MahaRERA Property Intelligence · Pune

SERRENE

P52100010852 · Mohammedwadi · promoter Nirmaann Encon Developers

Certificate SignedDue 30 Jun 2023

Delivery & Registration

MahaRERA registrationP52100010852
Registered on31 Aug 2017
Promoter-declared completion30 Jun 2023
Current statusCertificate Signed
Against todayabout 37 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Nirmaann Encon Developers is the promoter of record on 3 projects, of which none currently carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+11.

BuildingWingsFloorsDeclared completion
A1G+11-
B1G+11-
BUNGLOW 11G+1-
BUNGLOW 21G+1-
C1G+0-
D1G+1-

Complaints & Orders

21 complaints are on the MahaRERA record for this project, with orders passed in 13. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.

Complaint no.FiledPartiesStatus
CC00500000009616322/10/2021PARAMJEET SINGH ARORA vs NIRMAANN ECON DEVELOPERSorder passed
CC00500000009616623/10/2021PARAMJEET SINGH ARORA vs NIRMAANN ECON DEVELOPERSorder passed
CC00500000009616723/10/2021PARAMJEET SINGH ARORA vs NIRMAANN ECON DEVELOPERSorder passed
CC00500000009616823/10/2021PARAMJEET SINGH ARORA vs NIRMAANN ECON DEVELOPERSorder passed
CC00500000009616923/10/2021PARAMJEET SINGH ARORA vs NIRMAANN ECON DEVELOPERSorder passed
CC00500000009619428/10/2021PARAMJEET SINGH ARORA vs NIRMAAN ECON DEVELOPERSorder passed
CC00500000009619528/10/2021PARAMJEET SINGH ARORA vs NIRMAAN ECON DEVELOPERSorder passed
CC00500000009619728/10/2021PARAMJEET SINGH ARORA vs NIRMAANN ECON DEVELOPERSorder passed
CC00500000009619828/10/2021PARAMJEET SINGH ARORA vs NIRMAAN ECON DEVELOPERSorder passed
CC00500000010634105/12/2021Paramjeet Singh Arora vs Nirmaann Encon Developersorder passed
CC00500000016746306/09/2022Anjali Meena vs M/s. Nirmaann Encon Developersorder passed
CC1250112304/04/2025Seema Ashish Daweshar vs NIRMAANN ENCON DEVELOPERSorder passed
CC1250148803/05/2025Shrikant Shivaji Bansode vs NIRMAANN ENCON DEVELOPERSorder passed
CC1250149303/05/2025Gagandeep Singh Gujral vs NIRMAANN ENCON DEVELOPERSpending / no order on file
CC1250161316/05/2025PRAFUL RAMKRISHNA JAGTAP vs NIRMAANN ENCON DEVELOPERSpending / no order on file
CC1250166623/05/2025Paramjeet Singh Arora vs NIRMAANN ENCON DEVELOPERSpending / no order on file
CC1250166723/05/2025Paramjeet Singh Arora vs NIRMAANN ENCON DEVELOPERSpending / no order on file
CC1250171626/05/2025AlpeshKumar Jayantilal Patel vs NIRMAANN ENCON DEVELOPERSpending / no order on file
CC1250173127/05/2025Mohit Kumawat vs NIRMAANN ENCON DEVELOPERSpending / no order on file
CC1250176129/05/2025Harpal Singh Gujral vs NIRMAANN ENCON DEVELOPERSpending / no order on file
CC1250177930/05/2025Saranjeet Kaur Arora vs NIRMAANN ENCON DEVELOPERSpending / no order on file

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 2 times. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
30 Jun 202331 Dec 2022Due to second Covid-19 wave & subsequent lockdown, along with changes and delays in PMC sanctioning, completion date needs to be changed to 31/12/2022.
30 Jun 202329 Sep 2020As per recent notification, 11 villages under PMRDA jurisdiction have been included in Pune Municipal Corporation limits which includes the village our project is located in i.e. U

Location, Land & Connectivity

Located at Mohammedwadi, Kondhwa-Undri-Saswad Road, Haveli, Pune, 411060. Per the filed land record, the plot is bounded to the north by EXISTING 12 METER WIDE MAIN ROAD, to the south by NYATI ETERNITY, to the east by NYATI ETERNITY and to the west by S NO 24 1 OPEN PLOT. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~7 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Magarpatta / Hadapsar IT7 km
Pune Junction / city centre9 km
Kharadi / EON IT Park11 km
Pune Int'l Airport (Lohegaon)14 km
Baner–Balewadi belt19 km
Hinjewadi Rajiv Gandhi IT Park24 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Nirmaann Encon Developers is the promoter on 2 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

Other flagged projects by Nirmaann Encon Developers

Nirmaann Encon Developers
FlaggedPune

Other RERA-registered projects in Undri

Lodha Pune Nibm Project
possession by Jul 2026 · Lodha Developers Limited
Samarth Rise
possession by Aug 2026 · Shri Samarth Developers
Fortune Prima
possession by Sep 2026 · Satish Shivlal Kokate
Arnav Sokande Patil Plaza
possession by Nov 2026 · Sokande Patil Prom & Developers
Raheja Sterling - Tower 3
possession by Nov 2026 · Cavalcade Properties PVT LTD
ARV Regalia
possession by Dec 2026 · Unitree India Realty LLP

Major developers building in Undri

Other RERA-registered projects in Pune

Setpal Palazzo
declared completion Dec 2019 · Setpal Properties Pvt. Ltd.
Seva Bhavan - Industrial Training Institute, Pune
declared completion Jun 2026 · Jankalyan Seva Foundation
Seven
possession by May 2027 · Virkar Developers LLP
Seven Green Phase 1
declared completion Mar 2019 · Dinesh Buildcon
Seven Star Icon
possession by Dec 2030 · Samarth Icon
Seventy 7 Skyway
possession by Dec 2026 · Siddhidata Group

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026