MahaRERA Property Intelligence · Pune

KOSMIC KOURTYARD PHASE 1

P52100032462 · Wagholi · promoter Triaa Lifespaces Llp

Certificate SignedDue 31 Dec 2025

Delivery & Registration

MahaRERA registrationP52100032462
Registered on04 Jan 2022
Promoter-declared completion31 Dec 2025
Current statusCertificate Signed
Against todayabout 7 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+15.

BuildingWingsFloorsDeclared completion
Wing - A41G+15-
Wing - A51G+15-
Wing - A61G+15-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at Wagholi, Wagholi, Pune City, Pune, 412207. Per the filed land record, the plot is bounded to the north by By Gat No 1127, to the south by By Gat No 1144, to the east by By Wagholi Avhalwadi Road and to the west by By Gat No 1129. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Triaa Lifespaces LLP is the promoter on 2 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

Other flagged projects by Triaa Lifespaces LLP

Other RERA-registered projects in Wagholi

Solvista Phase 1
possession by Sep 2026 · SSL Infrabuild LLP
Aurora 2
possession by Sep 2026 · Magnum Developers
Elite
possession by Sep 2026 · V & J Developers
Enliven Home B Wing Phase 2
possession by Sep 2026 · Siddhivinayak Properties
Godrej Greens
possession by Sep 2026 · Dream World Landmarks LLP
Kharadi Pune Phase I - Tower 1 To 4
possession by Oct 2026 · Lodha Developers Limited

Major developers building in Wagholi

Other RERA-registered projects in Pune

Kosmic Kourtyard Phase 2
possession by Dec 2028 · Triaa Lifespaces LLP
Kothrud Baug A4 B1
declared completion Jul 2022 · Grand Maratha Constructions Private Limi
Kothrud Pune -Tower A And B
possession by Sep 2029 · Lodha Developers Limited
Kothrud Vishwa
possession by Dec 2026 · J D Construction
Kotibhaskar Business Court And Mahati Residency
declared completion Apr 2023 · Kotibhaskar Infrastructures &develop
Kotwal Business Zone Building A
declared completion Aug 2025 · Vishhram Developers

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026