MahaRERA Property Intelligence · Pune

99 RIVERFRONT

P52100019974 · BANER · promoter Srrinivas Infrabuildtech Private

Certificate SignedDue 30 Dec 2023

Delivery & Registration

MahaRERA registrationP52100019974
Registered on15 Mar 2019
Promoter-declared completion30 Dec 2023
Current statusCertificate Signed
Against todayabout 31 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Srrinivas Infrabuildtech Private is the promoter of record on 2 projects, of which none currently carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+15.

BuildingWingsFloorsDeclared completion
A BUILDING1G+1530 Dec 2023

Complaints & Orders

2 complaints are on the MahaRERA record for this project, with orders passed in 2. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.

Complaint no.FiledPartiesStatus
CC00500000002301211/05/2019Nirmiti Builders through Sunil Puranik vs Srrinivas Infrabuildtech Private Limitedorder passed
CC00500000006469704/10/2020Srrinivas Realtors Pvt Ltd vs Srrinivas Infrabuildtech Pvt Ltdorder passed

Legal & Litigation

The promoter has declared 5 court cases on this project to MahaRERA. 1 is still pending. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your flat. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
Igr Maharashtra2a-2014/11457-14/5482/20182018Pending
Civil Court Senior Division Pune726/20202020Ending For Hearing Of Amendment Application
Civil Court Senior Division2218/20222022Next Date Is Given
Civil Court Senior Division2380/20222022Next Date Is Given
Civil Court Senior Division2532/20222022Next Date Is Given

Location, Land & Connectivity

Located at BANER, BANER, Pune City, Pune, 411045. Per the filed land record, the plot is bounded to the north by PROPOSED 24 M WIDE ROAD, to the south by ADJACENT SURVEY NO 154, to the east by GREEN BELT RPB S NO 154 and to the west by ADJACENT SURVEY NO 154. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Srrinivas Infrabuildtech Private Limited is the promoter on 2 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

Other flagged projects by Srrinivas Infrabuildtech Private Limited

Srrinivas Infrabuildtech Private Limited
FlaggedPune

Other RERA-registered projects in Baner

7 Business BAY
possession by Jul 2026 · Saaj Buildcon Private Limited
Maitreya
Not filing quarterly progress reports · possession by Jul 2026 · Vaibhav Shamrao Taro
Mercury
possession by Aug 2026 · SB Real Estate Private Limited
Aarambh
possession by Aug 2026 · ADI Realtors
Nancy Hillview A-1
possession by Aug 2026 · M/S Sarsan Aawishkar Properties
Truspace Platina
possession by Aug 2026 · Atharva Developments

Major developers building in Baner

Other RERA-registered projects in Pune

99 Riverfront
declared completion Dec 2024 · Srrinivas Infrabuildtech Private Limited
A.a. Aurora
possession by Dec 2030 · Sai Realty
A Familia
declared completion Dec 2024 · Nidisha Buildcon LLP
A G Landmark
possession by Dec 2026 · A G Landmarks
A P Pinnacle Phase 1
declared completion Mar 2024 · A P Construction
A P Pinnacle Phase 2
declared completion Dec 2025 · A P Construction

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026