31 Jul 2025declared completionK-RERA registration · read 20 Sep 2026
159registered unitsK-RERA registration · read 20 Sep 2026

The record · free to read

Registration read 20 Sep 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Jul 2025

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

K-RERA registration · read 20 Sep 2026

Inventory & scale

What this registration contains.

1 BHK
13

Filed categories, unchanged · K-RERA registration · read 20 Sep 2026

The whole registration

2.0registered acres

78.5registered units per acre

The average covers the registered land and all registered unit types. It does not describe the space, outlook or surroundings of an individual home.

From another project · Prestige Park Grove

A larger advertised area. Almost the same carpet area.

In Tower 14, E4 has 141 sq ft more saleable area than E2. Its carpet area is only 0.46 sq m larger. The report puts the two layouts side by side.

This illustrates the report format. These findings concern the named sample, not this project.

Read the sample report ↗
Prestige Park Grove · Tower 14 comparison · approved sample report
Prestige Park Grove · Tower 14 comparison · approved sample report

The source record

The details behind the headline.

K-RERA · PRM/KA/RERA/1250/303/PR/201222/003761

This project, on the record

The comparable facts of this project, from its own RERA registration record. Each context percentile names its exact comparison set, drawn from Quietlist’s full register store. The paid report adds drawing-read rows to this same table — what the filed plans show about the site, its edges and the unit layouts.

On the register

Declared completion31 July 2025
Land area8,197 sq m (2.0 acres)
Homes registered159
Tower/wing entries3
Unit mix13 × 1 BHK

In context

Density78.5 homes per acre
Density in context63rd percentile of 72 Devanahalli projects (median 68.1)

Values as crawled from the official K-RERA record; context percentiles name their comparison population.

Official Registry Facts

Official project scale

RERA filing

Registration-form facts from the K-RERA detail page: use these to sanity-check the builder brochure, parking allotment, and sanctioned-plan references before relying on plan-extracted approximations.

DisclosureOfficial valueWhy it matters
Registered units159Total inventory registered with K-RERA.
Registered land area8,197 sqmThe land area attached to this K-RERA registration.
Sanctioned FAR/FSI2.25Higher FAR generally means a denser vertical build, subject to site layout and open-space design.
Registered tower/wing entries3Official tower/wing count in the K-RERA detail page.
Parking total (reconciled)159Separate filed counts; these categories may overlap and are not added together.
Open-parking field19Separate filed counts; these categories may overlap and are not added together.
Garage field0Separate filed counts; these categories may overlap and are not added together.
Project start date01-02-2021

Official inventory & towers

RERA filing

K-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.

Registered inventory mix

TypeUnitsShareOfficial carpet area
1 BHK13100%0 sqm

Registered tower / wing summary

Tower/wingFloorsUnitsParkingHeight
Tower 1135252-
Tower 2135353-
Tower 3135454-

Official unit register

RERA filing

K-RERA detail-page flat rows: exact unit numbers, official carpet area, UDS, and parking lots. 159 official flat/unit rows, matching the 159 registered units disclosed above. Use this as a checklist against the specific flat number in your cost sheet and draft agreement.

By unit type

Unit typeRowsCarpet areaUDSParking lots
2BHK120759.0-887.0 sqft390.1-456.3 sqft120
3BHK261,245.0 sqft640.4 sqft26
1BHK13469.0 sqft241.2 sqft13

By tower / wing

Tower/wingRowsCarpet areaUDSParking lots
Tower 354759.0-865.0 sqft390.1-445.0 sqft54
Tower 253469.0-887.0 sqft241.2-456.3 sqft53
Tower 152760.0-1,245.0 sqft390.8-640.4 sqft52
Show sample official unit rows
UnitTowerFloorTypeCarpetUDSParking
1-01ATower 113BHK1,245.0 sqft640.4 sqft1
1-01BTower 113BHK1,245.0 sqft640.4 sqft1
1-01CTower 112BHK760.0 sqft390.8 sqft1
1-01DTower 112BHK857.0 sqft441.0 sqft1
1-02ATower 123BHK1,245.0 sqft640.4 sqft1
1-02BTower 123BHK1,245.0 sqft640.4 sqft1

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

No litigation declared on this project's K-RERA filing.

