MahaRERA Property Intelligence · Pune

18 Nests

P52100029709 · Kharadi · promoter Asr Constructions

Certificate SignedDue 31 Dec 2024

Delivery & Registration

MahaRERA registrationP52100029709
Registered on26 Jun 2021
Promoter-declared completion31 Dec 2024
Current statusCertificate Signed
Against todayabout 19 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+5.

BuildingWingsFloorsDeclared completion
18 Nests1G+5-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 4 times. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
31 Dec 202130 Jun 2022Project execution got delayed due to covid and labour crunch. Everything has now been streamlined and we are set to complete by end of April 2022.
31 Dec 202131 Mar 2023Construction complete. Waiting on due diligence for completion certificate by the corporation.
31 Dec 202131 Dec 2023Completion certificate is applied but yet to received same from corporation They had issue of zoning given by them 5 years before
31 Dec 202131 Dec 2024Applied for completion certificate 16 month back corporation officers having issues regarding zoning given by them for which they are taking corrective steps

Location, Land & Connectivity

Located at Kharadi, Rajaram Patil Nagar, Pune City, Pune, 411014. Per the filed land record, the plot is bounded to the north by Playground from S No 63, to the south by Private Plot No 24, to the east by Road and to the west by Road. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~159 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Pune Int'l Airport (Lohegaon)158 km
Kharadi / EON IT Park159 km
Magarpatta / Hadapsar IT162 km
Pune Junction / city centre166 km
Baner–Balewadi belt172 km
Hinjewadi Rajiv Gandhi IT Park174 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Kharadi

Satyam Shivam Phase 2
Not filing quarterly progress reports · possession by Sep 2026 · Vijayalaxmi Associates
The Collection - W2 And W7
possession by Sep 2026 · Bramhacorp Limited
Unique Youtopia Phase III
possession by Sep 2026 · Unique Associates
Spandan
possession by Oct 2026 · Evolve Infra
Ganga Platinum A
possession by Oct 2026 · Shree Balaji Associates Pune LLP
Percept Bounty 3
possession by Dec 2026 · Prime Estate

Major developers building in Kharadi

Other RERA-registered projects in Pune

18 SKY
possession by Mar 2029 · Swastik Developers
19 Grand West - C Wing And D Wing
declared completion Dec 2024 · Shivam Development Ventures LLP
19 Grand West Wing A
declared completion Dec 2024 · Shivam Development Ventures LLP
19 Grand West Wing B
declared completion Nov 2022 · Shivam Development Ventures LLP
1976 Sadashiv Peth
declared completion Nov 2023 · Niwas Enterprises
198 City Hub
declared completion Jun 2026 · Urban Syndicate

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026