Plotted Development Intelligence · Thane

Lodha Villa Royale Palava

P51700047245 · Khoni & Antarli · promoter Lodha

Certificate SignedDue 30 Sep 2025

Delivery & Registration

MahaRERA registrationP51700047245
Registered on13 Oct 2022
Promoter-declared completion30 Sep 2025
Current statusCertificate Signed
Against todayabout 10 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Sales & Inventory

Of 179 plots filed with MahaRERA, 138 are sold/booked and 41 remain available (~77% sold) — selling steadily. This is the promoter's own reported inventory as at the last compliance filing; confirm current availability directly.

Complaints & Orders

1 complaint is on the MahaRERA record for this project, with orders passed in 0. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.

Complaint no.FiledPartiesStatus
CC1260300121/05/2026MADHU KHATRI vs LODHA DEVELOPERS LIMITEDpending / no order on file

Legal & Litigation

The promoter has declared 6 court cases on this project to MahaRERA. 6 are still pending. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your flat. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
Court Of Civil Judge KalyanRCS No 3972013Pending
Court Of Civil Judge KalyanRCS No 2032014Pending
Court Of Civil Judge KalyanSpl C S No 372015Pending
Court Of Civil Judge KalyanRCS No 2842015Pending
Court Of Civil Judge KalyanRCS No 5862016Pending
Revenue Minister2718by 2732018Pending

Location, Land & Connectivity

Located at Khoni & Antarli, Khoni & Antarli, Mumbai City, Mumbai City, 421204. Per the filed land record, the plot is bounded to the north by 149 Khoni, to the south by 42 and 44 Khoni, to the east by 61 and 64 Khoni and to the west by 21 Antarali. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Lodha Developers Limited is the promoter on 171 MahaRERA-registered projects, of which 9 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

See every Lodha Developers Limited project & its RERA track record →

Other flagged projects by Lodha Developers Limited

Lodha Developers Limited
FlaggedThane
Lodha Developers Limited
FlaggedThane
Lodha Developers Limited
FlaggedThane
Lodha Developers Limited
FlaggedThane
Lodha Developers Limited
FlaggedThane
Lodha Developers Limited
FlaggedThane

Other RERA-registered projects in Dombivali

Balaji Estate
possession by Jul 2026 · M/s. Sai Balaji Buildcon
Jayram Heights
possession by Jul 2026 · Ashapura Enterprises
Pearl B
possession by Jul 2026 · Lodha Developers Limited
Runwal Gardens Phase 4 Bldg No. 33-34
possession by Sep 2026 · Runwal Residency Private Limited
Sai Siddhi Residency
possession by Sep 2026 · Devendra Damodar Patil
Alimkar Heights
possession by Oct 2026 · Alimkar & Sons

Major developers building in Dombivali

Other RERA-registered projects in Thane

Lodha Villa Royale Tdlr 2
possession by Dec 2027 · Lodha Developers Limited
LOK Mangal Srushti
declared completion Jun 2022 · Balaram Gopal Gawli
Lok Nagari Developer Ph - II
declared completion Dec 2021 · Lok Nagari Developer
Lok Nagari Developer Ph - III
declared completion Dec 2022 · Lok Nagari Developer
Lotuaai Darshan Wing B
declared completion Jun 2026 · Lotuaai Construction CO
Lotus
declared completion Sep 2023 · Sujeet Kumar Jeetpratap Singh

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026