MahaRERA Property Intelligence · Mumbai Suburban

Tirumala Habitats

P51800004278 · Mulund (W) · promoter Aap Realtors Ltd

Certificate SignedDue 30 Jun 2019

Delivery & Registration

MahaRERA registrationP51800004278
Registered on09 Aug 2017
Promoter-declared completion30 Jun 2019
Current statusCertificate Signed
Against todayabout 85 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+46.

BuildingWingsFloorsDeclared completion
Tirumala Habitats1G+46-

Complaints & Orders

15 complaints are on the MahaRERA record for this project, with orders passed in 14. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.

Complaint no.FiledPartiesStatus
CC00600000000092429/09/2017Komal Patel vs Aditya Kediaorder passed
CC00600000002298411/02/2018Shubha Shetty vs AAP Realtors Ltdorder passed
CC00600000005569409/08/2018Possession delay vs Aditya Kediaorder passed
CC00600000005668623/10/2018Prashant B Bhadra vs AAP REALTORS LTDorder passed
CC00600000019729821/06/2021Abhinav Angirish vs Aap Realtors Pvt. Ltd., Aditya Kedia and Kirti Kediaorder passed
CC00600000019737322/06/2021Abhinav Angirish vs Aap Realtors Ltd., Aditya Kedia and Kirti Kediaorder passed
CC00600000019743529/06/2021Rahul Wadhwani vs Aap Realtors Ltd., Aditya Kedia and Kirti Kediaorder passed
CC00600000019830904/10/2021Mrs. Geeta Bhavesh Bhanushali, Mr Bhavesh Bhanushali and Mr. Kalyanji Bhanushali vs Transcon Skycity Private Limitedorder passed
CC00600000019830804/10/2021Sheela Bhanushali and Govind Bhanushali vs Transcon Skycity Private Limitedorder passed
CC00600000030362109/12/2022sonali desai vs AAP Realtors Ltd.pending / no order on file
CC00600000039648203/07/2023Rahul Anantrai Mehta vs Aap Realtors Limitedorder passed
CC00600000039648403/07/2023Minal Hitesh Bagthariya vs Aap Realtors Limitedorder passed
CC00600000041868902/01/2024SAPNA KUSUMGAR vs AAP REALTORS LTDorder passed
CC00600000042868902/01/2024SIDDHARTH KUSUMGAR vs AAP REALTORS LTDorder passed
CC00600000042870203/01/2024YOGESH KUSUMGAR vs AAP REALTORS LTDorder passed

Legal & Litigation

The promoter has declared 14 court cases on this project to MahaRERA. 8 are still pending. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your flat. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
The High Court Bombay35012006The Suit Is Pending
The Charity Commissioner Maharashtra22014Pending
The High Court Bombay34172003Pending
The High Court BombayCAA/1002015Pending
The High Court BombayCOAPP/722015Pending
ReraCC006000000000242018Disposed
ReraCC0060000000556942018Disposed
ReraCC0060000000566862018Disposed
ReraCC0060000000229842018Disposed
Rera Appellate TribunalAT0060000000109892019Pending
Bombay High Court128502018Pending
Small Cause Court Mumbai3512016Disposed
Bombay City Civil11662018Pending
Bombay City Ciivil11672018Pending

Location, Land & Connectivity

Located at Mulund (W), BalRajeshwar Road, Kurla, Mumbai Suburban, 400080. Per the filed land record, the plot is bounded to the north by 622B-2pt, to the south by 622B-2pt, to the east by 622B-2pt and to the west by 622B-2pt. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~9 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Powai / Hiranandani business park9 km
Andheri MIDC / SEEPZ10 km
Chhatrapati Shivaji Int'l Airport14 km
Bandra Kurla Complex (BKC)15 km
Lower Parel / Worli business district24 km
Nariman Point / Fort32 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Mulund West

Kailash Residency
possession by Aug 2026 · Tridev Shreeji Associates
Ananta
possession by Aug 2026 · K Ajmera Developers
AAI Satidevi Paradise
possession by Sep 2026 · Shreenath Developers
Laizer Elegance
Not filing quarterly progress reports · possession by Sep 2026 · Laizer Builders & Developers
THE NEW Anand Deep CHS LTD
possession by Sep 2026 · Shreejee Buildcon
Tirupati Apartments Chsl
possession by Oct 2026 · Tirupati Aparmtnets CO Operative Housing

Major developers building in Mulund West

Other RERA-registered projects in Mumbai Suburban

Tirupati Apartments Chsl
possession by Oct 2026 · Tirupati Aparmtnets CO Operative Housing
Tirupati Height
declared completion Feb 2023 · Tirupati Developer
Titanium Rajshree
possession by Nov 2028 · Orange Infra Housing LLP
Titirsha CO OP HSG SOC LTD
declared completion Dec 2025 · Titirsha CO OP HSG SOC LTD
Tivon Park Wing E And F
possession by Dec 2026 · D S Developers
Tivon Park Wing G And H
possession by Dec 2026 · D.s. Developers

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026