VIJAYA RESIDENCY

Pune · NAJMA SHAMSHUDDIN SHAIKH

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 May 2018declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 May 2018

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100011934

Delivery and registration

When is the project declared for completion?

VIJAYA RESIDENCY is registered with MahaRERA as P52100011934 and the promoter has declared completion for 31 May 2018.

31 May 2018

declared completion

100months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100011934
Registered on01 Sep 2017
Promoter-declared completion31 May 2018
Current statusCertificate Signed
Against todayabout 100 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for VIJAYA RESIDENCY record 4 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 4 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Najma Shamshuddin Shaikh is the promoter of record on 5 projects registered with MahaRERA, 2 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

5projects

registered with MahaRERA

2flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for VIJAYA RESIDENCY in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+4.

BuildingWingsFloorsDeclared completion
VIJAYA RESIDENCY1G+431 May 2018

Legal and disputes

What disputes are disclosed?

1 complaint is on the MahaRERA record for VIJAYA RESIDENCY, with orders passed in 1 of them.

1complaint

1with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00500000002300314/05/2019Mr Ramesh Padal vs heena builder and promoterorder passed

Location, Land & Connectivity

Located at Pune City, Pune, 411014. Per the filed land record, the plot is bounded to the north by ROAD, to the south by ROAD, to the east by BY SHREE SAI PRASAD SOCIETY and to the west by BY THE PROPERTY OF MR SUSHANT KHUNE. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~121 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Hinjewadi Rajiv Gandhi IT Park121 km
Baner–Balewadi belt126 km
Pune Junction / city centre136 km
Pune Int'l Airport (Lohegaon)137 km
Kharadi / EON IT Park141 km
Magarpatta / Hadapsar IT142 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Kharadi

Satyam Shivam Phase 2
Not filing quarterly progress reports · possession by Sep 2026 · Vijayalaxmi Associates
The Collection - W2 And W7
possession by Sep 2026 · Bramhacorp Limited
Unique Youtopia Phase III
possession by Sep 2026 · Unique Associates
Spandan
possession by Oct 2026 · Evolve Infra
Ganga Platinum A
possession by Oct 2026 · Shree Balaji Associates Pune LLP
Percept Bounty 3
possession by Dec 2026 · Prime Estate

Major developers building in Kharadi

Other RERA-registered projects in Pune

Vijaya Shrushti
declared completion Mar 2019 · Kadam Constructions
Vijaya Vasant
possession by Jun 2027 · Growstone Ventures Unit I LLP
Vijayalaxmi Sulojay
possession by Dec 2026 · Shreevijayalaxmi Developers
Vikram Goldmine
declared completion Oct 2018 · Vikram Venkatrao Gaikwad
Vikram Residency
possession by May 2027 · Vikram Landmarks
Village Residency II Building A
declared completion Dec 2021 · Prateek Omprakash Agrawal

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.