr (~77%) is already collected, ₹4.88 Cr receivable — a read on how far along these sales really are. Note: the project registers 80 homes in total, but this sold/unsold inventory filing covers only 42 of them — the other 38 aren't in the ledger yet. Ask the builder what they are (an unreleased phase, held-back stock, or non-saleable/car-park units) before reading too much into the percentage. This is the promoter's own reported inventory as at the last compliance filing; confirm current availability directly.

What buyers actually paid: across 25 registered agreements, the effective carpet rate is ₹16,007/sqft (typical range ₹15,757–₹19,458) — computed from the agreement values and carpet areas the promoter filed, not broker quotes. Compare your quote against this before negotiating.

The unsold units on the filing — if you're quoted a unit NOT on this list, ask why it shows as sold/booked on the RERA record:

FloorUnitCarpetReckoner value
Floor 141401636 sqft (59.13 sqm)₹10.00 Lakh
Floor 171701768 sqft (71.39 sqm)₹1.15 Cr
Floor 171702565 sqft (52.52 sqm)₹85.07 Lakh
Floor 181801768 sqft (71.39 sqm)₹1.15 Cr
Floor 181802565 sqft (52.52 sqm)₹85.07 Lakh
Floor 181803374 sqft (34.72 sqm)₹56.35 Lakh
Floor 191902565 sqft (52.52 sqm)₹85.07 Lakh
Floor 191904500 sqft (46.43 sqm)₹75.31 Lakh
Floor 201903374 sqft (34.72 sqm)₹56.35 Lakh
Floor 202001768 sqft (71.39 sqm)₹1.15 Cr
Floor 202002565 sqft (52.52 sqm)₹85.07 Lakh
Floor 212101768 sqft (71.39 sqm)₹1.15 Cr
Floor 212102565 sqft (52.52 sqm)₹85.07 Lakh
Floor 212103374 sqft (34.72 sqm)₹56.35 Lakh
Floor 212104500 sqft (46.43 sqm)₹68.47 Lakh
Floor 6602565 sqft (52.52 sqm)₹77.34 Lakh
Floor 6604500 sqft (46.43 sqm)₹68.47 Lakh

⚠ The inventory filing also declares: 7 reserved. Before booking, confirm YOUR unit appears in none of these lists and get any lender NOC in writing.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+21 and 80 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
ROOPNIKETAN COOPERATIVE HOUSING SOCIETY1G+2180-

Unit mix on the filing: 80 residential.

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 1 time. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
31 Dec 202530 Jun 2026Delay on account of Amendment in Plan

Location, Land & Connectivity

Located at MULUND EAST, SANT TUKARAM ROAD, Kurla, Mumbai Suburban, 400081. Per the filed land record, the plot is bounded to the north by NEELKANTH SOCIETY, to the south by ROAD AND ALOK SOCIETY, to the east by SANT TUKARAM ROAD and to the west by CHINTAMANI SOCIETY. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~8 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Powai / Hiranandani business park8 km
Andheri MIDC / SEEPZ10 km
Chhatrapati Shivaji Int'l Airport13 km
Bandra Kurla Complex (BKC)15 km
Lower Parel / Worli business district23 km
Nariman Point / Fort30 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Shree Shingar Constructions Private Limited is the promoter on 2 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

Other RERA-registered projects in Mulund East

Abundance
possession by Sep 2026 · Goodwill Developers
Jagdale Giriraj
possession by Sep 2026 · Jagdale Infrastructure Pvt. Ltd.
Richmond Ananya
possession by Sep 2026 · Divine Enterprises
Mithagar Road Ekta Chsl
possession by Dec 2026 · Palan Realty Private Limited
Bimal Apartment Chsl
possession by Dec 2026 · Rite Builders & Developers
Govind Prakash SRA CHS LTD
possession by Dec 2026 · Omsai Developers

Major developers building in Mulund East

Other RERA-registered projects in Mumbai Suburban

Rooprajat Enclave
possession by Dec 2026 · Siddhivinayak Developers
Roopvijay CHS Limited
declared completion Apr 2023 · Shreeji Parshvanath Infra Ventures LLP
Roots
declared completion Sep 2023 · Mahindra Lifespace Developers Limited
Rosalia Apartments
declared completion Jun 2023 · Kusum Associates
Rosary Villa Co Operative Housing Society Limited
declared completion Mar 2018 · Jay Vee Construction
Rose Blossom Chsl
possession by Aug 2026 · Vini Developers

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026