Plotted Development Intelligence · Pune
P52100022278 · Hinjewadi · promoter Kolte-Patil
| MahaRERA registration | P52100022278 |
| Registered on | 09 Sep 2019 |
| Promoter-declared completion | 30 Mar 2022 |
| Current status | Certificate Signed |
| Against today | about 52 months past the declared date |
MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.
Across MahaRERA, Kolte-Patil is the promoter of record on 38 projects, of which 1 carries a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.
No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.
The promoter has declared 12 court cases on this project to MahaRERA. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your flat. This is declared by the promoter; there may be further cases not on the RERA record.
| Court | Case no. | Year | Status |
|---|---|---|---|
| Cjsd | Spl CS 2255/2009 | 2009 | The Matter Is Pending Adjudication And Is Currently Fixed For Framing Additional Issues |
| Cjjd | RCS 1487/2005 | 2005 | The Matter Is Pending Adjudication And Is Currently Fixed For Evidence |
| Cjjd | SPL CS 265/2013 | 2013 | The Matter Is Pending Adjudication And Is Pending At Evidence Stage |
| Cjsd | SPL CS 575/2015 | 2015 | Disposed Off |
| Cjsd Pune | Special civil suit 421/2016 | 2016 | Currently The Suit Is Pending For Withdrawal Or Dismissal |
| Supreme Court | SLP CC No 9463/2017 | 2017 | Disposed Off |
| Supreme Court | SLP CC No 9467/2017 | 2017 | Disposed Off |
| High Court | 11697/2017 | 2017 | Currently The Matter Is Pending For Admission |
| High Court | 11701/2017 | 2017 | Currently The Matter Is Pending For Admission |
| High Court | 11702/2017 | 2017 | Currently The Matter Is Pending For Admission |
| High Court | WPST 31252/2017 | 2017 | The Matter Is Yet To Come Up For Hearing Before Court Current Stage Is Pre Admission For Circulation |
| Cjjd | RCS 1689/2021 | 2021 | Currently The Matter Is Posted For Filing Of Written Statement |
Located at Hinjewadi, Survey no 74 hinjewadi-marunji-kasarsai road taluka mulshi, Mulshi, Pune, 411057. Per the filed land record, the plot is bounded to the north by Sector R17A Township Green and Township Boundary, to the south by Township Green and Township Boundary, to the east by 18 M wide Township Internal Road and to the west by 30 M wide R P ROad. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.
The nearest major job hub is ~4 km away — a manageable everyday commute to a major job hub.
| Landmark | Straight-line |
|---|---|
| Hinjewadi Rajiv Gandhi IT Park | 4 km |
| Baner–Balewadi belt | 9 km |
| Pune Junction / city centre | 19 km |
| Pune Int'l Airport (Lohegaon) | 22 km |
| Kharadi / EON IT Park | 25 km |
| Magarpatta / Hadapsar IT | 25 km |
Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.
🔒 The verdict & buyer playbook · Compliance report
The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.
🔒 Unit-by-unit guidance · Unit Guidance report
Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.
🔒 Full financial records — escrow, funding & the document catalog · Compliance report
The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.
Should you buy in Life Republic - Sector R 17 B - 17 B Avenue - Nora?
This page is the free MahaRERA filing summary. The full RERA Property Intelligence Report gives you the full regulatory standing, declared court litigation, buyer-complaint and adjudication history, quarterly-progress-report discipline, the builder's MahaRERA-wide track record, the building/tower breakdown, and the sanctioned layout plan. See a real one first:
Sample: Lodha Alibaug Plots → · browse all sample reports →
Compliance Report · ₹999
The regulator’s filing record, read · 1 working day
Scan with any UPI app to pay · quietlist@kotak
Unit Guidance Report · ₹2,999
Everything, down to which unit · 1 working day
Not useful to your decision? Full refund — no questions asked.
Scan with any UPI app to pay · quietlist@kotak
Paying from outside India? Pay $15 (Compliance) or $39 (Unit Guidance) via PayPal, or email hello@quietlist.in for a card invoice. Prefer to talk first, or have a portfolio to check? Same address. An information aid for your own due diligence, not legal or investment advice.
Free · Watch this project
We'll email you when this project's RERA record changes.
Kolte-Patil Integrated Townships Limited is the promoter on 12 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).
See every Kolte-Patil Integrated Townships Limited project & its RERA track record →
Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.
Last checked against the RERA register: 27 Jul 2026