MahaRERA Property Intelligence · Pune

SHIV HILLS PHASE 2

P52100027023 · SHIV PALACE HSG CO-OP SOCIETY · promoter Trimurti Developers

Certificate SignedDue 30 Jun 2025

Delivery & Registration

MahaRERA registrationP52100027023
Registered on10 Nov 2020
Promoter-declared completion30 Jun 2025
Current statusCertificate Signed
Against todayabout 13 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Trimurti Developers is the promoter of record on 65 projects, of which 7 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+4.

BuildingWingsFloorsDeclared completion
SHIV HILLS PHASE 21G+4-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 1 time. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
30 Jun 202430 Jun 2025Due to UDCPR 2020, We will be getting additional FSI of 1191.59 sq.mtrs thus totalling B/up FSI of 2033.42 sq.mtrs Due to this No of Floors will also increase. Consent of 2/3 Allot

Location, Land & Connectivity

Located at SHIV PALACE HSG CO-OP SOCIETY, BJS ROAD, Haveli, Pune, 411014. Per the filed land record, the plot is bounded to the north by 6 M ROAD, to the south by PL NO 19 AND 20, to the east by 9 M ROAD and to the west by PL NO 25. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Trimurti Developers is the promoter on 12 MahaRERA-registered projects, of which 2 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

See every Trimurti Developers project & its RERA track record →

Other flagged projects by Trimurti Developers

Other RERA-registered projects in Kharadi

Satyam Shivam Phase 2
Not filing quarterly progress reports · possession by Sep 2026 · Vijayalaxmi Associates
The Collection - W2 And W7
possession by Sep 2026 · Bramhacorp Limited
Unique Youtopia Phase III
possession by Sep 2026 · Unique Associates
Spandan
possession by Oct 2026 · Evolve Infra
Ganga Platinum A
possession by Oct 2026 · Shree Balaji Associates Pune LLP
Percept Bounty 3
possession by Dec 2026 · Prime Estate

Major developers building in Kharadi

Other RERA-registered projects in Pune

Shiv Malhar
declared completion Sep 2018 · Swaraj Developers
Shiv Malhar
possession by Dec 2026 · Shiv Developers
Shiv Malhar Pride
possession by Sep 2028 · Not Available
Shiv Nisarg
declared completion Jan 2024 · Mangesh Vasant Gundal
Shiv Paradise
possession by Mar 2028 · Ranjit Ashok Taware
Shiv Park
declared completion Sep 2022 · Trimurti Developers

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026