7 of 25 compliance document slots are filed as Not Applicable; the remaining 18 slots have usable uploaded filings.

No completion certificate (OC) on file yet — project has not been declared complete.

⚠ Registration validity has lapsed: originally due 31 Jul 2025 — which has passed with no OC on file.

Named utility/regulatory approvals

Electricity (BESCOM/ESCOM)Not found in catalog
Water & sewage (BWSSB/KWSSB)✓ On file (BWSSB)
Fire NOC✓ On file (Fire Force Department)
Pollution control (KSPCB)Not found in catalog
Environmental clearanceNot found in catalog
Airport Authority height clearance✓ On file (Airport Authority of India)

"Not found in catalog" can mean the approval genuinely isn't on file yet, or that it doesn't apply to this project (K-RERA doesn't tell us which). Ask the builder directly for any marked not found before relying on it.

K-RERA enforcement record (the regulator's own defaulter list & penalty orders)

⚠ Listed on K-RERA's official DEFAULTER list.

Project team & certifications

RERA filing

K-RERA names 3 project professional/vendor rows across Architect, Contractor, Structural engineer. Use this to cross-check whose certificates, drawings, and contractor commitments support the filing; final reliance still belongs with your lawyer/technical reviewer.

RoleNameRegistration / licenceSinceLocality
ArchitectInFORM Architects-19979th Main Rd, Banashankari 2nd stage
ContractorMF FARMLANDS PRIVATE LIMITED-2010Devenahalli Taluk, Bengaluru Rural
Structural engineerRajendra Kumar Bhola---

Builder track record

RERA filing

Mf Farmlands has 2 other K-RERA-registered projects in our records (average reported construction progress 97%). 0 are past their declared completion deadline with no completion certificate recorded — but because K-RERA publishes OCs inconsistently, a project that has actually been finished and handed over still shows up this way, so this overstates real delays, especially for a high-volume established builder. That is a lower delayed rate than the K-RERA average across Bengaluru on the same measure.

Read this as a list to spot-check for a pattern of genuinely stalled projects, not as a delay rate — pull up a few of the builder’s other K-RERA registrations and check whether they’ve actually been delivered.

Financials & Construction Progress

Financial disclosures

RERA filing

⚠ No quarterly financial disclosures (collections, escrow withdrawals) on record, despite no completion certificate yet — meaning we can't verify the project's cashflows against its construction progress. Worth asking the builder directly why no quarterly filings are available.

Declared construction cost ÷ registered units averages to ₹37.1 lakhs per unit — the developer's own declared construction/development cost, not a sale price. K-RERA filings don't disclose what the builder is charging, so this can't tell you whether you're getting a fair deal — only you comparing your quoted price against comparable listings nearby can answer that.

RERA 70% project account is on file: HDFC DEVANHALLI (IFSC HDFC0001744, a/c …4016). RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Construction photo filings

RERA filing

K-RERA has 1 project-photo upload.

These are developer-uploaded progress photos in the official document catalog. We do not treat them as proof of current site condition; use them as a prompt to ask for newer dated photos or a site visit. Individual filings are listed in the document catalog below.

Location & Connectivity

The nearest major job hub is ~23 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Kempegowda Int'l Airport3 km
Outer Ring Road / Manyata23 km
Whitefield IT hub28 km
MG Road / city centre30 km
Bellandur–Marathahalli belt32 km
Electronic City42 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Mf Farmlands.
Mf Farmlands has 3 projects registered in Bangalore, 2 completed.

Other projects by this builder in Bangalore

MVN Aero ONE T5 & T6
On track · 95% built · 78% sold
MVN Aero ONE Tower 4
On track · 99% built · 91% sold

Other RERA-registered projects in Devanahalli

Under The Sun – Luxury Villa Lifestyle By Fortius
Construction Of 423 Houses In Vijayappura & Devan

Major developers building in Devanahalli

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.

Own a unit in MVN Aero One Phase 1?

Sell directly to Quietlist's pre-screened buyer list — flat fee, no broker commission.

List your unit →

Last checked against the RERA register: 20 Sep 2026