Certificate SignedDue 28 Feb 2021

Delivery & Registration

MahaRERA registrationP51800011875
Registered on31 Aug 2017
Promoter-declared completion28 Feb 2021
Current statusCertificate Signed
Against todayabout 65 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Aspire Residency Llp is the promoter of record on 142 projects, of which 16 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+10.

BuildingWingsFloorsDeclared completion
ASPIRE RESIDENCY UPTO 10TH FLOOR PART1G+1031 Aug 2019
ASPIRE RESIDENCY FROM 10TH PART TO 13TH FLOOR1G+331 Aug 2019

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 1 time. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
28 Feb 202130 Aug 2020Construction is complete, minor finishing and cleaning activities in the process. Various NOC's for OC applied/received. Delay on account of technical issues related to handover of

Location, Land & Connectivity

Located at MULUND WEST, RAGHVENDRA SWAMI ROAD, Kurla, Mumbai Suburban, 400080. Per the filed land record, the plot is bounded to the north by CTS NO 705A, to the south by Amenity Open Space and CTS no 698A, to the east by Raghavendra Swami Road and to the west by CTS NO 707. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~7 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Powai / Hiranandani business park7 km
Andheri MIDC / SEEPZ9 km
Chhatrapati Shivaji Int'l Airport12 km
Bandra Kurla Complex (BKC)13 km
Lower Parel / Worli business district22 km
Nariman Point / Fort29 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Mulund West

Kailash Residency
possession by Aug 2026 · Tridev Shreeji Associates
Ananta
possession by Aug 2026 · K Ajmera Developers
AAI Satidevi Paradise
possession by Sep 2026 · Shreenath Developers
Laizer Elegance
Not filing quarterly progress reports · possession by Sep 2026 · Laizer Builders & Developers
THE NEW Anand Deep CHS LTD
possession by Sep 2026 · Shreejee Buildcon
Tirupati Apartments Chsl
possession by Oct 2026 · Tirupati Aparmtnets CO Operative Housing

Major developers building in Mulund West

Other RERA-registered projects in Mumbai Suburban

Astoria
possession by May 2028 · Avishkar Keval Kunj Redevelopment Privat
Astoria Tower B
possession by Dec 2027 · Conwood Realty Private Limited
Astrum
declared completion Jun 2026 · Upvan Developers
Astrum Annex
declared completion Jun 2026 · Astrum Reality Private Limited
Atharv Aaradhyam
possession by Apr 2028 · Atharv Infra LLP
Atharv Brindavan
possession by Mar 2031 · Atharv Realty

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026