MahaRERA Property Intelligence · Pune

Kiran Shubhamkaroti B

P52100010215 · promoter Kiran Creators Developers

Certificate SignedDue 30 Dec 2018

Delivery & Registration

MahaRERA registrationP52100010215
Registered on24 Aug 2017
Promoter-declared completion30 Dec 2018
Current statusCertificate Signed
Against todayabout 91 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Kiran Creators Developers is the promoter of record on 115 projects, of which 24 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+5.

BuildingWingsFloorsDeclared completion
Kiran Shubhamkaroti Building B1G+5-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at Haveli, Pune, 411045. Per the filed land record, the plot is bounded to the north by Road, to the south by Kiran Shubhamkaroti A, to the east by Part of s no 128 and to the west by Part of s no 128. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~3 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Baner–Balewadi belt3 km
Hinjewadi Rajiv Gandhi IT Park5 km
Pune Junction / city centre13 km
Pune Int'l Airport (Lohegaon)18 km
Magarpatta / Hadapsar IT19 km
Kharadi / EON IT Park20 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

M/S Kiran Creators & Developers Through Proprietor MR. Kashinath Ganesh Nehete is the promoter on 11 MahaRERA-registered projects, of which 1 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

See every M/S Kiran Creators & Developers Through P project & its RERA track record →

Other flagged projects by M/S Kiran Creators & Developers Through P

M/S Kiran Creators & Developers Through Proprietor MR. Kashinath Ganesh Nehete
FlaggedPune
M/S Kiran Creators & Developers Through Proprietor MR. Kashinath Ganesh Nehete
Past its declared completion datePune
M/S Kiran Creators & Developers Through Proprietor MR. Kashinath Ganesh Nehete
FlaggedPune
M/S Kiran Creators & Developers Through Proprietor MR. Kashinath Ganesh Nehete
FlaggedPune
M/S Kiran Creators & Developers Through Proprietor MR. Kashinath Ganesh Nehete
FlaggedPune
M/S Kiran Creators & Developers Through Proprietor MR. Kashinath Ganesh Nehete
FlaggedPune

Other RERA-registered projects in Baner

7 Business BAY
possession by Jul 2026 · Saaj Buildcon Private Limited
Maitreya
Not filing quarterly progress reports · possession by Jul 2026 · Vaibhav Shamrao Taro
Mercury
possession by Aug 2026 · SB Real Estate Private Limited
Aarambh
possession by Aug 2026 · ADI Realtors
Nancy Hillview A-1
possession by Aug 2026 · M/S Sarsan Aawishkar Properties
Truspace Platina
possession by Aug 2026 · Atharva Developments

Major developers building in Baner

Other RERA-registered projects in Pune

Kiran Shubharambh
declared completion Dec 2022 · M/S Kiran Creators & Developers Thro
Kiran Solistia
possession by Dec 2028 · Kiran Creators AND Developers Private Li
Kiran Sora
possession by Jul 2030 · Kiran Creators And Developers Private Li
Kiran Sparsh
declared completion Dec 2021 · M/S Kiran Creators & Developers Thro
Kiran Sufal
declared completion Dec 2024 · M/S Kiran Creators & Developers Thro
Kiran Sufal Phase II
declared completion Jun 2024 · Landowner MR Santosh Appa Kalate AND Oth

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026