SKKY VILLAS PHASE I

P52100024936 · WAGHOLI · promoter Arnav Construction

Certificate SignedDue 30 Mar 2022

Delivery & Registration

MahaRERA registrationP52100024936
Registered on12 Mar 2020
Promoter-declared completion30 Mar 2022
Current statusCertificate Signed
Against todayabout 52 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Arnav Construction is the promoter of record on 15 projects, of which 3 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at WAGHOLI, DOMKHEL WASTI ROAD , Haveli, Pune, 412207. Per the filed land record, the plot is bounded to the north by GAT NUMBER 1424, to the south by 12 METER WIDE ROAD BY GAT NUMBER 1402, to the east by GAT NUMBER 1420 and to the west by GAT NUMBER 1421 Part and 1422 Part. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Wagholi

Solvista Phase 1
possession by Sep 2026 · SSL Infrabuild LLP
Aurora 2
possession by Sep 2026 · Magnum Developers
Elite
possession by Sep 2026 · V & J Developers
Enliven Home B Wing Phase 2
possession by Sep 2026 · Siddhivinayak Properties
Godrej Greens
possession by Sep 2026 · Dream World Landmarks LLP
Kharadi Pune Phase I - Tower 1 To 4
possession by Oct 2026 · Lodha Developers Limited

Major developers building in Wagholi

Other RERA-registered projects in Pune

Skky Villas Phase II
declared completion Jun 2022 · Sameer Dattatray Bhadale
Skky Villas Phase III
declared completion Dec 2021 · Aditya Pride Realty
Sky 2 Cosmos
possession by Oct 2026 · Emperos Properties
Sky Bhumi
declared completion Mar 2025 · Sky Bhumi
SKY Blue
possession by Oct 2026 · Royal Realty
SKY County
possession by Dec 2027 · Deshmukh Developments

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026