A R IMPERIA

WAKAD · A R REALTY

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

0units filed as unsoldInventory · 18 September 2026
31 Dec 2024declared completionMahaRERA registration · read 12 Jul 2026
86registered unitsMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2024

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100032942

Delivery and registration

When is the project declared for completion?

A R IMPERIA is registered with MahaRERA as P52100032942 and the promoter has declared completion for 31 Dec 2024.

31 Dec 2024

declared completion

21months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100032942
Registered on02 Feb 2022
Promoter-declared completion31 Dec 2024
Current statusCertificate Signed
Against todayabout 21 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for A R IMPERIA record 12 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 12 quarterly progress reports on record since registration, with no current default.

Sales

How much has actually been sold?

In A R IMPERIA, 86 of 86 homes filed with MahaRERA are recorded as sold or booked, about 100%, and 0 remain available.

100%sold

86 of 86 homes

₹52.33 Cr

committed by buyers

Counts and agreement value as the promoter filed them at the last compliance date; this is the filed inventory, not current availability. Of that agreement value, ₹52.30 Cr (about 100%) is recorded as collected and ₹11.27 Lakh as receivable.

Source · MahaRERA sold/unsold inventory filing · read 12 Jul 2026

What buyers actually paid: across 86 registered agreements, the effective carpet rate is ₹7,947/sqft, with eight in ten falling between ₹7,680 and ₹8,344 — computed from the agreement values and carpet areas the promoter filed, not broker quotes.

No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing.

What the filings record, home by home

Read from MahaRERA on 18 September 2026

MahaRERA publishes, home by home, what this promoter filed: which homes are sold and which are not, the RERA carpet area of each, and for the sold ones the registered agreement value — the consideration filed for that specific home. On this project 86 homes carry one, and Every home on the filing is recorded sold or booked.

A filed consideration is what was registered for one home. It is not a valuation, and MahaRERA does not publish the date of any of these agreements — read a range as a spread, not as a trend. An unsold row means no sale had been filed for it when we looked, which is a filing state, not a promise that the home is available to you today. Only one observation of this ledger so far: no change can be reported yet. This observation is an archived copy whose time is the moment the file was written, not a portal fetch time.

Every home in A R IMPERIA is filed sold or booked, so there is no asking price left to test — but the record of what this project sold for is complete. The Price Comparison Report lists all 86 registered agreements: each home, its carpet area, the consideration filed against it and the rate that works out to. Built from the filing itself, sent by email.

See all 86 registered agreements — ₹2,999 →

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+10 and 86 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
A BUILDING1G+104231 Dec 2024
B BUILDING1G+104431 Dec 2024

Unit mix on the filing: 86 residential.

Legal and disputes

What disputes are disclosed?

3 complaints are on the MahaRERA record for A R IMPERIA, with orders passed in 0 of them.

3complaints

0with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC1240028430/09/2024Avishkar Bajrang Chendge vs A R REALTYpending / no order on file
CC1240028330/09/2024ROSHAN RAJKUMAR YADAV vs A R REALTYpending / no order on file
CC1240028530/09/2024TUSHAR SADASHIV KASTURE vs A R REALTYpending / no order on file

Location, Land & Connectivity

Located at WAKAD, WAKAD, Haveli, Pune, 411057. Per the filed land record, the plot is bounded to the north by REMAINING PROPERTY OUT OF S NO 113 4 2, to the south by PROPERTY OUT OF S NO 113 3B 3A, to the east by PROPERTY OUT OF S NO 113 3B 3A and to the west by PROPERTY OUT OF S NO 113 2 1. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~5 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Baner–Balewadi belt5 km
Hinjewadi Rajiv Gandhi IT Park7 km
Pune Junction / city centre11 km
Pune Int'l Airport (Lohegaon)12 km
Kharadi / EON IT Park15 km
Magarpatta / Hadapsar IT16 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

A R Realty is the promoter on 2 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

Other flagged projects by A R Realty

Other RERA-registered projects in Wakad

ANP Memento
possession by Sep 2026 · Five Star Construction Company
Manor Crystal
possession by Sep 2026 · Oxford Infra Group
Park59
possession by Sep 2026 · Shiv Developers
Sensorium, Phase VI
possession by Sep 2026 · Joyville Shapoorji Housing Private Limit
Sonchandr Residency
possession by Sep 2026 · Chandan Ramdas Kate
Spring Residency
possession by Sep 2026 · Pritam Ashok Kachi

Major developers building in Wakad

Other RERA-registered projects in Pune

A R Mirador
possession by Dec 2031 · Atlas Royal Living
A3, Song Of Joy, Geras Greensville2
declared completion Jun 2019 · Gera Developments Private Limited
A33 Border Road Society
possession by Dec 2028 · Tanishka Developers AND Builders
A4 THE Edge
possession by Dec 2027 · A4 Ventures
AA Privilege
possession by Dec 2028 · J N Realty And Homes
AAA Dham
declared completion Sep 2020 · AAA Housing Development LLP

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026