MahaRERA Property Intelligence · Pune

ANP BIZSQUARE

P52100055995 · Wakad · promoter Five Star Vighnesh

Certificate SignedDue 31 Jul 2026

Delivery & Registration

MahaRERA registrationP52100055995
Registered on06 May 2024
Promoter-declared completion31 Jul 2026
Current statusCertificate Signed
Against today0 months to the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Five Star Vighnesh is the promoter of record on 9 projects, of which none currently carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Construction Progress

MahaRERA's cost filing puts construction at ~96.7% of the estimated project cost incurred as of the last certificate (₹13.53 Cr spent against a ₹14.00 Cr estimate). This financial % is the regulator's own proxy for how much is physically built — the closest public read on real progress, and one a brochure never shows.

Cost-incurred % as last certified to MahaRERA; it can lag on-site reality between filings. Confirm the current stage and the latest Form 2 before you book.

Sales & Inventory

Of 68 homes filed with MahaRERA, 33 are sold/booked and 35 remain available (~49% sold) — selling steadily. Buyers have committed ₹26.26 Cr in agreement value so far. Of that, ₹25.90 Cr (~99%) is already collected, ₹35.90 Lakh receivable — a read on how far along these sales really are. This is the promoter's own reported inventory as at the last compliance filing; confirm current availability directly.

What buyers actually paid: across 33 registered agreements, the effective carpet rate is ₹13,591/sqft (typical range ₹11,162–₹15,356) — computed from the agreement values and carpet areas the promoter filed, not broker quotes. Compare your quote against this before negotiating.

The unsold units on the filing — if you're quoted a unit NOT on this list, ask why it shows as sold/booked on the RERA record:

FloorUnitCarpetReckoner value
Floor 1Shop-101366 sqft (33.98 sqm)₹29.68 Lakh
Floor 1Shop-102240 sqft (22.31 sqm)₹19.49 Lakh
Floor 1Shop-103242 sqft (22.5 sqm)₹19.65 Lakh
Floor 1Shop-104242 sqft (22.5 sqm)₹19.65 Lakh
Floor 1Shop-105248 sqft (23.06 sqm)₹20.14 Lakh
Floor 1Shop-1061,023 sqft (95.05 sqm)₹83.03 Lakh
Floor 2Office-201816 sqft (75.8 sqm)₹64.91 Lakh
Floor 2Office-207512 sqft (47.56 sqm)₹40.73 Lakh
Floor 3Office-306302 sqft (28.03 sqm)₹24.00 Lakh
Floor 3Office-307510 sqft (47.38 sqm)₹40.57 Lakh
Floor 4Office-406302 sqft (28.03 sqm)₹24.00 Lakh
Floor 4Office-407510 sqft (47.38 sqm)₹40.57 Lakh
Floor 5Office-501814 sqft (75.65 sqm)₹64.78 Lakh
Floor 5Office-503393 sqft (36.52 sqm)₹31.27 Lakh
Floor 5Office-507510 sqft (47.38 sqm)₹40.57 Lakh
Floor 6Office-601814 sqft (75.65 sqm)₹64.78 Lakh
Floor 6Office-606302 sqft (28.03 sqm)₹24.00 Lakh
Floor 6Office-607510 sqft (47.38 sqm)₹40.57 Lakh
Floor 7Office-701814 sqft (75.65 sqm)₹64.78 Lakh
Floor 7Office-702400 sqft (37.17 sqm)₹31.83 Lakh
Floor 7Office-703393 sqft (36.52 sqm)₹31.27 Lakh
Floor 7Office-704423 sqft (39.3 sqm)₹33.65 Lakh
Floor 7Office-705215 sqft (19.98 sqm)₹17.11 Lakh
Floor 7Office-707510 sqft (47.38 sqm)₹40.57 Lakh
Floor 8Office-807510 sqft (47.38 sqm)₹40.57 Lakh
Floor 9Office-901814 sqft (75.65 sqm)₹64.78 Lakh
Floor 9Office-902400 sqft (37.17 sqm)₹31.83 Lakh
Floor 9Office-903393 sqft (36.52 sqm)₹31.27 Lakh
Floor 9Office-904423 sqft (39.3 sqm)₹33.65 Lakh
Floor 9Office-905302 sqft (28.03 sqm)₹24.00 Lakh
Floor 9Office-906302 sqft (28.03 sqm)₹24.00 Lakh
Floor 9Office-907510 sqft (47.38 sqm)₹40.57 Lakh
Ground/Floor 0Shop-3505 sqft (46.89 sqm)₹40.96 Lakh
Ground/Floor 0Shop-4505 sqft (46.89 sqm)₹40.96 Lakh
Ground/Floor 0Shop-5520 sqft (48.34 sqm)₹42.22 Lakh

No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing — still confirm your specific unit's status in the agreement.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+10 and 68 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
A Comm Building1G+106830 Sep 2025

Unit mix on the filing: 68 non-residential (shops/offices).

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 1 time. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
30 Sep 202531 Jul 2026The project was delayed mainly due to reasons beyond our control, as explained below: 1.SHORTAGE OF LABOUR During the project period, sufficient labour was not available. Many wo

Location, Land & Connectivity

Located at Wakad, Hinjawadi Road, Bhumkar Chowk, Haveli, Pune, 411057. Per the filed land record, the plot is bounded to the north by 45 M Wide Road, to the south by Side Margine Of Building B, to the east by 6 M Wide Ramp and to the west by Side Margine And Ramp Of Parking. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~2 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Hinjewadi Rajiv Gandhi IT Park2 km
Baner–Balewadi belt6 km
Pune Junction / city centre15 km
Pune Int'l Airport (Lohegaon)18 km
Kharadi / EON IT Park21 km
Magarpatta / Hadapsar IT21 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Wakad

Fusion Towers Phase III
possession by Jul 2026 · Rama Synergy Spaces
Olive Orchard
possession by Jul 2026 · Anandtara Properties
Fairmont
possession by Aug 2026 · Krishna Icon Skyscraper LLP
Varad Residency
possession by Sep 2026 · Vilas Bhagaji Arekar
ANP Memento
possession by Sep 2026 · Five Star Construction Company
Manor Crystal
possession by Sep 2026 · Oxford Infra Group

Major developers building in Wakad

Other RERA-registered projects in Pune

ANP - Landmark
declared completion Mar 2023 · Five Star Construction Company
ANP Memento
possession by Sep 2026 · Five Star Construction Company
ANP Nova
possession by Dec 2026 · ANP Lifespaces LLP
ANP Olympus
declared completion Aug 2024 · M/s.five Star Shelters
ANP Privado
possession by Sep 2031 · ANP Shelters LLP
ANP Retreat
declared completion Jun 2025 · Five Star Construction Company

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026