MahaRERA Property Intelligence · Pune
P52100031799 · Hinjewadi · promoter Kolte-Patil
| MahaRERA registration | P52100031799 |
| Registered on | 12 Nov 2021 |
| Promoter-declared completion | 31 Oct 2025 |
| Current status | Certificate Signed |
| Against today | about 9 months past the declared date |
MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.
Across MahaRERA, Kolte-Patil is the promoter of record on 38 projects, of which 1 carries a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.
MahaRERA's cost filing puts construction at ~81.0% of the estimated project cost incurred as of the last certificate (₹45.39 Cr spent against a ₹56.06 Cr estimate). This financial % is the regulator's own proxy for how much is physically built — the closest public read on real progress, and one a brochure never shows. The declared completion date has already passed while the cost-incurred filing sits at ~81.0% — a wide gap between the promise and the money actually spent on site.
Cost-incurred % as last certified to MahaRERA; it can lag on-site reality between filings. Confirm the current stage and the latest Form 2 before you book.
Of 173 homes filed with MahaRERA, 172 are sold/booked and 1 remain available (~99% sold) — nearly sold out — little inventory left, so you're buying into an established buyer base. Buyers have committed ₹88.48 Cr in agreement value so far. Of that, ₹83.55 Cr (~94%) is already collected, ₹4.93 Cr receivable — a read on how far along these sales really are. This is the promoter's own reported inventory as at the last compliance filing; confirm current availability directly.
What buyers actually paid: across 172 registered agreements, the effective carpet rate is ₹7,853/sqft (typical range ₹7,623–₹8,435) — computed from the agreement values and carpet areas the promoter filed, not broker quotes. Compare your quote against this before negotiating.
The unsold units on the filing — if you're quoted a unit NOT on this list, ask why it shows as sold/booked on the RERA record:
| Floor | Unit | Carpet | Reckoner value |
|---|---|---|---|
| Floor 1 | LRR16M0106 | 637 sqft (59.2 sqm) | ₹45.02 Lakh |
No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing — still confirm your specific unit's status in the agreement.
The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+23 and 173 homes are registered across the project.
| Building | Wings | Floors | Homes | Declared completion |
|---|---|---|---|---|
| M | 1 | G+23 | 173 | - |
Unit mix on the filing: 173 residential.
37 complaints are on the MahaRERA record for this project, with orders passed in 6. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.
| Complaint no. | Filed | Parties | Status |
|---|---|---|---|
| CC12503704 | 17/10/2025 | Shrikesh Dattatray Salunkhe vs KOLTE-PATIL INTEGRATED TOWNSHIPS LIMITED | order passed |
| CC12503818 | 31/10/2025 | Sagar Saha vs KOLTE-PATIL INTEGRATED TOWNSHIPS LIMITED | order passed |
| CC12600257 | 14/01/2026 | Aditya Bapusaheb Shinde vs KOLTE-PATIL INTEGRATED TOWNSHIPS LIMITED | pending / no order on file |
| CC12504392 | 10/12/2025 | Gautam Gautam vs KOLTE-PATIL INTEGRATED TOWNSHIPS LIMITED | pending / no order on file |
| CC12504280 | 04/12/2025 | MOHIT KUMAR MUND vs KOLTE-PATIL INTEGRATED TOWNSHIPS LIMITED | order passed |
| CC12504309 | 05/12/2025 | Pritesh Raut vs KOLTE-PATIL INTEGRATED TOWNSHIPS LIMITED | pending / no order on file |
| CC12504302 | 05/12/2025 | Vinod Kumar Dubey vs KOLTE-PATIL INTEGRATED TOWNSHIPS LIMITED | pending / no order on file |
| CC12504324 | 06/12/2025 | VIVEK SURESH JADHAV vs KOLTE-PATIL INTEGRATED TOWNSHIPS LIMITED | pending / no order on file |
| CC12504321 | 06/12/2025 | Satyam Pradip Patil vs KOLTE-PATIL INTEGRATED TOWNSHIPS LIMITED | pending / no order on file |
