Pune/Project record

MahaRERA · the public record

Building A3 Eon homes

Hinjwadi Ph-3 · Hinjawadi Infradevelelopment Private Limited

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Dec 2023declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Dec 2023

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100013714

Delivery and registration

When is the project declared for completion?

Building A3 Eon homes is registered with MahaRERA as P52100013714 and the promoter has declared completion for 30 Dec 2023.

30 Dec 2023

declared completion

33months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100013714
Registered on23 Oct 2017
Promoter-declared completion30 Dec 2023
Current statusCertificate Signed
Against todayabout 33 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Building A3 Eon homes record 25 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 25 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Hinjawadi Infradevelelopment is the promoter of record on 11 projects registered with MahaRERA, none of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

11projects

registered with MahaRERA

0flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Building A3 Eon homes in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+22.

BuildingWingsFloorsDeclared completion
A31G+2230 Dec 2023

Legal and disputes

What disputes are disclosed?

2 complaints are on the MahaRERA record for Building A3 Eon homes, with orders passed in 2 of them.

2complaints

2with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00500000029010716/01/2024Rajeev Sharma vs hinjawadi infradevelopment private limitedorder passed
CC1240070207/11/2024Sudipta Dutta vs Hinjawadi Infradevelopment Pvt Ltdorder passed

Location, Land & Connectivity

Located at Hinjwadi Ph-3, Besides Tech Mahindra, Haveli, Pune, 411057. Per the filed land record, the plot is bounded to the north by Portion of layout, to the south by Pheriphery road, to the east by Portion of layout and to the west by A2 Building. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~5 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Hinjewadi Rajiv Gandhi IT Park5 km
Baner–Balewadi belt9 km
Pune Junction / city centre20 km
Pune Int'l Airport (Lohegaon)24 km
Magarpatta / Hadapsar IT26 km
Kharadi / EON IT Park27 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Hinjawadi Infradevelelopment Private Limited is the promoter on 11 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

See every Hinjawadi Infradevelelopment Private Limited project & its RERA track record →

Other flagged projects by Hinjawadi Infradevelelopment Private Limited

Hinjawadi Infradevelelopment Private Limited
FlaggedPune
Hinjawadi Infradevelelopment Private Limited
FlaggedPune
Hinjawadi Infradevelelopment Private Limited
FlaggedPune
Hinjawadi Infradevelelopment Private Limited
FlaggedPune
Hinjawadi Infradevelelopment Private Limited
FlaggedPune

Other RERA-registered projects in Wakad

ANP Memento
possession by Sep 2026 · Five Star Construction Company
Manor Crystal
possession by Sep 2026 · Oxford Infra Group
Park59
possession by Sep 2026 · Shiv Developers
Sensorium, Phase VI
possession by Sep 2026 · Joyville Shapoorji Housing Private Limit
Sonchandr Residency
possession by Sep 2026 · Chandan Ramdas Kate
Spring Residency
possession by Sep 2026 · Pritam Ashok Kachi

Major developers building in Wakad

Other RERA-registered projects in Pune

Building A3 - Venicia
declared completion Jun 2026 · Leena Constructions
Building B2 Eon Homes
possession by Dec 2027 · Hinjawadi Infradevelelopment Private Lim
Building C1 Eon Homes
possession by Jan 2029 · Hinjawadi Infradevelelopment Private Lim
Building C2 Eon Homes
possession by Dec 2027 · Hinjawadi Infradevelelopment Private Lim
Building C3 Eon Homes
declared completion Dec 2025 · Hinjawadi Infradevelelopment Private Lim
Building - D- Wing -D-1- Navyangan Phase - II
declared completion Dec 2025 · Avior Merlin Venture LLP

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026