Pune/Project record

MahaRERA · the public record

RTC SILVER

WAGHOLI · YOGESH ANANDPAL GOYAL

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

13units filed as unsoldInventory · 18 September 2026
31 Oct 2025declared completionMahaRERA registration · read 12 Jul 2026
56registered unitsMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Oct 2025

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100032721

Delivery and registration

When is the project declared for completion?

RTC SILVER is registered with MahaRERA as P52100032721 and the promoter has declared completion for 31 Oct 2025.

31 Oct 2025

declared completion

11months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100032721
Registered on24 Jan 2022
Promoter-declared completion31 Oct 2025
Current statusCertificate Signed
Against todayabout 11 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for RTC SILVER record 16 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (FY 2025-2026).

Promoter record

What else is this promoter on record for?

Yogesh Anandpal Goyal is the promoter of record on 2 projects registered with MahaRERA, none of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

2projects

registered with MahaRERA

0flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

How much has actually been sold?

In RTC SILVER, 43 of 56 homes filed with MahaRERA are recorded as sold or booked, about 77%, and 13 remain available.

77%sold

43 of 56 homes

₹38.01 Cr

committed by buyers

Counts and agreement value as the promoter filed them at the last compliance date; this is the filed inventory, not current availability. Of that agreement value, ₹38.01 Cr (about 100%) is recorded as collected and ₹0 as receivable.

Source · MahaRERA sold/unsold inventory filing · read 12 Jul 2026

What buyers actually paid: across 43 registered agreements, the effective carpet rate is ₹7,921/sqft, with eight in ten falling between ₹7,007 and ₹9,367 — computed from the agreement values and carpet areas the promoter filed, not broker quotes.

The units recorded as unsold on the filing. The reckoner value is the government's ready-reckoner assessment the promoter filed against that unit, the figure stamp duty is charged on. It is not a price anyone paid, not an asking price, and not a valuation of the home.

FloorUnitCarpetGovt reckoner value
Floor 116,757 sqft (627.7 sqm)₹4.39 Cr
Floor 125,363 sqft (498.23 sqm)₹3.48 Cr
Floor 1010011,073 sqft (99.72 sqm)₹73.15 Lakh
Floor 101002884 sqft (82.1 sqm)₹60.22 Lakh
Floor 101004935 sqft (86.86 sqm)₹63.71 Lakh
Floor 1010051,006 sqft (93.42 sqm)₹68.53 Lakh
Floor 101006809 sqft (75.18 sqm)₹55.15 Lakh
Floor 101007884 sqft (82.1 sqm)₹60.22 Lakh
Floor 1111011,073 sqft (99.72 sqm)₹76.63 Lakh
Floor 111108979 sqft (90.94 sqm)₹69.88 Lakh
Floor 463,272 sqft (303.97 sqm)₹2.12 Cr
Floor 6604935 sqft (86.86 sqm)₹63.71 Lakh
Floor 77051,006 sqft (93.42 sqm)₹68.53 Lakh

No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing.

What the filings record, home by home

Read from MahaRERA on 18 September 2026

MahaRERA publishes, home by home, what this promoter filed: which homes are sold and which are not, the RERA carpet area of each, and for the sold ones the registered agreement value — the consideration filed for that specific home. On this project 43 homes carry one, and 13 of the 56 are recorded unsold.

Here is one of those unsold homes, priced against what buyers of the same home on other floors actually filed:

HomeCarpetFiled for the same home on other floorsBased on
1002884 sqftRs 69.75 lakh typical, over Rs 67.61 lakh to Rs 75.60 lakh5 filed on this stack, floors 6–11

A filed consideration is what was registered for one home. It is not a valuation, and MahaRERA does not publish the date of any of these agreements — read a range as a spread, not as a trend. An unsold row means no sale had been filed for it when we looked, which is a filing state, not a promise that the home is available to you today. Only one observation of this ledger so far: no change can be reported yet. This observation is an archived copy whose time is the moment the file was written, not a portal fetch time.

In RTC SILVER, 10 of the 13 unsold homes have agreements filed on their own stack. The Price Comparison Report gives each of them its own row — the filed agreements behind that stack listed in full, the government reckoner value the promoter filed against it, and whether it is mortgaged to a lender while still on the unsold list. Built from the filing itself, sent by email.

See the other 12 homes — ₹2,999 →

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+10 and 56 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
RTC SILVER B41G+1056-

Unit mix on the filing: 56 non-residential (shops/offices).

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered31 Oct 2025.

Location, Land & Connectivity

Located at WAGHOLI, PUNE NAGAR ROAD, Pune City, Pune, 412207. Per the filed land record, the plot is bounded to the north by OPEN SPACE, to the south by PLOT NO 1342 - PART, to the east by ROAD and to the west by PLOT NO 1 AND 6. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~3 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Kharadi / EON IT Park3 km
Pune Int'l Airport (Lohegaon)4 km
Magarpatta / Hadapsar IT7 km
Pune Junction / city centre10 km
Baner–Balewadi belt19 km
Hinjewadi Rajiv Gandhi IT Park24 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Yogesh Anandpal Goyal is the promoter on 2 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

Other flagged projects by Yogesh Anandpal Goyal

Yogesh Anandpal Goyal
FlaggedPune

Other RERA-registered projects in Wagholi

Aurora 2
possession by Sep 2026 · Magnum Developers
Elite
possession by Sep 2026 · V & J Developers
Enliven Home B Wing Phase 2
possession by Sep 2026 · Siddhivinayak Properties
Godrej Greens
possession by Sep 2026 · Dream World Landmarks LLP
Kharadi Pune Phase I - Tower 1 To 4
possession by Oct 2026 · Lodha Developers Limited
Defence Colony Pune Phase4
possession by Nov 2026 · Defence Colony Pune

Major developers building in Wagholi

Other RERA-registered projects in Pune

Rubeecon Tower
possession by Jun 2029 · Chaandrai Construction NP LLP
Rudra Dham Phase 1
declared completion Jan 2021 · Rudra Construction & Developers
Rudra Heritage
possession by Dec 2027 · Rudra Construction
Rudra Palace
declared completion Jul 2020 · Sunil Gajaram Kaware
Rudra Residency
declared completion Dec 2022 · S M Ventures
Rudradeep
declared completion Mar 2026 · Raghvendra Maharudra Tulshibagwale

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026