Bangalore/Project record

K-RERA · the public record

Abhi Homes

Devanahalli · ABHI DEVELOPERS

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

68%construction reportedQ1 2026 filing
283units not bookedof 292 · Q1 2026 filing
31 Mar 2023declared completionK-RERA registration · read 20 Sep 2026

The record · free to read

Registration read 20 Sep 2026

Progress & dates

The timeline on file.

Promoter-reported construction

K-RERA quarterly filings · Q3 2025 to Q1 2026

declared completion

31 Mar 2023

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

K-RERA registration · read 20 Sep 2026

Inventory & scale

What this registration contains.

Filed categories, unchanged · K-RERA registration · read 20 Sep 2026

The whole registration

2.2registered acres

132.7registered units per acre

The average covers the registered land and all registered unit types. It does not describe the space, outlook or surroundings of an individual home.

From another project · Prestige Park Grove

A larger advertised area. Almost the same carpet area.

In Tower 14, E4 has 141 sq ft more saleable area than E2. Its carpet area is only 0.46 sq m larger. The report puts the two layouts side by side.

This illustrates the report format. These findings concern the named sample, not this project.

Read the sample report ↗
Prestige Park Grove · Tower 14 comparison · approved sample report
Prestige Park Grove · Tower 14 comparison · approved sample report

The source record

The details behind the headline.

K-RERA · PRM/KA/RERA/1250/303/PR/190711/002665

This project, on the record

The comparable facts of this project, from its own RERA registration record. Each context percentile names its exact comparison set, drawn from Quietlist’s full register store. The paid report adds drawing-read rows to this same table — what the filed plans show about the site, its edges and the unit layouts.

On the register

Declared completion31 March 2023
Land area8,902 sq m (2.2 acres)
Homes registered292
Tower/wing entries3

In context

Density132.7 homes per acre
Density in context90th percentile of 72 Devanahalli projects (median 68.1)

Values as crawled from the official K-RERA record; context percentiles name their comparison population.

Official Registry Facts

Official project scale

RERA filing

Registration-form facts from the K-RERA detail page: use these to sanity-check the builder brochure, parking allotment, and sanctioned-plan references before relying on plan-extracted approximations.

DisclosureOfficial valueWhy it matters
Registered units292Total inventory registered with K-RERA.
Registered land area8,902 sqmThe land area attached to this K-RERA registration.
Sanctioned FAR/FSI2Higher FAR generally means a denser vertical build, subject to site layout and open-space design.
Registered tower/wing entries3Official tower/wing count in the K-RERA detail page.
Parking total (reconciled)172Separate filed counts; these categories may overlap and are not added together.
Open-parking field10Separate filed counts; these categories may overlap and are not added together.
Garage field1Separate filed counts; these categories may overlap and are not added together.
Project start date01-04-2019

Official inventory & towers

RERA filing

K-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.

Registered tower / wing summary

Tower/wingFloorsUnitsParkingHeight
ABHI HOMES BLOCK-A41200-
ABHI HOMES BLOCK-B48888-
ABHI HOMES BLOCK-C48484-

Official unit register

RERA filing

K-RERA detail-page flat rows: exact unit numbers, official carpet area, UDS, and parking lots. 292 official flat/unit rows, matching the 292 registered units disclosed above. Use this as a checklist against the specific flat number in your cost sheet and draft agreement.

By unit type

Unit typeRowsCarpet areaUDSParking lots
2BHK17243.6-47.5 sqm326.0-351.0 sqm172
1BHK12030.2-33.7 sqm229.0-256.0 sqm0 (120 with 0)

By tower / wing

Tower/wingRowsCarpet areaUDSParking lots
ABHI HOMES BLOCK-A12030.2-33.7 sqm229.0-256.0 sqm0 (120 with 0)
ABHI HOMES BLOCK-B8844.3-47.5 sqm330.0-351.0 sqm88
ABHI HOMES BLOCK-C8443.6-46.4 sqm326.0-343.0 sqm84
Show sample official unit rows
UnitTowerFloorTypeCarpetUDSParking
A-001ABHI HOMES BLOCK-A11BHK30.2 sqm231.0 sqm0
A-002ABHI HOMES BLOCK-A11BHK30.2 sqm230.0 sqm0
A-003ABHI HOMES BLOCK-A11BHK30.2 sqm230.0 sqm0
A-004ABHI HOMES BLOCK-A11BHK30.2 sqm231.0 sqm0
A-005ABHI HOMES BLOCK-A11BHK32.5 sqm248.0 sqm0
A-006ABHI HOMES BLOCK-A11BHK32.5 sqm248.0 sqm0

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

No litigation declared on this project's K-RERA filing.

⚠ 4 of 20 compliance document slots are filed as under process / not yet usable: Proforma For Sale Deed, Performa of Allotment Letter, Brochure of Current Project, Project Photo Uploaded.

No completion certificate (OC) on file yet — project has not been declared complete.

