30 Dec 2025declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Dec 2025

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100024191

Delivery and registration

When is the project declared for completion?

ATULYA-MAAN is registered with MahaRERA as P52100024191 and the promoter has declared completion for 30 Dec 2025.

30 Dec 2025

declared completion

9months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100024191
Registered on24 Jan 2020
Promoter-declared completion30 Dec 2025
Current statusCertificate Signed
Against todayabout 9 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for ATULYA-MAAN record 24 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • QPR non-compliance — flagged by MahaRERA for not filing its mandatory quarterly progress reports.
  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (FY 2025-2026).

Promoter record

What else is this promoter on record for?

Sai Platinum Ventures is the promoter of record on 55 projects registered with MahaRERA, 4 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

55projects

registered with MahaRERA

4flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for ATULYA-MAAN in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date.

BuildingWingsFloorsDeclared completion
ATULYA MAAN- WING A1-31 Dec 2024
ATULYA MAAN- WING B1-31 Dec 2024

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at MAAN, S.No. is 440/2/1. which is erroneously mentioned as 440/2/4 above. Please ignore the same and read S.No.as 440/2/1. Maan-PIRANGUT ROAD, Pune City, Pune, 411057. Per the filed land record, the plot is bounded to the north by SURVEY NO 440 2 OF MR ARUN SALUNGE, to the south by MAAN PIRANGUT ROAD, to the east by SURVEY NO 439 K AND 439 B OF MR BHAGWAN SALUNKE and to the west by REMAINING AREA OF SURVEY NO 440 2 A OF MR RAHUL. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Wakad

ANP Memento
possession by Sep 2026 · Five Star Construction Company
Manor Crystal
possession by Sep 2026 · Oxford Infra Group
Park59
possession by Sep 2026 · Shiv Developers
Sensorium, Phase VI
possession by Sep 2026 · Joyville Shapoorji Housing Private Limit
Sonchandr Residency
possession by Sep 2026 · Chandan Ramdas Kate
Spring Residency
possession by Sep 2026 · Pritam Ashok Kachi

Major developers building in Wakad

Other RERA-registered projects in Pune

Atulya Nakshtra
declared completion Dec 2019 · D S Developers
Atulya Nirman A B Wing
declared completion Dec 2022 · D S Associates
Atulya Raghukul Bldg - A
declared completion Dec 2023 · Calyx Lenora Realty LLP
Atulya Raghukul Bldg - B
declared completion Jun 2024 · Calyx Lenora Realty LLP
Atulya Raghukul Bldg - F
declared completion Dec 2023 · Calyx Lenora Realty LLP
Atulya Raghukul Bldg - G
declared completion Dec 2023 · Calyx Lenora Realty LLP

What to verify (QPR non-filer)

  1. Cross-check the developer's last QPR filing date on the MahaRERA portal — non-filing can indicate stalled construction.
  2. Visit the site (or request a third-party inspection report) to verify actual construction progress.
  3. If no QPR has been filed for more than two quarters, file a complaint with MahaRERA for non-disclosure.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.