MahaRERA Property Intelligence · Pune

Abharan

P52100055819 · Maan · promoter Vedant Developers And

Certificate SignedDue 31 Jul 2028

Delivery & Registration

MahaRERA registrationP52100055819
Registered on22 Apr 2024
Promoter-declared completion31 Jul 2028
Current statusCertificate Signed
Against today24 months to the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Vedant Developers And is the promoter of record on 79 projects, of which 6 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Construction Progress

MahaRERA's cost filing puts construction at ~51.1% of the estimated project cost incurred as of the last certificate (₹2.61 Cr spent against a ₹5.10 Cr estimate). This financial % is the regulator's own proxy for how much is physically built — the closest public read on real progress, and one a brochure never shows.

Cost-incurred % as last certified to MahaRERA; it can lag on-site reality between filings. Confirm the current stage and the latest Form 2 before you book.

Sales & Inventory

Of 37 homes filed with MahaRERA, 4 are sold/booked and 33 remain available (~11% sold) — early in sales — more choice of units now, but confirm the developer has the pre-sales to fund the build. Buyers have committed ₹1.13 Cr in agreement value so far. Of that, ₹66.82 Lakh (~59%) is already collected, ₹46.37 Lakh receivable — a read on how far along these sales really are. This is the promoter's own reported inventory as at the last compliance filing; confirm current availability directly.

The unsold units on the filing — if you're quoted a unit NOT on this list, ask why it shows as sold/booked on the RERA record:

FloorUnitCarpetReckoner value
Floor 1101642 sqft (59.67 sqm)₹26.31 Lakh
Floor 1102642 sqft (59.67 sqm)₹26.31 Lakh
Floor 1103650 sqft (60.38 sqm)₹26.63 Lakh
Floor 1105453 sqft (42.04 sqm)₹18.54 Lakh
Floor 1106453 sqft (42.04 sqm)₹18.54 Lakh
Floor 1107453 sqft (42.04 sqm)₹18.54 Lakh
Floor 2201642 sqft (59.67 sqm)₹26.31 Lakh
Floor 2202642 sqft (59.67 sqm)₹26.31 Lakh
Floor 2203650 sqft (60.38 sqm)₹26.63 Lakh
Floor 2205452 sqft (42.02 sqm)₹18.54 Lakh
Floor 2206453 sqft (42.04 sqm)₹18.54 Lakh
Floor 2207453 sqft (42.04 sqm)₹18.54 Lakh
Floor 2208453 sqft (42.04 sqm)₹18.54 Lakh
Floor 2210651 sqft (60.51 sqm)₹26.63 Lakh
Floor 3301642 sqft (59.67 sqm)₹26.31 Lakh
Floor 3302642 sqft (59.67 sqm)₹26.31 Lakh
Floor 3303650 sqft (60.38 sqm)₹26.63 Lakh
Floor 3305453 sqft (42.04 sqm)₹18.54 Lakh
Floor 3306453 sqft (42.04 sqm)₹18.54 Lakh
Floor 4401642 sqft (59.67 sqm)₹26.31 Lakh
Floor 4402642 sqft (59.67 sqm)₹26.31 Lakh
Floor 4403650 sqft (60.38 sqm)₹26.63 Lakh
Floor 4407453 sqft (42.04 sqm)₹18.54 Lakh
Floor 4408453 sqft (42.04 sqm)₹18.54 Lakh
Floor 4410651 sqft (60.51 sqm)₹26.68 Lakh
Floor 5501642 sqft (59.67 sqm)₹26.31 Lakh
Floor 5502642 sqft (59.67 sqm)₹26.31 Lakh
Floor 5504452 sqft (42.02 sqm)₹18.53 Lakh
Floor 5506452 sqft (42.02 sqm)₹18.54 Lakh
Floor 5507452 sqft (42.02 sqm)₹18.54 Lakh
Floor 5508452 sqft (42.02 sqm)₹18.54 Lakh
Floor 5510651 sqft (60.51 sqm)₹26.68 Lakh
Floor 6601642 sqft (59.67 sqm)₹26.31 Lakh

No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing — still confirm your specific unit's status in the agreement.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+6 and 37 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
Abharan1G+637-

Unit mix on the filing: 37 residential.

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 1 time. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
30 Apr 202731 Jul 2028Due to delay of getting Revise sanction plan

Location, Land & Connectivity

Located at Maan, Maan, Haveli, Pune, 411057. Per the filed land record, the plot is bounded to the north by Road, to the south by Property out of S No 314 2, to the east by Road and Part land of adj S No 366 and to the west by Property out of S No 314 2. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Wakad

Fusion Towers Phase III
possession by Jul 2026 · Rama Synergy Spaces
ANP Bizsquare
possession by Jul 2026 · Five Star Vighnesh Associates
Olive Orchard
possession by Jul 2026 · Anandtara Properties
Fairmont
possession by Aug 2026 · Krishna Icon Skyscraper LLP
Varad Residency
possession by Sep 2026 · Vilas Bhagaji Arekar
ANP Memento
possession by Sep 2026 · Five Star Construction Company

Major developers building in Wakad

Other RERA-registered projects in Pune

Abhiaayu Heights
declared completion Jan 2024 · Manoj Yeole Ramdas Yeole
Abhilasha
declared completion May 2022 · Kudale Sable Builders
Abhilasha
declared completion Dec 2023 · Ashwamedh Spaces Private Limited
Abhilasha Heights
declared completion May 2023 · Sagar Shashikant Awate
Abhilasha Park
declared completion Dec 2019 · Sarovar Associates
Abhilasha Park A Building
declared completion Jul 2023 · Sarovar Associates

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026