MahaRERA Property Intelligence · Pune

PRUTHVI EKDANTA HOMES PHASE II

P52100016032 · Kesnand Village · promoter Pruthvi Associates

Certificate SignedDue 31 Jul 2022

Delivery & Registration

MahaRERA registrationP52100016032
Registered on12 Apr 2018
Promoter-declared completion31 Jul 2022
Current statusCertificate Signed
Against todayabout 48 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Pruthvi Associates is the promoter of record on 24 projects, of which 5 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+7.

BuildingWingsFloorsDeclared completion
PRUTHVI EKDANTA HOMES PHASE II1G+731 Jul 2020

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at Kesnand Village, Kesnand - Wagholi Road, Haveli, Pune, 412207. Per the filed land record, the plot is bounded to the north by Property of Gulab Bhiva Satav, to the south by Property of Baban Shivram Satav, to the east by Property of Baban Shivram Satav and to the west by 20 Ft wide road. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~9 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Kharadi / EON IT Park9 km
Pune Int'l Airport (Lohegaon)11 km
Magarpatta / Hadapsar IT12 km
Pune Junction / city centre16 km
Baner–Balewadi belt26 km
Hinjewadi Rajiv Gandhi IT Park30 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

M/S Pruthvi Associates is the promoter on 2 MahaRERA-registered projects, of which 2 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other flagged projects by M/S Pruthvi Associates

M/S Pruthvi Associates
Past its declared completion datePune

Other RERA-registered projects in Wagholi

Solvista Phase 1
possession by Sep 2026 · SSL Infrabuild LLP
Aurora 2
possession by Sep 2026 · Magnum Developers
Elite
possession by Sep 2026 · V & J Developers
Enliven Home B Wing Phase 2
possession by Sep 2026 · Siddhivinayak Properties
Godrej Greens
possession by Sep 2026 · Dream World Landmarks LLP
Kharadi Pune Phase I - Tower 1 To 4
possession by Oct 2026 · Lodha Developers Limited

Major developers building in Wagholi

Other RERA-registered projects in Pune

Pruthvi Residency
declared completion Nov 2025 · Shri Siddhivinayak Developers
Pruthvi Tower
declared completion Mar 2025 · Vaishali Santosh Lokhande
Pulse
declared completion Jun 2026 · Donnish Realtors LLP
Punde Heights
possession by Dec 2027 · Pushkaraj Reality
Pune Baner Project-Tower 3
possession by Jun 2030 · Goel Ganga Ventures India Private Limite
Pune Baner Project-Tower 4 And 5
possession by Jun 2030 · Goel Ganga Ventures India Private Limite

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026