MahaRERA Property Intelligence · Pune

MEERA CASA

P52100015062 · Kharadi · promoter Dgcon Realtors

Certificate SignedDue 31 Dec 2021

Delivery & Registration

MahaRERA registrationP52100015062
Registered on22 Jan 2018
Promoter-declared completion31 Dec 2021
Current statusCertificate Signed
Against todayabout 55 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+6.

BuildingWingsFloorsDeclared completion
MEERA CASA1G+631 Dec 2020

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 1 time. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
31 May 201931 Dec 2021The delay in completion of Project is due to Financial issues and Present Covid-19 Pandemic situations.

Location, Land & Connectivity

Located at Kharadi, At Village Kharadi, Haveli, Pune, 411014. Per the filed land record, the plot is bounded to the north by S NO 31, to the south by Colony Road, to the east by S No 32 and to the west by Property Out of S No 27. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~1 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Kharadi / EON IT Park1 km
Pune Int'l Airport (Lohegaon)4 km
Magarpatta / Hadapsar IT4 km
Pune Junction / city centre7 km
Baner–Balewadi belt17 km
Hinjewadi Rajiv Gandhi IT Park21 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Kharadi

Satyam Shivam Phase 2
Not filing quarterly progress reports · possession by Sep 2026 · Vijayalaxmi Associates
The Collection - W2 And W7
possession by Sep 2026 · Bramhacorp Limited
Unique Youtopia Phase III
possession by Sep 2026 · Unique Associates
Spandan
possession by Oct 2026 · Evolve Infra
Ganga Platinum A
possession by Oct 2026 · Shree Balaji Associates Pune LLP
Percept Bounty 3
possession by Dec 2026 · Prime Estate

Major developers building in Kharadi

Other RERA-registered projects in Pune

Meera Heights
declared completion Mar 2023 · Moraya Realty
Meera Residency
declared completion Dec 2021 · Sagar Developers
Megapolis Mystic - C
declared completion Dec 2019 · Pegasus Properties Pvt. Ltd.
Megapolis Mystic - F
declared completion Feb 2025 · Pegasus Properties Pvt. Ltd.
Megapolis Mystic - G
possession by Dec 2026 · Pegasus Properties Pvt. Ltd.
Megapolis Mystic Phase 2
declared completion Mar 2020 · Pegasus Properties Pvt. Ltd.

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026