Sumit Lata

Sion · Sumit Snehashish Venture

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Jan 2021declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Jan 2021

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51900012481

Delivery and registration

When is the project declared for completion?

Sumit Lata is registered with MahaRERA as P51900012481 and the promoter has declared completion for 30 Jan 2021.

30 Jan 2021

declared completion

68months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51900012481
Registered on01 Sep 2017
Promoter-declared completion30 Jan 2021
Current statusCertificate Signed
Against todayabout 68 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Sumit Lata record 15 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 15 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Sumit Snehashish Venture is the promoter of record on 2 projects registered with MahaRERA, none of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

2projects

registered with MahaRERA

0flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Sumit Lata in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+19.

BuildingWingsFloorsDeclared completion
Sumit Lata PHASE I1G+19-
Sumit Lata PHASE II1G+4-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered30 Jul 2020The construction of building is completed in all aspects and we have received NOC for OC from Fire Department & are in process of applying for Occupation Certificate. We request y

Location, Land & Connectivity

Located at Sion, Borivali, Mumbai Suburban, 400022. Per the filed land record, the plot is bounded to the north by Road No 24b, to the south by Road No 18 Sion Hospital, to the east by Ashalaya Building and to the west by Road No 24. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~105 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Hinjewadi Rajiv Gandhi IT Park105 km
Baner–Balewadi belt110 km
Pune Junction / city centre121 km
Pune Int'l Airport (Lohegaon)122 km
Kharadi / EON IT Park126 km
Magarpatta / Hadapsar IT126 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Sion

Runwal Timeless
possession by Sep 2026 · Runwal Developers Limited
Harsh Tulip
possession by Oct 2026 · Harsh Developers & Infrastructure LL
Lodha NCP Tower - 1
possession by Dec 2026 · Lodha Developers Limited
Raunak Centrum
possession by Dec 2026 · Raunak Jigna Associates
Shankesh Crown
possession by Dec 2026 · H. Mehta Realtors LLP
Shreeji Palazzo
possession by Dec 2026 · Excellent Enterprise

Major developers building in Sion

Other RERA-registered projects in Mumbai City

Sumukh Plaza
declared completion Dec 2025 · Dharmesh Construction CO.
Sunshine Infinity
declared completion Dec 2019 · SQ Infrastructure Private Limited
Sunstone Epitome
possession by Dec 2028 · Sunstone Constructions
Supreme Melange
declared completion Jun 2024 · Supreme Ventures LLP
Suraj Apartments
possession by Dec 2026 · Mala Co-Operative Housing Society Limite
Suraj Aureva
possession by Dec 2031 · Suraj Estate Developers LTD

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026