Mumbai/Project record

MahaRERA · the public record

Akhand Phase 2

Vasai · TECHTON LIFESPACES LLP

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

375units filed as unsoldInventory · 20 September 2026
31 Dec 2029declared completionMahaRERA registration · read 12 Jul 2026
409registered unitsMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2029

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P99000079420

Delivery and registration

When is the project declared for completion?

Akhand Phase 2 is registered with MahaRERA as P99000079420 and the promoter has declared completion for 31 Dec 2029.

31 Dec 2029

declared completion

39months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP99000079420
Registered on04 Mar 2025
Promoter-declared completion31 Dec 2029
Current statusCertificate Signed
Against today39 months to the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Akhand Phase 2 record 5 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 5 quarterly progress reports on record since registration, with no current default.

Construction

How much construction cost has been reported?

In Akhand Phase 2, ₹82.50 Lakh of a declared ₹96.45 Cr estimated project cost is reported as incurred, about 0.9%, as at the last certified filing with MahaRERA.

0.9%

₹82.50 Lakh

of ₹96.45 Cr declared cost

Cost incurred as last certified to MahaRERA. It is a financial measure, not a survey of site work, and it can lag on-site reality between filings.

Source · MahaRERA quarterly progress filing · read 12 Jul 2026

Sales

How much has actually been sold?

In Akhand Phase 2, 34 of 409 homes filed with MahaRERA are recorded as sold or booked, about 8%, and 375 remain available.

8%sold

34 of 409 homes

₹19.15 Cr

committed by buyers

Counts and agreement value as the promoter filed them at the last compliance date; this is the filed inventory, not current availability. Of that agreement value, ₹94.81 Lakh (about 5%) is recorded as collected and ₹18.20 Cr as receivable.

Source · MahaRERA sold/unsold inventory filing · read 12 Jul 2026

What buyers actually paid: across 34 registered agreements, the effective carpet rate is ₹11,807/sqft, with eight in ten falling between ₹8,367 and ₹16,947 — computed from the agreement values and carpet areas the promoter filed, not broker quotes.

No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing.

What the filings record, home by home

Read from MahaRERA on 20 September 2026

MahaRERA publishes, home by home, what this promoter filed: which homes are sold and which are not, the RERA carpet area of each, and for the sold ones the registered agreement value — the consideration filed for that specific home. On this project 34 homes carry one, and 375 of the 409 are recorded unsold.

Here is one of those unsold homes, priced against what buyers of the same home on other floors actually filed:

HomeCarpetFiled for the same home on other floorsBased on
1001536 sqftRs 63.55 lakh typical, over Rs 44.50 lakh to Rs 93.89 lakh19 filed at this size

A filed consideration is what was registered for one home. It is not a valuation, and MahaRERA does not publish the date of any of these agreements — read a range as a spread, not as a trend. An unsold row means no sale had been filed for it when we looked, which is a filing state, not a promise that the home is available to you today. Only one observation of this ledger so far: no change can be reported yet. This observation is an archived copy whose time is the moment the file was written, not a portal fetch time.

In Akhand Phase 2, 251 of the 375 unsold homes have agreements filed on their own stack. The Price Comparison Report gives each of them its own row — the filed agreements behind that stack listed in full, the government reckoner value the promoter filed against it, and whether it is mortgaged to a lender while still on the unsold list. Built from the filing itself, sent by email.

See the other 374 homes — ₹2,999 →

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+23 and 409 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
Building No- 8-Wing I1G+23150-
Building No- 8- Wing J1G+23128-
Building No- 8- Wing K1G+23131-

Unit mix on the filing: 409 residential.

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at Vasai, Village Gokhiware, Andheri, Mumbai Suburban, 401208. Per the filed land record, the plot is bounded to the north by Boundry Wall, to the south by Wing N and M, to the east by Boundry Wall and to the west by Wing P and Q. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Techton Lifespaces LLP is the promoter on 5 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

Other flagged projects by Techton Lifespaces LLP

Techton Lifespaces LLP
FlaggedPalghar
Techton Lifespaces LLP
FlaggedPalghar
Techton Lifespaces LLP
FlaggedPalghar
Techton Lifespaces LLP
FlaggedPalghar

Other RERA-registered projects in Vasai East

AAI Chandika Hills
possession by Sep 2026 · Shivam Builders & Developers
Dreams Heights Building NO- I
possession by Sep 2026 · Lodha Builders AND Developers
Trinity Oasis
possession by Sep 2026 · Harsh Tirupati Developers LLP
Matoshri Heights
possession by Oct 2026 · Nagesh Hemant Patil
Hayaat Galaxy II
possession by Nov 2026 · M M Enterprises
Apeksha Complex
possession by Dec 2026 · Kothari Construction CO

Major developers building in Vasai East

Other RERA-registered projects in Palghar

Akhand Phase 3
possession by Dec 2030 · Techton Lifespaces LLP
Akruti Heaven
possession by Mar 2028 · Ashish Anil Patil
Akruti Prime Square
possession by Dec 2026 · Ashish Anil Patil
Akshay Chsl
possession by Mar 2028 · V Construction
Akshay Enclave
possession by Dec 2028 · Shree Shivbali Builders Private Limited
AL Hamd Residency
possession by Dec 2028 · A A Realty

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026