| CC12504379 | 09/12/2025 | Sagar Pandurang Naik vs KOLTE-PATIL INTEGRATED TOWNSHIPS LIMITED | pending / no order on file |
| CC12504568 | 22/12/2025 | Sudhir Hingade vs KOLTE-PATIL INTEGRATED TOWNSHIPS LIMITED | pending / no order on file |
| CC12504406 | 11/12/2025 | Aniket Dnyaneshwar Dalvi vs KOLTE-PATIL INTEGRATED TOWNSHIPS LIMITED | pending / no order on file |
| CC12504446 | 13/12/2025 | Avadhoot Ravindra Bhosle vs KOLTE-PATIL INTEGRATED TOWNSHIPS LIMITED | pending / no order on file |
| CC12504441 | 13/12/2025 | Sunil Vrajlal Jadav vs KOLTE-PATIL INTEGRATED TOWNSHIPS LIMITED | pending / no order on file |
| CC12504449 | 13/12/2025 | Akshay Ashokrao Pokalwar vs KOLTE-PATIL INTEGRATED TOWNSHIPS LIMITED | pending / no order on file |
| CC12504650 | 28/12/2025 | Sourabh Suhas Potnis vs KOLTE-PATIL INTEGRATED TOWNSHIPS LIMITED | pending / no order on file |
| CC12604097 | 01/07/2026 | Raju Yadav vs KOLTE-PATIL INTEGRATED TOWNSHIPS LIMITED | pending / no order on file |
| CC12600047 | 03/01/2026 | Abhishek Ashok Jagnade vs KOLTE-PATIL INTEGRATED TOWNSHIPS LIMITED | order passed |
| CC12600217 | 12/01/2026 | Suresh Krushna Koparde vs KOLTE-PATIL INTEGRATED TOWNSHIPS LIMITED | pending / no order on file |
| CC12600643 | 04/02/2026 | Pavan Jagannathrao Gadewar vs KOLTE-PATIL INTEGRATED TOWNSHIPS LIMITED | order passed |
| CC12600853 | 15/02/2026 | Atul Vijaykumar Ganjewar vs KOLTE-PATIL INTEGRATED TOWNSHIPS LIMITED | order passed |
| CC12602040 | 07/04/2026 | Pramod Madhukar Nikumbh vs KOLTE-PATIL INTEGRATED TOWNSHIPS LIMITED | pending / no order on file |
| CC12602241 | 16/04/2026 | Rohini Balaso Shankardas vs KOLTE-PATIL INTEGRATED TOWNSHIPS LIMITED | pending / no order on file |
| CC12602543 | 01/05/2026 | Vijay Prabhakar Jadhav vs KOLTE-PATIL INTEGRATED TOWNSHIPS LIMITED | pending / no order on file |
| CC12603083 | 24/05/2026 | Geeta Chandrakant Zarkar vs KOLTE-PATIL INTEGRATED TOWNSHIPS LIMITED | pending / no order on file |
| CC12603854 | 22/06/2026 | Abhijeet Rajendra Kale vs KOLTE-PATIL INTEGRATED TOWNSHIPS LIMITED | pending / no order on file |
| CC12604206 | 05/07/2026 | Pankaj Jagatram Bhakre vs KOLTE-PATIL INTEGRATED TOWNSHIPS LIMITED | pending / no order on file |
| CC12604015 | 28/06/2026 | Sachin Gorakhnath Nale vs KOLTE-PATIL INTEGRATED TOWNSHIPS LIMITED | pending / no order on file |
| CC12603949 | 25/06/2026 | SHUBHAM BALAJI NAYAB vs KOLTE-PATIL INTEGRATED TOWNSHIPS LIMITED | pending / no order on file |
| CC12603911 | 24/06/2026 | Viliyam Pavalu Souz vs KOLTE-PATIL INTEGRATED TOWNSHIPS LIMITED | pending / no order on file |
| CC12603954 | 25/06/2026 | Ashutosh Maruti Khot vs KOLTE-PATIL INTEGRATED TOWNSHIPS LIMITED | pending / no order on file |
| CC12604016 | 28/06/2026 | Abhijit Jagdish Awachat vs KOLTE-PATIL INTEGRATED TOWNSHIPS LIMITED | pending / no order on file |
| CC12604002 | 27/06/2026 | Karan Madansing Bahure vs KOLTE-PATIL INTEGRATED TOWNSHIPS LIMITED | pending / no order on file |
| CC12604005 | 27/06/2026 | Jasmin chimanbhai Patel vs KOLTE-PATIL INTEGRATED TOWNSHIPS LIMITED | pending / no order on file |
| CC12604092 | 30/06/2026 | nikita Pandey vs KOLTE-PATIL INTEGRATED TOWNSHIPS LIMITED | pending / no order on file |
| CC12604180 | 04/07/2026 | Vandana Abhinav Joshi vs KOLTE-PATIL INTEGRATED TOWNSHIPS LIMITED | pending / no order on file |
| CC12604218 | 05/07/2026 | Pavan Keshav Mahajan vs KOLTE-PATIL INTEGRATED TOWNSHIPS LIMITED | pending / no order on file |
The promoter has declared 14 court cases on this project to MahaRERA. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your flat. This is declared by the promoter; there may be further cases not on the RERA record.
