MahaRERA Property Intelligence · Thane

LODHA SPLENDORA - PLATINO - D

P51700000659 · promoter Lodha

Certificate SignedDue 30 Sep 2022

Delivery & Registration

MahaRERA registrationP51700000659
Registered on19 Jul 2017
Promoter-declared completion30 Sep 2022
Current statusCertificate Signed
Against todayabout 46 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date.

BuildingWingsFloorsDeclared completion
PLATINO D1--

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Legal & Litigation

The promoter has declared 2 court cases on this project to MahaRERA. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your flat. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
In The Court Of Civil Judge Jd Thane865 to 8702013Service Report
In The Court Of Civil Judge Jd Thane6522007Dismissal Order

Location, Land & Connectivity

Located at Mumbai City, Mumbai City, 400607. Per the filed land record, the plot is bounded to the north by Residental, to the south by Residental, to the east by Amenity Plot TMC and to the west by Central Green. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~16 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
Powai / Hiranandani business park16 km
Andheri MIDC / SEEPZ17 km
Chhatrapati Shivaji Int'l Airport21 km
Bandra Kurla Complex (BKC)23 km
Lower Parel / Worli business district32 km
Nariman Point / Fort39 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Lodha Developers Limited is the promoter on 171 MahaRERA-registered projects, of which 9 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

See every Lodha Developers Limited project & its RERA track record →

Other flagged projects by Lodha Developers Limited

Lodha Developers Limited
FlaggedThane
Lodha Developers Limited
FlaggedThane
Lodha Developers Limited
FlaggedThane
Lodha Developers Limited
FlaggedThane
Lodha Developers Limited
FlaggedThane
Lodha Developers Limited
FlaggedThane

Other RERA-registered projects in Thane

Godrej Exquisite
possession by Sep 2026 · Godrej Macbricks Private Limited
Lodha Crown Kolshet-Tower 1
possession by Sep 2026 · Lodha Developers Limited
Odysseus
possession by Sep 2026 · Sagar Enterprise
Unique Vistas Mhada Building NO. 1,2,3
possession by Sep 2026 · Madhu Harshad Doshi
Unique Vistas Mhada Buildingno. 4 5 6 7
possession by Sep 2026 · Madhu Harshad Doshi
Daffodil
possession by Dec 2026 · Shree Tirupati Greenfield Developers

Major developers building in Thane

Other RERA-registered projects in Thane

Lodha Splendora Platino E TO G , Vivant A TO D
declared completion Jun 2019 · Lodha Developers Limited
Lodha Splendora - River View
declared completion Sep 2024 · Lodha Developers Limited
Lodha Sterling - Tower C
possession by Mar 2030 · Lodha Developers Limited
Lodha Sterling - Tower G
declared completion Sep 2025 · Lodha Developers Limited
Lodha Sterling - Tower H
declared completion May 2024 · Lodha Developers Limited
Lodha Supremus - Thane, Kolshet
declared completion Jul 2022 · Lodha Developers Limited

What to verify (inactive registration)

  1. Download the MahaRERA order stating the reason for deregistration or suspension — this is public on the portal.
  2. Check whether the developer has filed a challenge in the Appellate Tribunal and whether the order is stayed.
  3. Do not make any further payments until the registration status is restored or you obtain legal advice.
  4. Contact MahaRERA's helpdesk for guidance on alternative arrangements or pending dues.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026