MahaRERA Property Intelligence · Pune

Ornate

P52100022119 · Wakad · promoter Unique Developers

Certificate SignedDue 30 Sep 2024

Delivery & Registration

MahaRERA registrationP52100022119
Registered on27 Aug 2019
Promoter-declared completion30 Sep 2024
Current statusCertificate Signed
Against todayabout 22 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Unique Developers is the promoter of record on 129 projects, of which 12 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+4.

BuildingWingsFloorsDeclared completion
Ornate1G+430 Sep 2023

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at Wakad, Wakad, Haveli, Pune, 411057. Per the filed land record, the plot is bounded to the north by Plot No 442 and 441, to the south by Survey no 107, to the east by 60Mtr DP Road and to the west by 30ft Internal Road. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~2 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Hinjewadi Rajiv Gandhi IT Park2 km
Baner–Balewadi belt7 km
Pune Junction / city centre17 km
Pune Int'l Airport (Lohegaon)19 km
Kharadi / EON IT Park22 km
Magarpatta / Hadapsar IT22 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Unique Developers is the promoter on 4 MahaRERA-registered projects, of which 1 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

See every Unique Developers project & its RERA track record →

Other flagged projects by Unique Developers

Other RERA-registered projects in Wakad

Fusion Towers Phase III
possession by Jul 2026 · Rama Synergy Spaces
ANP Bizsquare
possession by Jul 2026 · Five Star Vighnesh Associates
Olive Orchard
possession by Jul 2026 · Anandtara Properties
Fairmont
possession by Aug 2026 · Krishna Icon Skyscraper LLP
Varad Residency
possession by Sep 2026 · Vilas Bhagaji Arekar
ANP Memento
possession by Sep 2026 · Five Star Construction Company

Major developers building in Wakad

Other RERA-registered projects in Pune

Oro Vista
declared completion Dec 2018 · Suresh Malpani & Associates
Orrion Capital
declared completion Dec 2025 · Amit Rajendra Kudale
Orville Business Port
possession by Dec 2026 · Siddhesh Properties
Oshan Vivara
possession by Dec 2029 · Oshan Constructions
Osian Almanova Phase 1
possession by Dec 2029 · Osian Infratech LLP
Osian Almanova Phase 2
possession by Dec 2031 · Osian Infratech LLP

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026