GALAXY PREMIERO

KHARADI · RAMDEO DEVELOPERS

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Apr 2024declared completionMahaRERA registration · read 12 Jul 2026
4registered unitsMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Apr 2024

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100020043

Delivery and registration

When is the project declared for completion?

GALAXY PREMIERO is registered with MahaRERA as P52100020043 and the promoter has declared completion for 30 Apr 2024.

30 Apr 2024

declared completion

29months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100020043
Registered on19 Mar 2019
Promoter-declared completion30 Apr 2024
Current statusCertificate Signed
Against todayabout 29 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for GALAXY PREMIERO record 22 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 22 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Ramdeo Developers is the promoter of record on 3 projects registered with MahaRERA, 1 of which carries a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

3projects

registered with MahaRERA

1flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

How much has actually been sold?

In GALAXY PREMIERO, 0 of 4 homes filed with MahaRERA are recorded as sold or booked, about 0%, and 4 remain available.

0%sold

0 of 4 homes

Counts as the promoter filed them at the last compliance date; this is the filed inventory, not current availability.

Source · MahaRERA sold/unsold inventory filing · read 12 Jul 2026

The units recorded as unsold on the filing. The reckoner value is the government's ready-reckoner assessment the promoter filed against that unit, the figure stamp duty is charged on. It is not a price anyone paid, not an asking price, and not a valuation of the home.

FloorUnitCarpetGovt reckoner value
Floor 119,078 sqft (843.33 sqm)₹7.56 Cr
Floor 229,078 sqft (843.33 sqm)₹7.56 Cr
Floor 339,078 sqft (843.33 sqm)₹7.56 Cr
Ground/Floor 0110,000 sqft (929.03 sqm)₹8.33 Cr

No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for GALAXY PREMIERO in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+13 and 4 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
GALAXY PREMIERO1G+13430 Apr 2023

Unit mix on the filing: 4 non-residential (shops/offices).

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at KHARADI, KHARADI BYPASS, Pune City, Pune, 411014. Per the filed land record, the plot is bounded to the north by REMAINING PART OF S NO, to the south by REMAINING PART OF S NO 23, to the east by KHARADI BY PASS and to the west by RAMAINING PART OF S NO 23. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~1 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Kharadi / EON IT Park1 km
Magarpatta / Hadapsar IT4 km
Pune Int'l Airport (Lohegaon)4 km
Pune Junction / city centre7 km
Baner–Balewadi belt17 km
Hinjewadi Rajiv Gandhi IT Park21 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Kharadi

Satyam Shivam Phase 2
Not filing quarterly progress reports · possession by Sep 2026 · Vijayalaxmi Associates
The Collection - W2 And W7
possession by Sep 2026 · Bramhacorp Limited
Unique Youtopia Phase III
possession by Sep 2026 · Unique Associates
Spandan
possession by Oct 2026 · Evolve Infra
Ganga Platinum A
possession by Oct 2026 · Shree Balaji Associates Pune LLP
Percept Bounty 3
possession by Dec 2026 · Prime Estate

Major developers building in Kharadi

Other RERA-registered projects in Pune

Galaxy Premium Building E1 And E2
declared completion Dec 2023 · Skyline Developers
Galaxy Pride
declared completion Dec 2022 · Dattatray Hanumant Borade
Galaxy Pride
possession by Mar 2028 · JDM Buildcon
Galaxy Residency
declared completion Mar 2022 · More Bhondve Associates
Galaxy Vineet
declared completion Feb 2021 · Vineet Constructions
Ganaraj Paradise
possession by Feb 2028 · Uni Gravity Developers LLP

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026