MahaRERA Property Intelligence · Raigarh
P52000008453 · promoter Xrbia Developers Ltd
| MahaRERA registration | P52000008453 |
| Registered on | 19 Aug 2017 |
| Promoter-declared completion | 30 Mar 2025 |
| Current status | Certificate Signed |
| Against today | about 16 months past the declared date |
MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.
Across MahaRERA, Xrbia Developers Ltd is the promoter of record on 27 projects, of which 16 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.
The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+7.
| Building | Wings | Floors | Declared completion |
|---|---|---|---|
| A4 | 1 | G+7 | 31 Mar 2024 |
| B1 | 1 | G+7 | 31 Mar 2024 |
| B2 | 1 | G+7 | 31 Mar 2024 |
| B3 | 1 | G+7 | 31 Mar 2024 |
| C1 | 1 | G+7 | 31 Mar 2024 |
| C2 | 1 | G+7 | 31 Mar 2024 |
| C3 | 1 | G+7 | 31 Mar 2024 |
| C4 | 1 | G+7 | 31 Mar 2024 |
| C5 | 1 | G+7 | 31 Mar 2024 |
| C6 | 1 | G+7 | 31 Mar 2024 |
| D1 | 1 | G+7 | 31 Mar 2024 |
| D2 | 1 | G+7 | 31 Mar 2024 |
| D3 | 1 | G+7 | 31 Mar 2024 |
| D4 | 1 | G+7 | 31 Mar 2024 |
| E1 | 1 | G+7 | 31 Mar 2024 |
| E2 | 1 | G+7 | 31 Mar 2024 |
26 complaints are on the MahaRERA record for this project, with orders passed in 26. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.
| Complaint no. | Filed | Parties | Status |
|---|---|---|---|
| CC006000000000529 | 10/09/2017 | CHEATED BY BUILDER vs M/S XRBIA DEVELOPERS LTD. | order passed |
| CC006000000023554 | 03/03/2018 | XRBIA DEVELOPERS LTD vs Sharad Dattanand Kalyanpur | order passed |
| CC006000000089619 | 07/06/2019 | mahendra dhanaji pawar vs xrbia developers Ltd | order passed |
| CC006000000196352 | 13/03/2021 | SUNIL SHANAKAR PHALAKE vs RAHUL R NAHAR | order passed |
| CC006000000195556 | 19/01/2021 | JITESH GAJANAN THORAT vs XRBIA DEVELOPERS LTD | order passed |
| CC006000000196353 | 13/03/2021 | SANDESH SHANKAR PATIL vs RAHUL N NAHAR | order passed |
| CC006000000199085 | 19/11/2021 | PANDHARINATH K MULAYE vs XERBIA DEVELOPERS LTD. | order passed |
| CC006000000209446 | 17/12/2021 | Rahul Nahar vs Rahul Nahar | order passed |
| CC006000000210563 | 28/03/2022 | Vivek Sawant vs XRbia | order passed |
| CC006000000334110 | 26/01/2023 | Sharad Kundlik Ghoderao vs Xrbia Developers Limited | order passed |
| CC006000000354398 | 18/02/2023 | Joanna Dantis vs Xrbia Developers Limited | order passed |
| CC006000000375154 | 18/04/2023 | Vivek Anil Sawant vs Xrbia Developers Limited | order passed |
| CC006000000395470 | 22/05/2023 | Bhushan Adinath Vardhamane vs Xrbia Developers Ltd | order passed |
| CC006000000480314 | 17/05/2024 | Rani Gonsalvez vs XRBIA DEVELOPES | order passed |
| CC006000000591395 | 02/08/2024 | Amodh Rane vs XRBIA DEVELOPERS | order passed |
| CC12401096 | 11/12/2024 | Vivek Anil Sawant vs Xrbia Developers Ltd | order passed |
| CC12502081 | 25/06/2025 | Indrajit Rajkumar Kundu vs Xrbia Developers Ltd | order passed |
| CC12502078 | 25/06/2025 | Ragini Rakesh Bhosle vs Xrbia Developers Ltd | order passed |
| CC12502162 | 30/06/2025 | Deepak More vs Xrbia Developers Ltd | order passed |
| CC12502478 | 19/07/2025 | OMKAR PRAKASH CHAVAN vs Xrbia Developers Ltd | order passed |
| CC12502543 | 23/07/2025 | Priyanka Poojary vs Xrbia Developers Ltd | order passed |
| CC12502822 | 12/08/2025 | Shilpa and Sandeep Surve Surve vs Xrbia Developers Ltd | order passed |
| CC12503273 | 14/09/2025 | Shivprasad Shetye vs Xrbia Developers Ltd | order passed |
| CC12503597 | 09/10/2025 | Dominic and Flavia Pereirra vs Xrbia Developers Ltd | order passed |
| CC12504131 | 24/11/2025 | VIJAY GANGARAM PEVEKAR vs Xrbia Developers Ltd | order passed |
| CC12504674 | 29/12/2025 | Ram Dattaram Dalvi vs Xrbia Developers Ltd | order passed |
The promoter has declared 1 court case on this project to MahaRERA. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your flat. This is declared by the promoter; there may be further cases not on the RERA record.
| Court | Case no. | Year | Status |
|---|---|---|---|
| Civil Judge Junior Division Karjat | REGULAR CIVIL SUIT NO 64/2001 | 2001 | For Evidence Of Plaintiff |
Located at Pune City, Pune, 410201. Per the filed land record, the plot is bounded to the north by S NO 10 18, to the south by S NO 21 24, to the east by S NO 19 23 and to the west by S NO 21. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.
The nearest major job hub is ~45 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.
| Landmark | Straight-line |
|---|---|
| Powai / Hiranandani business park | 45 km |
| Andheri MIDC / SEEPZ | 49 km |
| Bandra Kurla Complex (BKC) | 49 km |
| Chhatrapati Shivaji Int'l Airport | 49 km |
| Lower Parel / Worli business district | 54 km |
| Nariman Point / Fort | 56 km |
Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.
🔒 The verdict & buyer playbook · Compliance report
The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.
🔒 Unit-by-unit guidance · Unit Guidance report
Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.
🔒 Full financial records — escrow, funding & the document catalog · Compliance report
The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.
Should you buy in XRBIA VANGANI - PH 1?
This page is the free MahaRERA filing summary. The full RERA Property Intelligence Report gives you the full regulatory standing, declared court litigation, buyer-complaint and adjudication history, quarterly-progress-report discipline, the builder's MahaRERA-wide track record, the building/tower breakdown, and the sanctioned layout plan. See a real one first:
Sample: Lodha Kandivali – Tower 2 → · browse all sample reports →
Compliance Report · ₹999
The regulator’s filing record, read · 1 working day
Scan with any UPI app to pay · quietlist@kotak
Unit Guidance Report · ₹2,999
Everything, down to which unit · 1 working day
Not useful to your decision? Full refund — no questions asked.
Scan with any UPI app to pay · quietlist@kotak
Paying from outside India? Pay $15 (Compliance) or $39 (Unit Guidance) via PayPal, or email hello@quietlist.in for a card invoice. Prefer to talk first, or have a portfolio to check? Same address. An information aid for your own due diligence, not legal or investment advice.
Free · Watch this project
We'll email you when this project's RERA record changes.
Xrbia Developers Ltd is the promoter on 10 MahaRERA-registered projects, of which 9 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:
See every Xrbia Developers Ltd project & its RERA track record →
Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.
Last checked against the RERA register: 27 Jul 2026