New Registered 83 days ago · all new registrations in Bangalore

4%construction reportedQ1 2026 filing
140units not bookedof 140 · Q1 2026 filing
31 Dec 2030declared completionK-RERA registration · read 20 Sep 2026

The record · free to read

Registration read 20 Sep 2026

Progress & dates

The timeline on file.

Promoter-reported construction

K-RERA quarterly filings · Q1 2026 to Q1 2026

declared completion

31 Dec 2030

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

K-RERA registration · read 20 Sep 2026

Inventory & scale

What this registration contains.

3 BHK
109
4 BHK
9
2 BHK
22

Filed categories, unchanged · K-RERA registration · read 20 Sep 2026

The whole registration

1.9registered acres

74.2registered units per acre

The average covers the registered land and all registered unit types. It does not describe the space, outlook or surroundings of an individual home.

From another project · Prestige Park Grove

A larger advertised area. Almost the same carpet area.

In Tower 14, E4 has 141 sq ft more saleable area than E2. Its carpet area is only 0.46 sq m larger. The report puts the two layouts side by side.

This illustrates the report format. These findings concern the named sample, not this project.

Read the sample report ↗
Prestige Park Grove · Tower 14 comparison · approved sample report
Prestige Park Grove · Tower 14 comparison · approved sample report

The source record

The details behind the headline.

K-RERA · PRM/KA/RERA/1250/303/PR/300626/008779

This project, on the record

The comparable facts of this project, from its own RERA registration record. Each context percentile names its exact comparison set, drawn from Quietlist’s full register store. The paid report adds drawing-read rows to this same table — what the filed plans show about the site, its edges and the unit layouts.

On the register

Declared completion31 December 2030
Land area7,637 sq m (1.9 acres)
Homes registered140
Tower/wing entries2
Unit mix109 × 3 BHK, 9 × 4 BHK, 22 × 2 BHK

In context

Density74.2 homes per acre
Density in context59th percentile of 72 Devanahalli projects (median 68.1)

Values as crawled from the official K-RERA record; context percentiles name their comparison population.

Official Registry Facts

Official project scale

RERA filing

Registration-form facts from the K-RERA detail page: use these to sanity-check the builder brochure, parking allotment, and sanctioned-plan references before relying on plan-extracted approximations.

DisclosureOfficial valueWhy it matters
Registered units140Total inventory registered with K-RERA.
Official carpet area13,839 sqmRegulator-disclosed project-level carpet area, not vision-derived room sums.
Official built-up area27,618 sqmUseful scale context when comparing density and project cost.
Registered land area7,637 sqmThe land area attached to this K-RERA registration.
Sanctioned FAR/FSI2.49Higher FAR generally means a denser vertical build, subject to site layout and open-space design.
Registered tower/wing entries2Official tower/wing count in the K-RERA detail page.
Parking total (reconciled)140Separate filed counts; these categories may overlap and are not added together.
Covered-parking field168Separate filed counts; these categories may overlap and are not added together.
Open-parking field0Separate filed counts; these categories may overlap and are not added together.
Garage field0Separate filed counts; these categories may overlap and are not added together.
Approved plan numberBIAPPA/TP/CC/210/2025-26/26-27Use this to match the sanctioned drawing set shown by the builder.
Plan approval date15-05-2026
Project start date01-06-2026

Official inventory & towers

RERA filing

K-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.

Registered inventory mix

TypeUnitsShareOfficial carpet area
3 BHK10978%10,793 sqm
4 BHK96%1,459 sqm
2 BHK2216%1,587 sqm

Registered tower / wing summary

Tower/wingFloorsUnitsParkingHeight
Wing 113464644.95 m
Wing 213949444.95 m

Official unit register

RERA filing

K-RERA detail-page flat rows: exact unit numbers, official carpet area, UDS, and parking lots. 140 official flat/unit rows, matching the 140 registered units disclosed above. Use this as a checklist against the specific flat number in your cost sheet and draft agreement.

By unit type

Unit typeRowsCarpet areaUDSParking lots
3 BHK10985.4-180.8 sqm45.8-95.9 sqm109
2 BHK2270.2-74.0 sqm38.7-39.8 sqm22
4 BHK9150.3-171.2 sqm75.7-88.6 sqm9

By tower / wing

Tower/wingRowsCarpet areaUDSParking lots
Wing 29470.2-180.8 sqm38.7-95.9 sqm94
Wing 14685.4-166.7 sqm45.8-82.9 sqm46
Show sample official unit rows
UnitTowerFloorTypeCarpetUDSParking
W- 1 101Wing 113 BHK85.4 sqm47.3 sqm1
W- 1 103Wing 113 BHK97.0 sqm49.9 sqm1
W- 1 104Wing 113 BHK87.7 sqm45.8 sqm1
W- 1 201Wing 123 BHK85.4 sqm47.3 sqm1
W- 1 203Wing 123 BHK97.0 sqm49.9 sqm1
W- 1 204Wing 123 BHK87.7 sqm45.8 sqm1

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

No litigation declared on this project's K-RERA filing.

