MahaRERA · the public record
GULMOHAR ATRIUM
HINJEWADI · GULMOHAR DEVELOPMENT
Know the project.
Then choose your home.
The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.
The record · free to read
Registration read 12 Jul 2026Progress & dates
The timeline on file.
Available record
No construction trend to plot.
The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.
declared completion
30 Jun 2029
The registered date and a construction update answer different questions. Neither is a confirmation of possession.
MahaRERA registration · read 12 Jul 2026
From another project
See the report before you buy.
A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.
Read a sample report ↗The source record
The details behind the headline.
MahaRERA · P52100026292
Delivery and registration
When is the project declared for completion?
GULMOHAR ATRIUM is registered with MahaRERA as P52100026292 and the promoter has declared completion for 30 Jun 2029.
30 Jun 2029
declared completion
33months to go
against the declared date
The completion date and status as they stand on the MahaRERA registration record.
Source · MahaRERA project registration · read 12 Jul 2026
| MahaRERA registration | P52100026292 |
| Registered on | 07 Sep 2020 |
| Promoter-declared completion | 30 Jun 2029 |
| Current status | Certificate Signed |
| Against today | 33 months to the declared date |
Approvals and compliance
What compliance filings are on record?
MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for GULMOHAR ATRIUM record 28 quarterly progress reports since registration.
28quarterly filings
Entries as they appear on MahaRERA's own lists and the project's progress filing.
Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026
- Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (FY 2025-2026).
Promoter record
What else is this promoter on record for?
Gulmohar Development is the promoter of record on 11 projects registered with MahaRERA, 2 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).
11projects
registered with MahaRERA
2flagged
by MahaRERA
Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.
Source · MahaRERA register, all projects · read 12 Jul 2026
Construction
How much construction cost has been reported?
In GULMOHAR ATRIUM, ₹10.40 Cr of a declared ₹34.05 Cr estimated project cost is reported as incurred, about 30.5%, as at the last certified filing with MahaRERA.
30.5%
₹10.40 Cr
of ₹34.05 Cr declared cost
Cost incurred as last certified to MahaRERA. It is a financial measure, not a survey of site work, and it can lag on-site reality between filings.
Source · MahaRERA quarterly progress filing · read 12 Jul 2026
Sales
How much has actually been sold?
In GULMOHAR ATRIUM, 0 of 75 homes filed with MahaRERA are recorded as sold or booked, about 0%, and 75 remain available.
0%sold
0 of 75 homes
Counts as the promoter filed them at the last compliance date; this is the filed inventory, not current availability.
Source · MahaRERA sold/unsold inventory filing · read 12 Jul 2026
No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing.
Sales
Are registered sale-agreement prices available?
No registered sale-agreement price is recorded for GULMOHAR ATRIUM in the MahaRERA project file.
Not available
This is what the record does not contain, not a value of zero.
Source · MahaRERA project file · checked 17 September 2026
What the filings record, home by home
Read from MahaRERA on 17 September 2026
No home in GULMOHAR ATRIUM carries a registered agreement value on its MahaRERA filing, so there is no record here of what anyone has paid. What the promoter has filed is the government ready reckoner value for 75 homes — the Annual Statement of Rates valuation, with each home’s carpet area and floor already applied. Across them that is Rs 10,779 a sq ft typical, over Rs 10,779 to Rs 10,779.
A reckoner value is the basis stamp duty is charged on. It is not a price anyone paid, not an asking price, and not a valuation of the home to you.
The Reckoner Record lists all 75 of them — each home, its RERA carpet area, the valuation filed against it and the rate that works out to. It is the filing copied, not a reading of it.
Buildings & Wings
The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+6 and 75 homes are registered across the project.
| Building | Wings | Floors | Homes | Declared completion |
|---|---|---|---|---|
| GULMOHAR ATRIUM | 1 | G+6 | 75 | - |
Unit mix on the filing: 75 non-residential (shops/offices).
Complaints
No buyer complaints were on this project's MahaRERA record at the time of reading.
Deadline Extensions
The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.
| From | Extended to | Stated reason |
|---|---|---|
| as registered | 30 Jun 2029 | That there is no sale or booking in the said project. We have not yet completed the construction of the project. We need extension to complete work and sale of the project. |
Location, Land & Connectivity
Located at HINJEWADI, HINJEWADI , Pune City, Pune, 411057. Per the filed land record, the plot is bounded to the north by BY REMAINING PART OF SURVEY NO 139, to the south by BY SURVEY NO 138, to the east by BY 6 MTR WIDE EXISTING ROAD and to the west by BY REMAINING PART OF SURVEY NO 139. These are the boundaries as recorded in the filed land record.