Eklavya Skylark

Rajaram Patil Nagar · Eklavya Builders Private Limited

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Dec 2027declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2027

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100002715

Delivery and registration

When is the project declared for completion?

Eklavya Skylark is registered with MahaRERA as P52100002715 and the promoter has declared completion for 31 Dec 2027.

31 Dec 2027

declared completion

15months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100002715
Registered on04 Aug 2017
Promoter-declared completion31 Dec 2027
Current statusCertificate Signed
Against today15 months to the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Eklavya Skylark record 38 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (FY 2025-2026).

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Eklavya Skylark in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+6.

BuildingWingsFloorsDeclared completion
Skylark1G+630 Jun 2018

Legal and disputes

What disputes are disclosed?

1 complaint is on the MahaRERA record for Eklavya Skylark, with orders passed in 1 of them.

1complaint

1with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00500000005391624/01/2020Pooja Rajkumar Sheti vs Eklavya Builders Pvt. Ltd.order passed

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 3 times, as recorded on the register.

FromExtended toStated reason
as registered30 Apr 2019Received Commencement dated 19/05/2018 for 5th & 6th floor on 13/06/2018. Decision regarding loading of TDR on projects adjoining 6m & 9m roads pending at Municipal corporation.
30 Apr 201931 Jul 2023Revised Sanction received for 6th Floor on 28/06/2019 CC/0692/19, Project was delayed due to unavailability of construction material and construction workers initially and then by
31 Jul 202331 Dec 2027We have completed 98% of Project. Only Finishing work is pending. We require some time for completion of pending work , form Association and complete Handover as well as Conveyance

Location, Land & Connectivity

Located at Rajaram Patil Nagar, Grant Road, Pune City, Pune, 411014. Per the filed land record, the plot is bounded to the north by Open Plot, to the south by Road, to the east by 6m Road and to the west by Playground Reservation. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~2 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Kharadi / EON IT Park2 km
Pune Int'l Airport (Lohegaon)4 km
Magarpatta / Hadapsar IT6 km
Pune Junction / city centre9 km
Baner–Balewadi belt19 km
Hinjewadi Rajiv Gandhi IT Park23 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Kharadi

Satyam Shivam Phase 2
Not filing quarterly progress reports · possession by Sep 2026 · Vijayalaxmi Associates
The Collection - W2 And W7
possession by Sep 2026 · Bramhacorp Limited
Unique Youtopia Phase III
possession by Sep 2026 · Unique Associates
Spandan
possession by Oct 2026 · Evolve Infra
Ganga Platinum A
possession by Oct 2026 · Shree Balaji Associates Pune LLP
Percept Bounty 3
possession by Dec 2026 · Prime Estate

Major developers building in Kharadi

Other RERA-registered projects in Pune

Eknath
possession by Mar 2027 · Bhansali Associates
Eknath Aher Vaibhav
declared completion Jun 2019 · Chandrakant Eknath Aher
EL Regalo
possession by Dec 2026 · Mahesh Realtors
ELA Homes
declared completion Dec 2024 · Liquid Properties
Elanza
declared completion Dec 2025 · Santosh Mariba Bagadi
Elara
possession by Jun 2029 · Regenesis Project Management LLP

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026