MahaRERA Property Intelligence · Pune

Esclare Royale

P52100005660 · promoter Esclare Realty Llp

Certificate SignedDue 31 Mar 2019

Delivery & Registration

MahaRERA registrationP52100005660
Registered on11 Aug 2017
Promoter-declared completion31 Mar 2019
Current statusCertificate Signed
Against todayabout 88 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+6.

BuildingWingsFloorsDeclared completion
Esclare Royale1G+6-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 1 time. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
31 Dec 201831 Mar 2019Non Availability of Material.

Location, Land & Connectivity

Located at Pune City, Pune, 411014. Per the filed land record, the plot is bounded to the north by Road, to the south by Survey No 5 P, to the east by Road and to the west by Survey No 5 P. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~169 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Hinjewadi Rajiv Gandhi IT Park169 km
Baner–Balewadi belt174 km
Pune Int'l Airport (Lohegaon)182 km
Pune Junction / city centre183 km
Kharadi / EON IT Park186 km
Magarpatta / Hadapsar IT188 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Kharadi

Satyam Shivam Phase 2
Not filing quarterly progress reports · possession by Sep 2026 · Vijayalaxmi Associates
The Collection - W2 And W7
possession by Sep 2026 · Bramhacorp Limited
Unique Youtopia Phase III
possession by Sep 2026 · Unique Associates
Spandan
possession by Oct 2026 · Evolve Infra
Ganga Platinum A
possession by Oct 2026 · Shree Balaji Associates Pune LLP
Percept Bounty 3
possession by Dec 2026 · Prime Estate

Major developers building in Kharadi

Other RERA-registered projects in Pune

Eshaan
possession by Dec 2026 · Naman Realty
Eshan Culture
declared completion Feb 2024 · Eshan Developers
Espacio - A AND B
possession by Dec 2026 · Knight West Realty LLP
Espacio - Commercial
declared completion Jun 2025 · Knight West Realty LLP
Espacio - Wing C D AND E/mhada
declared completion Dec 2025 · Knight West Realty LLP
Espree Eminence
declared completion Dec 2022 · Espree Realtors

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026