Named utility/regulatory approvals

Electricity (BESCOM/ESCOM)✓ On file (All NOCs from Authority)
Water & sewage (BWSSB/KWSSB)✓ On file (All NOCs from Authority)
Fire NOC✓ On file (All NOCs from Authority)
Pollution control (KSPCB)✓ On file (All NOCs from Authority)
Environmental clearance✓ On file (All NOCs from Authority)
Airport Authority height clearance✓ On file (All NOCs from Authority)

"Not found in catalog" can mean the approval genuinely isn't on file yet, or that it doesn't apply to this project (K-RERA doesn't tell us which). Ask the builder directly for any marked not found before relying on it.

K-RERA enforcement record (the regulator's own defaulter list & penalty orders)

Penalty orders on record:

ViolationUnder sectionPenaltyOrder date
Non Submission Of Annual Report 2021 22Section 4(2)(l)(D)₹2,000,00014/12/2023

K-RERA complaint orders (3 complaints against a project of this name on K-RERA's orders register)

PartiesRelief soughtDisposalOrder date
Supratim Sircar vs Abhi DevelopersImmediate directions to Abhi Homes to hand over possession of the flat by the original hard deadline of June 2025. Compensation in the form of interest for the period of delay, as per Section 18(1).AUTHORITY28/10/2025
SHEIKSHAVALI U & K. SHABANA BEGUM vs ABHI DEVELOPERSWITH DUE RESPECT, WE ARE REQUESTIING RERA TO CONSIDER MY COMPLAINT ON PRIORITY AND PLEASE ARRNAGE TO GET THE REFUND WITH INTERESTAUTHORITY18/09/2024
Vani V and Ashok Kumar BS vs Abhi DevelopersRefund of 100000AUTHORITY11/06/2024

⚠ Matched by PROJECT NAME (the orders register carries no registration number) — confirm the respondent above is this project's builder before relying on it.

Statutory approval status

RERA filing

Clean approvals profile: every applicable statutory NOC is on file — including pollution-control clearance (KSPCB), the clearances buyers most often find still pending. Nothing is outstanding among the statutory NOCs — which compliance documents are filed versus still under process is a separate matter, covered in Litigation & compliance above. Note Fire NOC and environmental clearance are not among the approvals K-RERA marks applicable to this project — if the named-approvals check shows them as "not found in catalog", that is why; ask the builder directly whether they apply here. Since these are developer-filed portal statuses, have your lawyer confirm them against the linked NOC copies.

6 further authority slots are marked not applicable by the regulator.

Authority / NOCStatusDateFile
Water supply and sewage boardApproved23-07-2018WATER NOC.pdf
KSPCB- PCB (10 Acres to 125 Acres)Approved24-11-2018POLLUTION CONTROL.pdf
KPTCL- BESCOMApproved02-01-2019BESCOM NOC.pdf
Airport Authority of IndiaApproved03-01-2019AIRPORT NOC.pdf

Project team & certifications

RERA filing

K-RERA names 2 project professional/vendor rows across Architect, Structural engineer. Use this to cross-check whose certificates, drawings, and contractor commitments support the filing; final reliance still belongs with your lawyer/technical reviewer.

RoleNameRegistration / licenceSinceLocality
ArchitectBijith G Bhaskar ENSEMBLEE-2005N3668 3rd FLOOR 8th CROSS 13th MAIN HAL 2nd STAGE, INDIRANAGAR BANGALORE-560038
Structural engineerDOWN EARTH - DESIGN & BUILT---

Financials & Construction Progress

Financial disclosures

RERA filing

Latest quarterly filing (2026-Q1): ₹0.00 Cr collected from buyers, ₹12.87 Cr withdrawn from the project's escrow account. This quarter the escrow withdrawal (₹12.87 Cr) exceeded buyer collections (₹0.00 Cr) — worth asking the builder to reconcile against certified construction milestones, which is what RERA requires escrow draws to track.

Construction progress68% → 68% (+0 pts)
Units sold/booked as registered9/292 (3%)
Escrow withdrawals in available QPRs₹38.62 Cr
  • In the latest QPR, escrow withdrawal exceeds buyer collections for that quarter. This can be normal if prior balance existed, but it needs a clean explanation.

QPR figures are developer-filed quarterly disclosures. Collections and withdrawals are not a project valuation; they are a sanity check for whether sales, construction progress, and escrow draws appear directionally aligned.

Declared construction cost ÷ registered units averages to ₹12.0 lakhs per unit — the developer's own declared construction/development cost, not a sale price. K-RERA filings don't disclose what the builder is charging, so this can't tell you whether you're getting a fair deal — only you comparing your quoted price against comparable listings nearby can answer that.

RERA 70% project account is on file: STATE BANK OF INDIA Girinagar Branch (IFSC SBIN0016222, a/c …5215). RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Location & Connectivity

The nearest major job hub is ~23 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Kempegowda Int'l Airport3 km
Outer Ring Road / Manyata23 km
Whitefield IT hub29 km
MG Road / city centre30 km
Bellandur–Marathahalli belt33 km
Electronic City43 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Abhi Developers.
3 complaints on the K-RERA register against Abhi Developers in Bangalore.

Other RERA-registered projects in Devanahalli

Under The Sun – Luxury Villa Lifestyle By Fortius
Construction Of 423 Houses In Vijayappura & Devan

Major developers building in Devanahalli

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.