MahaRERA Property Intelligence · Pune

KRISH LANDMARK

P52100008156 · Kharadi · promoter Hemanshu Prataprai Shah

Certificate SignedDue 31 Mar 2024

Delivery & Registration

MahaRERA registrationP52100008156
Registered on18 Aug 2017
Promoter-declared completion31 Mar 2024
Current statusCertificate Signed
Against todayabout 28 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Hemanshu Prataprai Shah is the promoter of record on 4 projects, of which 1 carries a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+5.

BuildingWingsFloorsDeclared completion
KRISH LANDMARK1G+5-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 3 times. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
31 Mar 202431 Mar 2022Revised design of project, delay in taking over of plot road, delay in getting FSI from PMC - Hence project delayed
31 Mar 202430 Mar 20201. Water seapage in the basement. 2.Delayed delivery of mechanical car park. 3.Delayed connection from MSEB department.
31 Mar 202431 Mar 20241. Revise sanction under UDCPR and got additional floor with additional Elevator 2. Sudden Shortage of Steel and Cement due to international crises 3. Due to heavy fluctuations i

Location, Land & Connectivity

Located at Kharadi, Mundhava Kharadi road, Pune City, Pune, 411014. Per the filed land record, the plot is bounded to the north by PRIVATE PLOT NO 12, to the south by ROAD AND S NO 14 KHARADI, to the east by PRIVATE PLOT 10 AND PART OF 13-1A-2-8 and to the west by KHARADI-MUNDWA BYPASS. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~91 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Hinjewadi Rajiv Gandhi IT Park91 km
Baner–Balewadi belt96 km
Pune Junction / city centre107 km
Pune Int'l Airport (Lohegaon)108 km
Kharadi / EON IT Park112 km
Magarpatta / Hadapsar IT112 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Kharadi

Satyam Shivam Phase 2
Not filing quarterly progress reports · possession by Sep 2026 · Vijayalaxmi Associates
The Collection - W2 And W7
possession by Sep 2026 · Bramhacorp Limited
Unique Youtopia Phase III
possession by Sep 2026 · Unique Associates
Spandan
possession by Oct 2026 · Evolve Infra
Ganga Platinum A
possession by Oct 2026 · Shree Balaji Associates Pune LLP
Percept Bounty 3
possession by Dec 2026 · Prime Estate

Major developers building in Kharadi

Other RERA-registered projects in Pune

Krish Villas
declared completion Jun 2023 · Vishal Ashok Chugera
Krishiv Elite
possession by Oct 2027 · Krishiv Wellworth Enterprises
Krishiv Vista
declared completion Jun 2026 · VED Associates
Krishn Kirti Developers
declared completion May 2022 · Krishn Kirti Developers
Krishna Aakar
declared completion Dec 2019 · Krishna Aakar
Krishna Angan
declared completion Dec 2022 · Krishna Developers

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026