| Court | Case no. | Year | Status |
|---|---|---|---|
| Cjjd | SPL CS No 265/2013 | 2013 | The Matter Is Pending Adjudication And Is Pending At Evidence Stage |
| Cjjd | RCS No 1487/2005 | 2005 | The Matter Is Pending Adjudication And Is Currently Fixed For Evidence |
| Cjsd | SPL CS 2255/2009 | 2009 | The Matter Is Pending Adjudication And Is Currently Fixed For Framing Additional Issues |
| Cjsd | SPL C S 575/2015 | 2015 | Disposed Off |
| Supreme Court | S L P C CC No 9467/2017 | 2017 | Disposed Off |
| Supreme Court | S L P CC No 9463/2017 | 2017 | Disposed Off |
| Cjsd | 421/2016 | 2016 | Currently The Suit Is Pending For Withdrawal Or Dismissal |
| High Court | Writ Petition No 11697/2017 | 2017 | Disposed Off |
| High Court | Writ Petition No 11701/2017 | 2017 | Disposed Off |
| High Court | Writ Petition No 11702/2017 | 2017 | Disposed Off |
| High Court | WPST 31252/2017 | 2017 | The Matter Is Yet To Come Up For Hearing Before Court Current Stage Is Pre Admission For Circulation |
| Cjjd | RCS 1689/2021 | 2021 | Currently The Matter Is Posted For Filing Of Written Statement |
| Cjsd Pune | Civil MA 372/2022 | 2022 | Appearance And Filing Of Say |
| Bombay High Court | 7264 | 2022 | Admission |
Located at Hinjewadi, Hinjewadi, Mulshi, Pune, 411057. Per the filed land record, the plot is bounded to the north by Township boundary S No 52 part 53 part 54 part, to the south by 18 meter wide RP road, to the east by Township boundary S no 91 part PCMC Punawale and to the west by Township boundary. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.
The nearest major job hub is ~4 km away — a manageable everyday commute to a major job hub.
| Landmark | Straight-line |
|---|---|
| Hinjewadi Rajiv Gandhi IT Park | 4 km |
| Baner–Balewadi belt | 9 km |
| Pune Junction / city centre | 19 km |
| Pune Int'l Airport (Lohegaon) | 21 km |
| Kharadi / EON IT Park | 24 km |
| Magarpatta / Hadapsar IT | 25 km |
Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.
🔒 The verdict & buyer playbook · Compliance report
The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.
🔒 Unit-by-unit guidance · Unit Guidance report
Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.
🔒 Full financial records — escrow, funding & the document catalog · Compliance report
The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.
Should you buy in Life Republic Sector R16- 16th Avenue- Arezo- M Building?
This page is the free MahaRERA filing summary. The full RERA Property Intelligence Report gives you the full regulatory standing, declared court litigation, buyer-complaint and adjudication history, quarterly-progress-report discipline, the builder's MahaRERA-wide track record, the building/tower breakdown, and the sanctioned layout plan. See a real one first:
Sample: Lodha Kandivali – Tower 2 → · browse all sample reports →
Compliance Report · ₹999
The regulator’s filing record, read · 1 working day
Scan with any UPI app to pay · quietlist@kotak
Unit Guidance Report · ₹2,999
Everything, down to which unit · 1 working day
Not useful to your decision? Full refund — no questions asked.
Scan with any UPI app to pay · quietlist@kotak
Paying from outside India? Pay $15 (Compliance) or $39 (Unit Guidance) via PayPal, or email hello@quietlist.in for a card invoice. Prefer to talk first, or have a portfolio to check? Same address. An information aid for your own due diligence, not legal or investment advice.
Free · Watch this project
We'll email you when this project's RERA record changes.
Kolte-Patil Integrated Townships Limited is the promoter on 12 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).
See every Kolte-Patil Integrated Townships Limited project & its RERA track record →
Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.
Last checked against the RERA register: 27 Jul 2026