PITTIE KOURTYARD - D TOWER

P52100002424 · KHARADI · promoter Raja Bahadur International

Certificate SignedDue 01 Apr 2023

Delivery & Registration

MahaRERA registrationP52100002424
Registered on01 Aug 2017
Promoter-declared completion01 Apr 2023
Current statusCertificate Signed
Against todayabout 39 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Raja Bahadur International is the promoter of record on 12 projects, of which 1 carries a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+23.

BuildingWingsFloorsDeclared completion
PITTIE KOURTYARD - D TOWER1G+2301 Apr 2022

Complaints & Orders

2 complaints are on the MahaRERA record for this project, with orders passed in 2. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.

Complaint no.FiledPartiesStatus
CC00500000010654928/01/2022Satyanarayan Dad vs Rajabahadur International Limitedorder passed
CC00500000010670317/03/2022Vikas Murlidhar Kohok vs RAJA BAHADUR INTERNATIONAL LTD.order passed

Location, Land & Connectivity

Located at KHARADI, HADAPSAR - MUNDHWA BY- PASS, Pune City, Pune, 411014. Per the filed land record, the plot is bounded to the north by SURVEY NO 37, to the south by SURVEY NO 30 HISSA 2 B, to the east by SURVEY NO 31 and to the west by S NO 30 HISSA 1 PLOT C AND 18 MTR D P ROAD. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~7 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Pune Junction / city centre2 km
Magarpatta / Hadapsar IT7 km
Kharadi / EON IT Park9 km
Baner–Balewadi belt9 km
Pune Int'l Airport (Lohegaon)10 km
Hinjewadi Rajiv Gandhi IT Park15 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Raja Bahadur International Ltd. is the promoter on 2 MahaRERA-registered projects, of which 1 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other flagged projects by Raja Bahadur International Ltd.

Raja Bahadur International Ltd.
Deregistered by MahaRERAPune

Other RERA-registered projects in Kharadi

Satyam Shivam Phase 2
Not filing quarterly progress reports · possession by Sep 2026 · Vijayalaxmi Associates
The Collection - W2 And W7
possession by Sep 2026 · Bramhacorp Limited
Unique Youtopia Phase III
possession by Sep 2026 · Unique Associates
Spandan
possession by Oct 2026 · Evolve Infra
Ganga Platinum A
possession by Oct 2026 · Shree Balaji Associates Pune LLP
Percept Bounty 3
possession by Dec 2026 · Prime Estate

Major developers building in Kharadi

Other RERA-registered projects in Pune

Piyusha
declared completion Mar 2019 · Amol Ajit Ravetkar
Placidia
possession by Dec 2028 · Vision Group
Planet9
declared completion Mar 2019 · Shree Sai Developers
Planning Designing Obtaining Approvals AND Const OF 680 MIG TS ON S NO 126,127,1 Tathawade Pune PH I
declared completion Dec 2024 · Pune Housing & Area Development Boar
Plateau Street 12, 14, 16, 18, 20, 26, 28, 30, 32, 52, 54 LCL 0031
declared completion Dec 2021 · Lavasa Corporation Ltd
Plateau Street 25
declared completion Dec 2021 · Lavasa Corporation Ltd

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026