Mumbai/Project record

MahaRERA · the public record

Ruparel Premia

Mulund West · Aarav Developers

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

35units filed as unsoldInventory · 20 September 2026
31 Dec 2027declared completionMahaRERA registration · read 12 Jul 2026
103registered unitsMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2027

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51800077584

Delivery and registration

When is the project declared for completion?

Ruparel Premia is registered with MahaRERA as P51800077584 and the promoter has declared completion for 31 Dec 2027.

31 Dec 2027

declared completion

15months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51800077584
Registered on15 Oct 2024
Promoter-declared completion31 Dec 2027
Current statusCertificate Signed
Against today15 months to the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Ruparel Premia record 5 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 5 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Aarav Developers is the promoter of record on 5 projects registered with MahaRERA, none of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

5projects

registered with MahaRERA

0flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Construction

How much construction cost has been reported?

In Ruparel Premia, ₹11.28 Cr of a declared ₹44.46 Cr estimated project cost is reported as incurred, about 25.4%, as at the last certified filing with MahaRERA.

25.4%

₹11.28 Cr

of ₹44.46 Cr declared cost

Cost incurred as last certified to MahaRERA. It is a financial measure, not a survey of site work, and it can lag on-site reality between filings.

Source · MahaRERA quarterly progress filing · read 12 Jul 2026

Sales

How much has actually been sold?

In Ruparel Premia, 40 of 82 homes filed with MahaRERA are recorded as sold or booked, about 49%, and 42 remain available.

49%sold

40 of 82 homes

₹33.88 Cr

committed by buyers

Counts and agreement value as the promoter filed them at the last compliance date; this is the filed inventory, not current availability. Of that agreement value, ₹11.86 Cr (about 35%) is recorded as collected and ₹22.00 Cr as receivable. The project registers 103 homes in total, while this sold/unsold inventory filing covers 82 of them.

Source · MahaRERA sold/unsold inventory filing · read 12 Jul 2026

What buyers actually paid: across 40 registered agreements, the effective carpet rate is ₹22,188/sqft, with eight in ten falling between ₹17,881 and ₹23,490 — computed from the agreement values and carpet areas the promoter filed, not broker quotes.

The inventory filing also declares: 21 reserved.

What the filings record, home by home

Read from MahaRERA on 20 September 2026

MahaRERA publishes, home by home, what this promoter filed: which homes are sold and which are not, the RERA carpet area of each, and for the sold ones the registered agreement value — the consideration filed for that specific home. On this project 47 homes carry one, and 35 of the 103 are recorded unsold. Since we started watching this ledger, 7 homes have moved out of the unsold list, most recently on 11 September 2026.

Here is one of those unsold homes, priced against what buyers of the same home on other floors actually filed:

HomeCarpetFiled for the same home on other floorsBased on
1605458 sqftRs 22,195 a sq ft typical, over Rs 16,388 to Rs 23,86633 filed at this size

A filed consideration is what was registered for one home. It is not a valuation, and MahaRERA does not publish the date of any of these agreements — read a range as a spread, not as a trend. An unsold row means no sale had been filed for it when we looked, which is a filing state, not a promise that the home is available to you today. One of the two observations is an archived copy whose time is the moment the file was written, not a portal fetch time.

In Ruparel Premia, every one of the 35 unsold homes has agreements filed on its own stack. The Price Comparison Report gives each of them its own row — the filed agreements behind that stack listed in full, the government reckoner value the promoter filed against it, and whether it is mortgaged to a lender while still on the unsold list. Built from the filing itself, sent by email.

See the other 34 homes — ₹2,999 →

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+21 and 103 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
Ruparel Premia1G+21103-

Unit mix on the filing: 95 residential and 8 non-residential (shops/offices).

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at Mulund West , Jawahar Lal Nehru Road, Mumbai City, Mumbai City, 400080. Per the filed land record, the plot is bounded to the north by Building, to the south by Building, to the east by Jawahar lal Nehru Existing Road and to the west by Building. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Mulund West

AAI Satidevi Paradise
possession by Sep 2026 · Shreenath Developers
Laizer Elegance
Not filing quarterly progress reports · possession by Sep 2026 · Laizer Builders & Developers
THE NEW Anand Deep CHS LTD
possession by Sep 2026 · Shreejee Buildcon
Tirupati Apartments Chsl
possession by Oct 2026 · Tirupati Aparmtnets CO Operative Housing
Horizon Garden View
possession by Nov 2026 · Horizon Promoters India LTD
Montana Phase - 3
possession by Dec 2026 · Lohitka Properties LLP

Major developers building in Mulund West

Other RERA-registered projects in Mumbai Suburban

Ruparel Primero
declared completion Dec 2025 · Shree Siddhivinayak Classic Construction
Ruparel Pristine
possession by Dec 2026 · Shiddhivinayak Developers
Ruparel Skygreens I
possession by Dec 2026 · Shree Siddhivinayak Infrastructure &
Ruparel Stardom
possession by Jun 2028 · AMI Modispaces LLP
Ruparel Urbana
possession by Dec 2028 · R R Builders
Ruparel Westsky
possession by Dec 2027 · Ruparel Shreeji Construction PVT LTD

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026