2 of 24 compliance document slots are filed as Not Applicable; the remaining 22 slots have usable uploaded filings.

No completion certificate (OC) on file yet — project has not been declared complete.

Named utility/regulatory approvals

Electricity (BESCOM/ESCOM)✓ On file (ESCOM/Electricity)
Water & sewage (BWSSB/KWSSB)✓ On file (KWSSB/Water)
Fire NOC✓ On file (Fire Force Department)
Pollution control (KSPCB)✓ On file (KSPCB)
Environmental clearance✓ On file (SEIAA)
Airport Authority height clearance✓ On file (Airport Authority of India)

"Not found in catalog" can mean the approval genuinely isn't on file yet, or that it doesn't apply to this project (K-RERA doesn't tell us which). Ask the builder directly for any marked not found before relying on it.

Statutory approval status

RERA filing

10 further authority slots are marked not applicable by the regulator.

Authority / NOCStatusDateFile

Project team & certifications

RERA filing

K-RERA names 4 project professional/vendor rows across Chartered accountant, Engineer, Architect, Contractor. Use this to cross-check whose certificates, drawings, and contractor commitments support the filing; final reliance still belongs with your lawyer/technical reviewer.

RoleNameRegistration / licenceSinceLocality
Chartered accountantC Venkatesulu0196592000Bengaluru Urban, Karnataka - 560011
EngineerSrinivasa Rao BolimuntaBCCL/BL-3.6/SE-0043/21-222021Bengaluru Urban, Karnataka - 560083
ArchitectDISHA K NCA/2025/1931252025Bengaluru Urban, Karnataka - 560070
ContractorAAROHANA PROJECTS-2023Bengaluru Urban, Karnataka - 560070

Builder track record

RERA filing

Rohan has 24 other K-RERA-registered projects in our records — grouped across the several project-specific entities this developer registers under (e.g. this project is filed as “Aarohana Projects”) (average reported construction progress 66%). 10 are past their declared completion deadline with no completion certificate recorded — but because K-RERA publishes OCs inconsistently, a project that has actually been finished and handed over still shows up this way, so this overstates real delays, especially for a high-volume established builder. That is a lower delayed rate than the K-RERA average across Bengaluru on the same measure.

Read this as a list to spot-check for a pattern of genuinely stalled projects, not as a delay rate — pull up a few of the builder’s other K-RERA registrations and check whether they’ve actually been delivered.

Financials & Construction Progress

Financial disclosures

RERA filing

Latest quarterly filing (2026-Q1): ₹0.00 Cr collected from buyers, ₹0.00 Cr withdrawn from the project's escrow account.

Construction progress4% → 4% (+0 pts)
Units sold/booked as registered0/140 (0%)

QPR figures are developer-filed quarterly disclosures. Collections and withdrawals are not a project valuation; they are a sanity check for whether sales, construction progress, and escrow draws appear directionally aligned.

Declared construction cost ÷ registered units averages to ₹74.3 lakhs per unit — the developer's own declared construction/development cost, not a sale price. K-RERA filings don't disclose what the builder is charging, so this can't tell you whether you're getting a fair deal — only you comparing your quoted price against comparable listings nearby can answer that.

RERA 70% project account is on file: STATE BANK OF INDIA Banaswadi IFSC Code : SBIN0007986 Pin Code : 560033. RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Location & Connectivity

The nearest major job hub is ~23 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Kempegowda Int'l Airport4 km
Outer Ring Road / Manyata23 km
Whitefield IT hub30 km
MG Road / city centre31 km
Bellandur–Marathahalli belt34 km
Electronic City44 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Aarohana Projects. View Aarohana Projects's full track record →
Aarohana Projects has 2 projects registered in Bangalore.

Other projects by this builder in Bangalore

Other RERA-registered projects in Devanahalli

Under The Sun – Luxury Villa Lifestyle By Fortius
Construction Of 423 Houses In Vijayappura & Devan

Major developers building in Devanahalli

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.

Own a unit in Aarohana Adira?

Sell directly to Quietlist's pre-screened buyer list — flat fee, no broker commission.

List your unit →

Last checked against the RERA register: 20 Sep 2026